Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 133.00 |
Borrower/Recipient | 201.32 |
P066955
Closed
Guangming Yan
N/A
January 21, 2003
(as of board presentation)
January 29, 2004
November 1, 2004
US$ 334.32 million
N/A
2004
US$ 133.00 million
A
Not Applicable
June 30, 2011
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 133.00 |
Borrower/Recipient | 201.32 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 133.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 133.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 334.32 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 15, 2015 | IBRD-47240 | Loan Repay | 4,311,203.50 |
Apr 15, 2014 | IBRD-47240 | Int Charges | 300,501.80 |
Apr 15, 2014 | IBRD-47240 | Loan Repay | 4,206,780.00 |
Oct 15, 2014 | IBRD-47240 | Int Charges | 270,256.16 |
Oct 15, 2014 | IBRD-47240 | Loan Repay | 4,241,588.00 |
Oct 15, 2013 | IBRD-47240 | Int Charges | 350,917.53 |
Oct 15, 2013 | IBRD-47240 | Loan Repay | 4,176,944.80 |
Jan 29, 2004 | IBRD-47240 | Loan Commitment | 133,000,000.00 |
Oct 15, 2023 | IBRD-47240 | Int Charges | 7,763.32 |
Oct 15, 2023 | IBRD-47240 | Int Charges | 288,670.97 |
Oct 15, 2023 | IBRD-47240 | Loan Repay | 4,902,937.50 |
Apr 15, 2024 | IBRD-47240 | Loan Repay | 4,942,718.00 |
Apr 15, 2024 | IBRD-47240 | Int Charges | 157,912.34 |
Apr 15, 2024 | IBRD-47240 | Int Charges | 3,414.99 |
Oct 15, 2022 | IBRD-47240 | Int Charges | 247,882.10 |
Oct 15, 2022 | IBRD-47240 | Loan Repay | 4,823,376.50 |
Apr 15, 2023 | IBRD-47240 | Int Charges | 347,743.03 |
Apr 15, 2023 | IBRD-47240 | Loan Repay | 4,863,157.00 |
Apr 15, 2023 | IBRD-47240 | Int Charges | 19,976.65 |
Apr 15, 2021 | IBRD-47240 | Loan Repay | 4,709,008.00 |
Apr 15, 2021 | IBRD-47240 | Int Charges | 126,350.74 |
Oct 15, 2021 | IBRD-47240 | Int Charges | 109,331.23 |
Oct 15, 2021 | IBRD-47240 | Loan Repay | 4,748,788.50 |
Apr 15, 2022 | IBRD-47240 | Loan Repay | 4,783,596.00 |
Apr 15, 2022 | IBRD-47240 | Int Charges | 83,592.27 |
Apr 15, 2020 | IBRD-47240 | Int Charges | 538,680.75 |
Apr 15, 2020 | IBRD-47240 | Loan Repay | 4,634,419.50 |
Oct 15, 2020 | IBRD-47240 | Int Charges | 334,164.12 |
Oct 15, 2020 | IBRD-47240 | Loan Repay | 4,669,227.50 |
Apr 15, 2019 | IBRD-47240 | Loan Repay | 4,559,831.50 |
Apr 15, 2019 | IBRD-47240 | Int Charges | 823,868.00 |
Oct 15, 2019 | IBRD-47240 | Loan Repay | 4,594,639.00 |
Oct 15, 2019 | IBRD-47240 | Int Charges | 756,075.80 |
Oct 15, 2018 | IBRD-47240 | Int Charges | 848,229.25 |
Oct 15, 2018 | IBRD-47240 | Loan Repay | 4,525,023.50 |
Apr 15, 2017 | IBRD-47240 | Int Charges | 588,362.10 |
Apr 15, 2017 | IBRD-47240 | Loan Repay | 4,415,627.00 |
Oct 15, 2017 | IBRD-47240 | Int Charges | 614,442.90 |
Oct 15, 2017 | IBRD-47240 | Loan Repay | 4,450,435.00 |
Apr 15, 2018 | IBRD-47240 | Loan Repay | 4,485,243.00 |
Apr 15, 2018 | IBRD-47240 | Int Charges | 3,339.36 |
Apr 15, 2018 | IBRD-47240 | Int Charges | 613,032.06 |
Apr 15, 2016 | IBRD-47240 | Int Charges | 344,639.75 |
Apr 15, 2016 | IBRD-47240 | Loan Repay | 4,346,011.50 |
Oct 15, 2016 | IBRD-47240 | Int Charges | 477,101.10 |
Oct 15, 2016 | IBRD-47240 | Loan Repay | 4,380,819.50 |
Apr 15, 2015 | IBRD-47240 | Int Charges | 269,601.16 |
Apr 15, 2015 | IBRD-47240 | Loan Repay | 4,276,395.50 |
Oct 15, 2015 | IBRD-47240 | Int Charges | 308,541.20 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2011-05-26 |
Financial Management | Satisfactory | 2011-05-26 |
