Eritrea Education Sector Investment Project

Abstract*

The Education Sector Investment Project in Eritrea, seeks a more equitable, and increased enrollment in basic education, and an enhanced quality in basic, and secondary education. The project components are as follows: 1) increasing equitable enrollment in basic education, will be achieved by improving access to education, through a low-cost construction of classrooms, and facilities at elementary, and middle schools. By identifying appropriate locations...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Key Details

Project Details

  • P070272

  • Closed

  • Susan E. Hirshberg

  • N/A

  • Eritrea

  • March 24, 2003

  • (as of board presentation)

    June 19, 2003

  • September 23, 2003

  • US$ 89.96 million

  • B

  • Not Applicable

  • August 31, 2011

  • BANK APPROVED

  • December 20, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 45.00
Borrower/Recipient 14.50
EC: European Commission 44.96

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 45.00
IBRD + IDA Commitment 45.00
Lending Instrument
Grant Amount 44.96
Total Project Cost** 104.46

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 19, 2003 IDA-37940 Loan Commitment 45,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2011-08-28
Counterpart Funding Satisfactory 2011-08-28
Project Management Moderately Satisfactory 2011-08-28
Financial Management Satisfactory 2011-08-28
Procurement Satisfactory 2011-08-28
Monitoring and Evaluation Moderately Unsatisfactory 2011-08-28
Overall Implementation Progress (IP) Moderately Unsatisfactory 2011-08-28

