The Social Welfare Development Project (SWDP) will strengthen the quality, targeting and administration of social benefits and services to those most in need in Croatia. The SWDP is a Specific Investment Loan with three components. The first, improving social services delivery will develop a sustainable spectrum of social programs across prevention, service delivery, and client re-integration into the community. It will have two sub-components: 'programming...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Social Welfare Development Project will strengthen the quality of social services and will improve administration, planning and policy making of the social welfare system

Key Details

Project Details

  • P069937

  • Closed

  • Ivan Drabek

  • N/A

  • Croatia

  • April 29, 2002

  • (as of board presentation)

    June 14, 2005

  • December 21, 2001

  • US$ 42.00 million

  • B

  • Not Applicable

  • March 31, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 40.00
Borrower/Recipient 18.30
SWEDEN: Swedish Intl. Dev. Cooperation Agency (SIDA) 2.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.00
IDA Commitment N/A
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount 2.00
Total Project Cost** 60.30

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 14, 2005 IBRD-73070 Loan Commitment 40,000,000.00
Nov 15, 2017 IBRD-73070 Loan Repay 1,828,903.80
May 15, 2018 IBRD-73070 Loan Repay 1,839,864.50
May 15, 2019 IBRD-73070 Loan Repay 1,728,404.20
Nov 15, 2019 IBRD-73070 Loan Repay 1,703,163.60
May 15, 2020 IBRD-73070 Loan Repay 1,668,737.50
Nov 15, 2014 IBRD-73070 Int Charges 75,417.37
Nov 15, 2014 IBRD-73070 Loan Repay 1,921,298.20
Nov 15, 2013 IBRD-73070 Loan Repay 2,076,138.40
Nov 15, 2013 IBRD-73070 Int Charges 66,851.66
May 15, 2014 IBRD-73070 Int Charges 70,281.90
May 15, 2014 IBRD-73070 Loan Repay 2,108,403.20
May 15, 2015 IBRD-73070 Int Charges 38,794.51
May 15, 2015 IBRD-73070 Loan Repay 1,753,645.00
Nov 15, 2015 IBRD-73070 Int Charges 25,539.94
Nov 15, 2015 IBRD-73070 Loan Repay 1,665,650.10
May 15, 2016 IBRD-73070 Loan Repay 1,751,483.60
May 15, 2016 IBRD-73070 Int Charges 18,329.27
Nov 15, 2016 IBRD-73070 Int Charges 6,115.99
Nov 15, 2016 IBRD-73070 Loan Repay 1,661,945.00
May 15, 2017 IBRD-73070 Int Charges 2,383.98
May 15, 2017 IBRD-73070 Loan Repay 1,693,437.90
Nov 15, 2018 IBRD-73070 Loan Repay 1,746,543.60

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2011-05-01
Progress towards achievement of PDO Satisfactory 2011-05-01
Counterpart Funding Satisfactory 2011-05-01
Financial Management Satisfactory 2011-05-01
Monitoring and Evaluation Satisfactory 2011-05-01
Overall Implementation Progress (IP) Satisfactory 2011-05-01
Project Management Satisfactory 2011-05-01

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-30-2011
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-10-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • reduction by at least 15% of social worker time spent on social benefits administrationValueIn 2005 it was estimated that social workers spentTo be measured after the introduction of the MIS aSocial workers spend up to 55% of their time on ad
    DateDecember 30, 2005March 21, 2011March 31, 2011
    CommentIn 2007 social workers in three pilot counties spent 34% of their time on social benefit administration rather than on providingservices to the clients. It is expected this share will be significantly reduced with the introduction of MIS and the front- andback-office work model in the centers for social welfare
  • Increased number of beneficiaries receiving alternative community-based services generated by ILPValue0.008620.006840.00
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Increased share of residential institutions for children and adults meet public health standardsValue30.0073.0073.00
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Increased number of clients receiving community-based home care servicesValue3113.004350.004300.00
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Development and operationalization of the new tools for policy planning and system development such as Social Planning, Methodological Centers and Quality StandardsValueNo tools developed.All tools have been developed. Work on rolling outAll tools applied either in pilot counties or nati
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Creation of Department for Social Welfare Development as new organizational structure of the Social Welfare Directorate of MHSW to carry out reform agenda and monitor progressValueNo Department for Social Welfare Development in plDepartment for Social Welfare Development operatioDepartment for Social Welfare operational
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • New social planning methodology developed and piloted in three pilot countiesValueNo social planning methodology in placeNew social planning methodology developed and legiNew social planning methodology implemented
    DateDecember 30, 2005March 21, 2011March 31, 2011
    CommentIn addition to ten county masterplans that have been developed so far, remaining 11 counties should develop their master-plans byend-2011.
  • Concept of methodological centers (MCs) developed and MCs implementedValueNo MC concept in placeWork on MCs postponedMCs operational
    DateDecember 30, 2005March 21, 2011March 31, 2011
    CommentAfter a thorough review of the experience with 3 MCs, the Ministry decided to postpone further work on MCs and revise the MCselection criteria after implementing new quality standards.
  • Number of ILP (Innovation and Learning Program) projects implementedValue0.0034.0034.00
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Number of persons included in prevention programs under ILPValue0.003050.002781.00
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Quality standards for social care developed and implementedValueNo quality standards in placeNew quality standards developed, approved and fullNew quality standards developed, approved and impl
    DateDecember 30, 2005March 21, 2011March 31, 2011
    CommentWork on expanding the quality standards to NGOs, foster families and other, non-state residential institutions has commenced inearly 2011.
  • One-stop-shop model for CSWs developedValueNo one-stop-shop model in placeOne-stop-shop model has been designed, adopted andOne-stop-shop model adopted
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Management Information System designed and implementedValueMIS not in placeRevision of MIS software finalized, user data entrMIS operational
    DateDecember 30, 2005March 21, 2011March 31, 2011
    CommentMIS is not fully operational as there has been delay in the procurement of IT equipment necessary for full operation of the newMIS. Furthermore, changes to the software had to be introduced after its initial piloting. MIS is expected to become fullyoperational in the whole country by January 1, 2012.
  • Data exchange system that will reduce application burden on clients and social workers establishedValueNo data exchange system in placeData exchange model and software have been developData exchange system with the key agencies in plac
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Number of public social welfare homes for children and adults that improved hygienic standardsValue0.0045.0045.00
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment
  • Number of newly constructed and upgraded centers for social welfare (CSWs)Value0.0014.0014.00
    DateDecember 30, 2005March 21, 2011March 31, 2011
    Comment