Financier | Commitments |
---|---|
IDA Credit | 33.00 |
P071259
Closed
Michael Webster
N/A
November 4, 2003
(as of board presentation)
October 5, 2006
March 22, 2007
US$ 33.00 million
N/A
2007
US$ 33.00 million
B
Not Applicable
June 30, 2013
BANK APPROVED
September 18, 2013
Financier | Commitments |
---|---|
IDA Credit | 33.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 33.00 |
IBRD + IDA Commitment | 33.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 33.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 22, 2021 | IDA-42330 | Int Charges | 6,822.05 |
Mar 22, 2021 | IDA-42330 | Int Charges | 6,822.05 |
Mar 22, 2021 | IDA-42330 | Loan Repay | 224,322.56 |
Aug 15, 2020 | IDA-42330 | Loan Repay | 4,587.55 |
Oct 7, 2020 | IDA-42330 | Loan Repay | 216,929.66 |
Oct 7, 2020 | IDA-42330 | Int Charges | 27.11 |
Oct 7, 2020 | IDA-42330 | Int Charges | 27.11 |
Oct 7, 2020 | IDA-42330 | Int Charges | 70,518.94 |
Oct 7, 2020 | IDA-42330 | Int Charges | 70,518.94 |
Oct 7, 2020 | IDA-45500 | Loan Repay | 71,672.58 |
Oct 7, 2020 | IDA-45500 | Int Charges | 8.96 |
Oct 7, 2020 | IDA-45500 | Int Charges | 8.96 |
Oct 7, 2020 | IDA-45500 | Int Charges | 24,647.75 |
Oct 7, 2020 | IDA-45500 | Int Charges | 24,647.75 |
Aug 15, 2020 | IDA-45500 | Loan Repay | 1,537.21 |
Feb 15, 2020 | IDA-42330 | Loan Repay | 4,446.79 |
Feb 15, 2020 | IDA-45500 | Loan Repay | 1,478.09 |
Feb 21, 2020 | IDA-42330 | Loan Repay | 209,434.66 |
Feb 21, 2020 | IDA-42330 | Int Charges | 80.21 |
Feb 21, 2020 | IDA-42330 | Int Charges | 80.21 |
Feb 21, 2020 | IDA-42330 | Int Charges | 75,387.32 |
Feb 21, 2020 | IDA-42330 | Int Charges | 75,387.32 |
Feb 21, 2020 | IDA-45500 | Loan Repay | 69,208.19 |
Feb 21, 2020 | IDA-45500 | Int Charges | 26.50 |
Feb 21, 2020 | IDA-45500 | Int Charges | 26.50 |
Feb 21, 2020 | IDA-45500 | Int Charges | 26,240.23 |
Feb 21, 2020 | IDA-45500 | Int Charges | 26,240.23 |
Mar 23, 2022 | IDA-45500 | Loan Repay | 70,600.62 |
Mar 23, 2022 | IDA-45500 | Int Charges | 44.31 |
Mar 23, 2022 | IDA-45500 | Int Charges | 44.31 |
Mar 23, 2022 | IDA-45500 | Int Charges | 25,478.33 |
Mar 23, 2022 | IDA-45500 | Int Charges | 25,478.33 |
Mar 23, 2022 | IDA-42330 | Loan Repay | 213,660.58 |
Mar 23, 2022 | IDA-42330 | Int Charges | 134.08 |
Mar 23, 2022 | IDA-42330 | Int Charges | 134.08 |
Mar 23, 2022 | IDA-42330 | Int Charges | 73,034.48 |
Mar 23, 2022 | IDA-42330 | Int Charges | 73,034.48 |
Feb 15, 2022 | IDA-42330 | Loan Repay | 2,782.12 |
Sep 15, 2021 | IDA-42330 | Loan Repay | 221,905.39 |
