Abstract*

The Participatory Management of Protected Areas Project for Peru's development objectives are: i) insure biodiversity conservation by increasing the involvement of civil society institutions and the private sector in planning and sustainable management of at least five protected areas (PA) of the Peruvian System of Natural Protected Areas (SINANPE), and one PA to be created during project implementation; and ii) obtain sustainability for the financing...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The projects development objectives are: (i) to ensure biodiversity conservation by increasing the involvement of civil society institutions and the private sector in the planning and sustainable management of five protected areas (PAs) of the Peruvian System of Natural Protected Areas (SINANPE); (ii) creation of one PA during project implementation; and (iii) to obtain financial sustainability for the financing of recurrent costs in SINANPE (National System of Protected Areas).The global objective of the project is to contribute to the conservation of biodiversity of global importance in Peru.

Key Details

Project Details

  • P068250

  • Closed

  • Gabriela Arcos

  • N/A

  • Peru

  • March 27, 2001

  • (as of board presentation)

    March 13, 2003

  • April 18, 2003

  • US$ 28.32 million

  • B

  • Not Applicable

  • December 31, 2010

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
FINLAND, Govt. of (Except for Min. for Foreign Affairs) 2.50
Global Environment Facility (GEF) 14.80
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. 4.44
Non-Government Organization (NGO) of Borrowing Country 1.00
Local Farmer Organizations 0.53
Borrower/Recipient 2.96
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 6.58

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 28.32
Total Project Cost** 32.81

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2010-12-16
Procurement Highly Satisfactory 2010-12-16
Project Management Satisfactory 2010-12-16
Summary Global Objective Rating Satisfactory 2010-12-16
Financial Management Satisfactory 2010-12-16
Monitoring and Evaluation Satisfactory 2010-12-16
Overall Implementation Progress (IP) Satisfactory 2010-12-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2011
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceModerately Satisfactory
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-11-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityUnsatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • PROFONANPE and INRENA's internal institutional capacity is strenghtened.ValueINRENA's current capacity weak and has limited expCompleted. Specialized technical training providedThe PA Service capacity in MINAMB enhanced. Tech.
    DateApril 19, 2004November 11, 2010October 14, 2009
    Comment
  • The ground work is developed with key stakeholders for the implementation of co-management agreements for protected areas (including legal and procurement documents)ValueCMA's have never been developed in Peru's PAs.Completed. At least 27 steps (legal, institutionalFurther out-reach and dissemination of the CMAs ha
    DateApril 19, 2004November 11, 2010December 8, 2008
    Comment
  • Increase of PROFONPANE endowment fund and capture of additional funds over life of projectValueProject began with an initial contribution to endoThis indicator was met in 2006 as follows: (i) US$This indicator has been fulfilled.
    DateApril 19, 2004April 28, 2010December 29, 2006
    Comment
  • Increased participation of civil society, private sector and key stakeholders in management of PAs.ValueThe five selected PA's for the project have littleIndicator achieved since: (i) 5 PA mgt. committeesPAMCs estlablished and/or strenthened in 5 PAs, an
    DateApril 19, 2004April 28, 2010October 14, 2009
    Comment
  • Strengthen the awareness of key stakeholders both in government, civil society and in the protected areas regarding co-management agreements.ValueLittle knowledge or interest among key stakeholderFully achieved: 5 PAMCs created and strengthened wThis indicator has been 90% achived since key stak
    DateApril 30, 2004April 28, 2010October 14, 2009
    Comment
  • Implementation of co-managmeent agreements in at least three protected areas.ValueThe 5 selected PA of the project face low capacity3 CMAs have been signed and will be completed by NAt least 3 co-managment agreements will be signed
    DateApril 19, 2004November 11, 2010August 27, 2008
    Comment
  • Implementation of Economic Sust. Activities Program (PAES) in selected PAs of the project.ValueCommunities carry out depredatory activitivies in The Economic Sust. Activities Program (PAES) has bThe PAES will continue to be implemented and will
    DateApril 29, 2004November 11, 2010October 14, 2009
    Comment
  • Development of the master plans (MP) for Protected AreasValueThe project's 5 PA need updated Master Plans(MP) tIndicator has been met by 100%: 5 management plansThe MP for the 5 PAs of the project updated to gui
    DateApril 19, 2004November 11, 2010October 14, 2009
    Comment
  • Development of the Sustainable Financial Plan for the National System of Protected AreasValueThe National Protected Areas System lacks a sustaiCompleted and approved by the National Service of It is expected that the sustainable financial stra
    DateApril 19, 2004November 11, 2010August 25, 2008
    Comment
  • The Rector Plan (plan director) for the SINANPE needs to be developed.ValueCurrently the SINANPE lacks a rector plan to guideCompleted and approved by the National Service of Draft PD ready for final presentation by August 20
    DateApril 19, 2004November 11, 2010August 25, 2008
    Comment