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-29-2012
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-29-2013PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Student enrollment at elementary school levelValue298,691 (SY 2002/03)300,129 (SY 2008/09)286,021 (SY 2009/10)464,000 (SY 2010/11)
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentThe team recently noticed that the Baseline Value for elementary enrollment was changed in the November 2009 ISR to reflect thefindings of the Project Restructuring team in 2007 (which they based on 2005/06 data). This final ISR now reflects the originalinformation. The ICR team will look at the broader enrollment trends.Preliminary numbers for 2010/11 indicate an increase of approximately 25,000 students at the elementary level.This indicator ofaccess agreed during restructuring of the project has been defined in terms of an increase in absolute numbers of students. It hasbecome difficult to measure absolute targets given that the population of Eritrea has declined in the recent past,including for theage groups 7-11. It is expected that the population of the age group 7-11 (elementary) will be about 436,000, which is lower thanthe original target enrollment of 464,000.The data on which the end target was based at appraisal and MTR/Restructuring needs to be evaluated.
  • Student enrollment at middle school levelValue87,019 (SY 2002/03)151,131 (SY 2008/09)151,702 (SY 2009/10)189,000 (SY 2010/11)
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentPreliminary numbers for SY 2010/11 are 154,598Although the numeric target was not met, the increases at this level are significant.
  • Female share of total enrollment in elementary, middle and secondary schoolsValue(SY 2002/03): 44% (elementary); 42% (middle); 36% SY 2008/09: 45% (elementary); 42% (middle); 40% (s(SY 2010/11): 50% (elementary); 45% (middle); 40%
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentPreliminary SY 2010/11:Elementary 45%Middle 44%Secondary 43%
  • Percentage of Grade 3 and Grade 5 learners attaining the minimum mastery level in the Monitoring and Learning Achievement TestValue58% (Gr. 3); 32% (Gr. 5); (2001)Gr. 3 - Math 43.21Engl 30.01Mother Tongue 47.62% (Gr. 3); 37% (Gr. 5);
    DateSeptember 23, 2003July 1, 2011August 31, 2011
    CommentOne could say Gr 3 did not succeed and Gr 5 did achieve the objective, but the report from the technical expert implies this isnotnecessarily the case. The final workshop report states that "Lower performance relative to expectations... is likely the resultof the novelty of the curriculum, not an actual drop in skills." Therefore it is not possible to meaningfully measure the outcomeof MLAII compared to MLA I.
  • # Percentage of Grade 8 national examination pass rate increases from 71% in 2005/06 academic year to 76% in 2010/11 academic year.Value71.0074.7876.00
    DateJuly 20, 2007May 12, 2011August 31, 2011
    CommentSY 2008/09 pass rate: 76.17%The SY2008/09 pass rate achieved the target. Analysis is needed to understand the real meaning of a 1.22 percent decline.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • New and cost-effective school designs in placeValueno standard school designNew and cost-effective school designs approvedNew and cost-effective school designs approved
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentDesigns have been used in for all civil works activitiesAchieved
  • Classrooms built and/ or rehabilitated (number) (Note: Number includes classrooms constructed at the elementary, middle, and secondary levels)Value01,2891,190
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentCP1: 442; CP2: 114; NCB IDA: 100; NCB ECTF: 304; ICB: 329Target surpassed
  • Teachers trained in-service (number)(Note: Number of teachers trained/upgraded through fast-track or summer training programs)Value04,5222,500
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentPrevious figures only included training exclusively for elementary school teachers (2,761) trained through Summer Programs orFast-Track. However, IDA supported a larger number of teacher training (incl. combination of elementary, middle, secondary teachersas well as MOE Staff) through summer programs, totaling 4,522Target surpassed
  • Teachers trained in-service (number)(Note: Number of teachers trained/upgraded through open and distance learning)Value02,0802,080
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    Comment1st batch (580) completed w/IDA support of which 411 graduated; 2nd batch (1,500 - paid out of EC funds) of which 1,254 graduated
  • Percentage of subjects requiring revisions under the curriculum reform completes new materials developmentValue0100%
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentMaterials developed for grades 1-8. Grades 9-12 books finalized and being printed. On course to achieve 100%.Target achieved
  • New round of MLA testing prepared, implemented, and results analyzedValue0Completedresults analyzed
    DateSeptember 23, 2003July 1, 2011August 31, 2011
    CommentMLA II was administered in October 2008. Results have been analyzed and submitted to IDA in January 2010. MLA Specialist workingwith GOE team to further analyze data.Target achieved. More importantly, meaningful lessons learned through TA for future student assessment in Eritrea
  • Capacity assessment completedValuenoYesyes
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentCapacity Assessment study completed as part of the proposed 15 Policy Studies (see next indicator)
  • Number of policy studies completedValue01515
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentTarget met - included studies financed both by IDA and the separate EC program.No analysis of content and use of information available.
  • Number of MoE management staff trained and upgradedValue0220150
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentData obtained during this mission updated; 220 includes IDA-financed only of 127 staff being trained at EIT, 93 trained throughSummer Programs. However, there have been many more MOE staff trained by other sources of funds, including 209 MOE staff supportedby the EC to pursue either their postgraduate or undergraduate studies.Target surpassed
  • Evaluation of previous targeting programs completed and new interventions preparedValueNoYesYes
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentTarget metTarget met
  • Number of girls and other disadvantaged children covered by incentive schemesValueN/A (new intervention after restructuring)3,000 in 20092,334 in 20102,300
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    CommentTarget achieved.Target achieved.
  • Number of disadvantaged pre-school age children enrolled in ECD centersValuen/a (new intervention after restructuring)80,000
    DateSeptember 23, 2003May 12, 2011August 31, 2011
    Comment782 community-based ECD Centers financed by IDA.ICR will provide final enrollment data
  • Textbooks purchased (number)(Note: Values to be included after Dec. 2008 mission)Valuen/aGrade 7: 408,000 (reprints)Grade 8: 408,000 (repr4.95 million elementary books printed & delivered
    DateJanuary 30, 2009May 12, 2011August 31, 2011
    CommentThe value was corrected to reflect data obtained during the May/June 2010 mission. 1.1 million books were printed financed by IDA,additional books have been printed by Danida and the EC. Since then, IDA has financed the printing of an additional 2.8 millionbooks (at various stages of editing, layout or printing)Target achieved.