Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.00 |
Borrower/Recipient | 14.86 |
GLOBAL ENVIRONMENT - Associated IBRD Fund | 10.00 |
P070552
Closed
Michael Carroll
N/A
April 9, 2002
(as of board presentation)
May 21, 2002
August 27, 2002
US$ 32.86 million
N/A
2002
US$ 8.00 million
B
Not Applicable
January 31, 2009
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.00 |
Borrower/Recipient | 14.86 |
GLOBAL ENVIRONMENT - Associated IBRD Fund | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.00 |
Total Project Cost** | 32.86 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2009-08-30 |
Summary Global Objective Rating | Moderately Satisfactory | 2009-08-30 |
Monitoring and Evaluation | Satisfactory | 2009-08-30 |
Procurement | Satisfactory | 2009-08-30 |
Counterpart Funding | Moderately Satisfactory | 2009-08-30 |
Project Management | Satisfactory | 2009-08-30 |
Financial Management | Satisfactory | 2009-08-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2009-08-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-06-2009 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 04-13-2010 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |