Financier | Commitments |
---|---|
Borrower/Recipient | 8.65 |
Local Communities | 9.46 |
International Bank for Reconstruction and Development | 20.00 |
P070950
Closed
Nathalie Weier Johnson
N/A
November 21, 2001
(as of board presentation)
June 1, 2004
December 21, 2004
US$ 38.11 million
N/A
2004
US$ 20.00 million
B
Not Applicable
June 30, 2012
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Borrower/Recipient | 8.65 |
Local Communities | 9.46 |
International Bank for Reconstruction and Development | 20.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 20.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 20.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 38.11 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2017 | IBRD-47410 | Loan Repay | 590,282.94 |
Nov 15, 2017 | IBRD-47410 | Loan Repay | 597,708.50 |
Nov 15, 2017 | IBRD-47410 | Int Charges | 47,204.49 |
Nov 15, 2018 | IBRD-47410 | Int Charges | 56,559.40 |
Nov 15, 2018 | IBRD-47410 | Loan Repay | 605,134.10 |
May 15, 2019 | IBRD-47410 | Int Charges | 52,196.66 |
May 15, 2019 | IBRD-47410 | Loan Repay | 612,559.75 |
May 15, 2018 | IBRD-47410 | Int Charges | 44,907.11 |
May 15, 2018 | IBRD-47410 | Loan Repay | 601,463.90 |
Nov 15, 2019 | IBRD-47410 | Int Charges | 39,288.20 |
Nov 15, 2019 | IBRD-47410 | Loan Repay | 616,315.06 |
May 15, 2020 | IBRD-47410 | Loan Repay | 619,985.30 |
May 15, 2020 | IBRD-47410 | Int Charges | 22,803.47 |
Nov 15, 2020 | IBRD-47410 | Int Charges | 7,466.96 |
Nov 15, 2020 | IBRD-47410 | Loan Repay | 627,410.94 |
May 15, 2021 | IBRD-47410 | Int Charges | 2,351.41 |
May 15, 2021 | IBRD-47410 | Loan Repay | 632,008.20 |
Jun 1, 2004 | IBRD-47410 | Loan Commitment | 20,000,000.00 |
Nov 15, 2014 | IBRD-47410 | Loan Repay | 568,006.10 |
Nov 15, 2014 | IBRD-47410 | Int Charges | 24,864.38 |
Nov 15, 2013 | IBRD-47410 | Int Charges | 325.66 |
Nov 15, 2013 | IBRD-47410 | Int Charges | 32,722.64 |
May 15, 2014 | IBRD-47410 | Int Charges | 27,905.01 |
May 15, 2014 | IBRD-47410 | Loan Repay | 564,335.94 |
Nov 15, 2013 | IBRD-47410 | Loan Repay | 556,910.30 |
Nov 15, 2015 | IBRD-47410 | Int Charges | 27,042.26 |
Nov 15, 2015 | IBRD-47410 | Loan Repay | 575,431.75 |
May 15, 2015 | IBRD-47410 | Int Charges | 24,375.22 |
May 15, 2015 | IBRD-47410 | Loan Repay | 571,761.50 |
May 15, 2016 | IBRD-47410 | Loan Repay | 582,857.30 |
May 15, 2016 | IBRD-47410 | Int Charges | 31,708.43 |
Nov 15, 2016 | IBRD-47410 | Int Charges | 39,527.48 |
Nov 15, 2016 | IBRD-47410 | Loan Repay | 586,612.70 |
May 15, 2017 | IBRD-47410 | Int Charges | 45,927.55 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2012-06-13 |
Procurement | Satisfactory | 2012-06-13 |
Project Management | Satisfactory | 2012-06-13 |
Financial Management | Satisfactory | 2012-06-13 |
Monitoring and Evaluation | Satisfactory | 2012-06-13 |
Counterpart Funding | Satisfactory | 2012-06-13 |
Overall Implementation Progress (IP) | Satisfactory | 2012-06-13 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-28-2012 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 10-28-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in vegetative cover in project microcatchments | Value | 0 | Increase by 20 percent above the baseline by proje | |
Date | December 21, 2004 | May 16, 2012 | June 30, 2012 | |
Comment |
Increase in soil fertility in project microcatchments | Value | 0 | Increase by 10 percent above the baseline by proje | |
Date | June 9, 2007 | May 16, 2012 | June 30, 2012 | |
Comment |
Increase in household incomes in participating microcatchment communities | Value | 0 | Increase by 10 percent above the baseline by proje | |
Date | June 9, 2007 | May 16, 2012 | June 30, 2012 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Microcatchment plans developed and fully implemented | Value | 0 | 28 microcatchment plans to be completed and under | |
Date | December 21, 2004 | May 16, 2012 | June 30, 2012 | |
Comment |
Training in support of organic farming and marketing of organic products provided | Value | 0 | Training programs in organic farming and marketing | |
Date | December 21, 2005 | May 16, 2012 | June 30, 2012 | |
Comment |
Adoption of environmental-friendly agricultural practices | Value | Virtually no farmers assumed to be using environme | Environmental-friendly agricultural practices have | |
Date | December 24, 2004 | May 16, 2012 | June 30, 2012 | |
Comment |
Development and adoption of packages of investments and practices for nutrient discharge reduction | Value | 0 | 65% of farmers with nutrient management problems i | |
Date | December 21, 2004 | May 16, 2012 | June 12, 2012 | |
Comment |
Water quality monitoring program developed and implemented | Value | No water quality monitoring program underway | Institutional and regulatory mechanisms in place s | |
Date | December 21, 2004 | May 16, 2012 | June 30, 2012 | |
Comment |
Development and promotion of a legal framework consistent with the EU Nitrates Directive for good agricultural practices based on on-farm trials, demonstrations, and trainings | Value | No legal framework in place. No demonstrations or | Turkish legislation with respect to nitrates pollu | |
Date | December 21, 2004 | May 16, 2012 | June 30, 2012 | |
Comment |
Adoption of environmental-friendly agricultural practices | Value | Virtually no farmers assumed to be using environme | Environmental-friendly agricultural practices have | |
Date | December 24, 2004 | May 16, 2012 | June 30, 2012 | |
Comment |
Agricultural pollution into the Black Sea is reduced in pilot MCs and efforts are underway to scale up these investments. | Value | No efforts in place in project MCs to reduce nutri | Replication strategy in place to set targets for f | |
Date | December 21, 2004 | May 16, 2012 | June 30, 2012 | |
Comment |
Water Quality monitoring program developed and implemented (CYGM) | Value | 0.00 | 83.00 | 0.00 |
Date | December 21, 2004 | May 16, 2012 | ||
Comment |