Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.30 |
Foreign Private Commercial Sources (unidentified) | 6.00 |
Borrower/Recipient | 2.70 |
P068133
Closed
Mustapha Benmaamar
N/A
May 23, 2003
(as of board presentation)
June 13, 2006
September 15, 2006
US$ 17.00 million
N/A
2006
US$ 8.30 million
C
Not Applicable
May 15, 2013
BANK APPROVED
September 6, 2017
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.30 |
Foreign Private Commercial Sources (unidentified) | 6.00 |
Borrower/Recipient | 2.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.30 |
Total Project Cost** | 17.00 |
Name | Review | Date |
---|---|---|
Summary Global Objective Rating | Moderately Satisfactory | 2013-01-30 |
Procurement | Satisfactory | 2013-01-30 |
Financial Management | Moderately Satisfactory | 2013-01-30 |
Project Management | Satisfactory | 2013-01-30 |
Counterpart Funding | Satisfactory | 2013-01-30 |
Monitoring and Evaluation | Satisfactory | 2013-01-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-01-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-15-2014 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 10-01-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
At least 160 large oil tankers and container ships that regularly navigate the Straits begin using the newly produced ENCs with supplemental ENRM info covering the area of the project | Value | No Activity | Vessels are equipped but charts not yet produced. | Well-functioning ENCs with ENRM supplemental infor |
Date | June 30, 2006 | April 30, 2010 | June 30, 2012 | |
Comment |
Sand wave model for the Straits fully integrated into the MEH system | Value | No Activity | Not yet done | Sand wave model for the Straits produced, tested a |
Date | June 30, 2006 | April 30, 2010 | June 30, 2012 | |
Comment | The model can only be finalized after the survey is completed. |
Evaluation of potential economic, financial and environmental costs/benefits and legal feasibility of MEH system, based on performance of the demonstration, approved by key stakeholders | Value | No Activity | This activity is replace d by a user survey follow | Agreed stakeholder decision on the evaluation resl |
Date | June 30, 2006 | March 15, 2012 | June 30, 2012 | |
Comment | This can only be done after the MEH system is operational. |
Development and evaluation of a demonstration MEH system for the most congested 300 kilometer section of the Straits of Malacca andSingapore are well coordinated, managed and technically supported. | Value | No activity | Survey completed, data center established and samp | The pilot MEH system is 100% established and funct |
Date | June 30, 2006 | March 15, 2012 | June 30, 2012 | |
Comment | Electronic navigation charts (ENC) and data center still required to make MEH pilot system fully established and functional. |
The littoral states and commercial shipping users of the Straits jointly decide whether or not to develop a full-scale MEH for the entire Straits based on evaluation of the demonstration project | Value | No activity | Not yet done. | Agreed stakeholder decision on whether to continue |
Date | June 30, 2006 | April 30, 2010 | June 30, 2012 | |
Comment | Decision on scaling up will not be taken until establishment of functioning demonstration MEH. |