Monitoring and Evaluation | Satisfactory | 2011-05-26 |
Project Management | Highly Satisfactory | 2011-05-26 |
Overall Implementation Progress (IP) | Satisfactory | 2011-05-26 |
Procurement | Satisfactory | 2011-05-26 |
Counterpart Funding | Highly Satisfactory | 2011-05-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-26-2011 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 05-01-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Ningbo wastewater collection and treatment (in core urban area) (%) | Value | 41 | 81 | 80 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Hangzhou solid waste collection and disposal (in core urban area) (%) | Value | 94 | 100 | 90 |
Date | January 31, 2003 | December 31, 2009 | January 31, 2010 | |
Comment |
Visitors satisfied with the accessibility of Yue Kingdom area | Value | 40.6 | N/A | 65 |
Date | June 1, 2008 | December 31, 2009 | December 31, 2010 | |
Comment |
Visitors satisfied with environmental cleanliness of Yue Kindgom area | Value | 44.2 | N/A | 65 |
Date | June 1, 2008 | December 31, 2009 | December 31, 2010 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Wastewater Treatment Capacity in Ningbo City - Jiangdongnan WWTP (m3/dx1000) | Value | 0 | 160 | 160 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Wastewater TCN City - Zhenhai WWTP (m3/dx1000) | Value | 44.00 | 76.00 | 74.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Wastewater TCN City - Jiangnan WWTP (m3/dx1000) | Value | 0.00 | 0.00 | 100.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Jiangdongnan Secondary Sewer | Value | 11.40 | 55.30 | 55.30 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment | Not available |
Zhenhai Secondary Sewer | Value | 0.00 | 23.20 | 23.20 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment | Not available |
Jiangnan Secondary Sewer | Value | 0.00 | 20.00 | 45.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Wastewater tariff in Ningbo City (average) (Y/m3) | Value | 0.10 | 1.15 | 1.20 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment | Data for 2010 |
Cicheng Housing Renovation and Upgrading | Value | 0.95 | 2.90 | 3.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Wastewater Collection and Treatment in Cicheng Old Town (%) | Value | 0.00 | 35.00 | 50.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Wastewater Collection and Treatment in Dongqian Lake Catchment Area (%) | Value | 0.00 | 65.00 | 70.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Dongqian Lake Water Quality | Value | V | IV | IV |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Hangzhou - Solid Waste Landfilled (million tons/year) | Value | 0.00 | 3.05 | 4.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment | Not available |
Solid Waste Tipping Fee (Y/ton) | Value | 0.00 | 59.54 | 59.54 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment | Not available |
Shaoxing Housing Renovation and Upgrading | Value | 20.40 | 102.00 | 102.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment | Not available |
Shaoxing Wastewater Treatment Capacity (m3/dx1000) | Value | 300.00 | 750.00 | 600.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Shaoxing Wastewater Collection and Treatment in core city of (%) | Value | 50.00 | 84.00 | 85.00 |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |
Shaoxing Water Quality in Canals | Value | V | IV | IV |
Date | December 31, 2003 | December 31, 2009 | December 31, 2010 | |
Comment |