Abstract*

The development objective of the Integrated Natural Resources and Biodiversity Management Project is to promote, particularly among groups of small and medium-sized fanners, the adoption of economically and environmentally viable integrated production systems, within a context of holistic ecosystem and natural resources management, while mainstreaming biodiversity. Likewise, the global environment objective seeks to promote increased understanding...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To promote, mainly among groups of small and medium-sized farmers, the adoption of economically and environmentally viable integrated production systems within a context of holistic ecosystem and natural resources management, while mainstreaming biodiversity.

Key Details

Project Details

  • P070653

  • Closed

  • Holger Kray

  • N/A

  • Uruguay

  • August 6, 2004

  • (as of board presentation)

    June 9, 2005

  • October 5, 2005

  • US$ 35.00 million

  • B

  • Not Applicable

  • August 31, 2012

  • BANK APPROVED

  • June 12, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 30.00
Local Sources of Borrowing Country 55.85
Global Environment Facility (GEF) 5.00
Borrower/Recipient 3.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 30.00
IDA Commitment N/A
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount 5.00
Total Project Cost** 93.85

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2016 IBRD-73050 Loan Repay 1,565,314.10
Oct 15, 2017 IBRD-73050 Int Charges 78,769.38
Oct 15, 2017 IBRD-73050 Loan Repay 1,565,314.10
Apr 15, 2017 IBRD-73050 Int Charges 83,641.45
Jun 9, 2005 IBRD-73050 Loan Commitment 30,000,000.00
Apr 15, 2014 IBRD-73050 Int Charges 62,752.46
Apr 15, 2018 IBRD-73050 Int Charges 477.39
Apr 15, 2018 IBRD-73050 Int Charges 70,425.02
Apr 15, 2018 IBRD-73050 Loan Repay 1,565,314.10
Oct 15, 2018 IBRD-73050 Loan Repay 1,565,314.10
Oct 15, 2018 IBRD-73050 Int Charges 86,882.23
Apr 15, 2020 IBRD-73050 Int Charges 17,737.33
Apr 15, 2020 IBRD-73050 Loan Repay 1,564,711.80
Oct 15, 2019 IBRD-73050 Int Charges 45,823.56
Oct 15, 2019 IBRD-73050 Loan Repay 1,565,314.10
Apr 15, 2019 IBRD-73050 Int Charges 68,601.54
Apr 15, 2019 IBRD-73050 Loan Repay 1,565,314.10
Oct 15, 2014 IBRD-73050 Int Charges 54,424.20
Oct 15, 2014 IBRD-73050 Loan Repay 1,565,314.10
Apr 15, 2017 IBRD-73050 Loan Repay 1,565,314.10
Apr 15, 2014 IBRD-73050 Loan Repay 1,565,314.10
Oct 15, 2013 IBRD-73050 Int Charges 16.99
Oct 15, 2013 IBRD-73050 Int Charges 76,845.66
Oct 15, 2013 IBRD-73050 Loan Repay 1,565,314.10
Apr 15, 2015 IBRD-73050 Int Charges 49,616.12
Apr 15, 2016 IBRD-73050 Int Charges 55,139.73
Apr 15, 2016 IBRD-73050 Loan Repay 1,565,314.10
Oct 15, 2015 IBRD-73050 Int Charges 52,514.26
Oct 15, 2015 IBRD-73050 Loan Repay 1,565,314.10
Apr 15, 2015 IBRD-73050 Loan Repay 1,565,314.10
Oct 15, 2016 IBRD-73050 Int Charges 73,201.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2012-09-06
Procurement Moderately Satisfactory 2012-09-06
Counterpart Funding Satisfactory 2012-09-06
Progress towards achievement of PDO Satisfactory 2012-09-06
Financial Management Satisfactory 2012-09-06
Monitoring and Evaluation Satisfactory 2012-09-06
Overall Low 2012-09-06
Overall Implementation Progress (IP) Satisfactory 2012-09-06

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 04-30-2013
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceModerately Satisfactory
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-22-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of proposals presented for integrated production systems at the farm level.Value06,4663,500
    DateDecember 5, 2005June 30, 2012August 31, 2012
    CommentTarget has been exceeded
  • Number of projects in which biodiversity is mainstreamed into their production system.Value01,5231,200
    DateDecember 5, 2005June 30, 2012August 31, 2012
    Comment
  • Ha. administered by small and medium producers in the management of biodiversityValue0379,873100,000
    DateDecember 5, 2007June 30, 2012August 31, 2011
    CommentIncludes pure biodiversity project, integrated projects and biodiversity FPES
  • Number of hectares of natural habitats including natural forests under restoration or management for conservation and production.Value018,9945,000
    DateDecember 5, 2005June 30, 2012August 31, 2012
    Comment5% of the target ha. figure of biodiversity (100,000 ha)
  • Number of proposals approvedValue0.005300.003000.00
    DateJune 29, 2007June 30, 2012August 31, 2011
    CommentNewly incorporated indicator after MTR.
  • Number of hectares incorporated to the integrated management of natural resources and biodiversity.Value0.0088188200.001000000.00
    DateAugust 31, 2009June 30, 2012August 31, 2012
    CommentThe final area covered by the project increased as the final round of subprojects was accounted.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Ha. that incorporate biodiversity/no of producersValue100,000ha./900379,873 ha, 1523 subprojects100,000ha./900
    DateDecember 5, 2005June 30, 2012August 31, 2012
    CommentThis indicator should be eliminated as it is already under PDO indicators individually
  • Number of expereinces published and disseminated in each of the country's eco-regions.Value104010
    DateDecember 5, 2005January 31, 2012August 31, 2012
    Commentthis indicator has been eliminated
  • Number and category of people trainedValue1,5006,4591,500
    DateDecember 5, 2005June 30, 2012August 31, 2012
    Comment
  • Activities in the management of water (Drought Alleviation Program)Value761740
    DateDecember 5, 2005June 30, 2012August 31, 2012
    Comment
  • Number of events and participants regarding soil and water conservation.Value112 events, 6,459 participants
    DateDecember 5, 2005June 30, 2012August 31, 2012
    Comment
  • Number of events (courses, sensibillization, SIG courses, workshops with rural teachers and field days in training of natural resource managementValue1,50050191,500
    DateDecember 5, 2005June 30, 2012August 31, 2011
    Comment
  • Ha. that incorporate biodiversity/no of producersValue100,000ha./900379,873 ha, 1523 subprojects100,000ha./900
    DateDecember 5, 2005June 30, 2012August 31, 2012
    CommentThis inidicator should be eliminated as its already under PDO indicators individually.
  • Number of expereinces published and disseminated in each of the country's eco-regions.Value10010
    DateDecember 5, 2005December 31, 2010August 31, 2011
    CommentThis indicator has been eliminated.