Financier | Commitments |
---|---|
IDA Credit | 70.00 |
P069569
Closed
Emmanuel Pinto Moreira
N/A
November 20, 2001
(as of board presentation)
November 20, 2001
November 30, 2001
US$ 70.00 million
N/A
2002
US$ 70.00 million
N/A
Not Applicable
June 30, 2003
BANK APPROVED
March 6, 2024
Financier | Commitments |
---|---|
IDA Credit | 70.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 70.00 |
IBRD + IDA Commitment | 70.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 70.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 20, 2001 | IDA-35760 | Loan Commitment | 70,000,000.00 |
INDICATOR | ICR REVIEW: 02-26-2004 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Not Rated | N/a |