Sep 15, 2021 | IDA-42330 | Int Charges | 172.56 |
Sep 15, 2021 | IDA-42330 | Int Charges | 172.56 |
Sep 15, 2021 | IDA-42330 | Int Charges | 76,387.80 |
Sep 15, 2021 | IDA-42330 | Int Charges | 76,387.80 |
Sep 15, 2021 | IDA-45500 | Int Charges | 57.03 |
Sep 15, 2021 | IDA-45500 | Int Charges | 57.03 |
Feb 15, 2016 | IDA-42330 | Int Charges | 317.87 |
Feb 15, 2016 | IDA-42330 | Int Charges | 317.87 |
Feb 15, 2016 | IDA-42330 | Int Charges | 2,701.35 |
Feb 15, 2016 | IDA-42330 | Int Charges | 2,701.35 |
Feb 15, 2016 | IDA-42330 | Int Charges | 44.73 |
Feb 15, 2016 | IDA-42330 | Int Charges | 44.73 |
Feb 15, 2016 | IDA-45500 | Int Charges | 892.78 |
Feb 15, 2016 | IDA-45500 | Int Charges | 892.78 |
Feb 15, 2016 | IDA-45500 | Int Charges | 14.78 |
Feb 15, 2016 | IDA-45500 | Int Charges | 14.78 |
Apr 11, 2016 | IDA-42330 | Int Charges | 78,984.90 |
Apr 11, 2016 | IDA-42330 | Int Charges | 78,984.90 |
Apr 11, 2016 | IDA-45500 | Int Charges | 26,103.92 |
Apr 11, 2016 | IDA-45500 | Int Charges | 26,103.92 |
Feb 15, 2017 | IDA-42330 | Loan Repay | 634.15 |
Feb 15, 2017 | IDA-45500 | Int Charges | 209.57 |
Feb 15, 2017 | IDA-45500 | Int Charges | 209.57 |
Aug 15, 2016 | IDA-45500 | Int Charges | 338.96 |
Aug 15, 2016 | IDA-45500 | Int Charges | 338.96 |
Aug 15, 2016 | IDA-45500 | Int Charges | 27,150.40 |
Aug 15, 2016 | IDA-45500 | Int Charges | 27,150.40 |
Feb 16, 2018 | IDA-45500 | Int Charges | 513.19 |
Feb 16, 2018 | IDA-45500 | Int Charges | 513.19 |
Feb 16, 2018 | IDA-45500 | Int Charges | 27,494.04 |
Feb 16, 2018 | IDA-45500 | Int Charges | 27,494.04 |
Aug 15, 2017 | IDA-42330 | Loan Repay | 220,920.90 |
Aug 15, 2017 | IDA-42330 | Int Charges | 4.59 |
Aug 15, 2017 | IDA-42330 | Int Charges | 4.59 |
Aug 15, 2017 | IDA-42330 | Int Charges | 76,542.36 |
Aug 15, 2017 | IDA-42330 | Int Charges | 76,542.36 |
Aug 15, 2017 | IDA-45500 | Int Charges | 295.22 |
Aug 15, 2017 | IDA-45500 | Int Charges | 295.22 |
Aug 15, 2017 | IDA-42330 | Int Charges | 3,281.23 |
Aug 15, 2017 | IDA-42330 | Int Charges | 3,281.23 |
Aug 15, 2017 | IDA-45500 | Int Charges | 26,885.01 |
Aug 15, 2017 | IDA-45500 | Int Charges | 26,885.01 |
Feb 16, 2017 | IDA-45500 | Int Charges | 25,855.44 |
Feb 16, 2017 | IDA-45500 | Int Charges | 25,855.44 |
Feb 16, 2017 | IDA-42330 | Int Charges | 76,571.16 |
Feb 16, 2017 | IDA-42330 | Int Charges | 76,571.16 |
Feb 16, 2017 | IDA-42330 | Loan Repay | 211,974.36 |
Aug 20, 2018 | IDA-42330 | Int Charges | 4.54 |
Aug 20, 2018 | IDA-42330 | Int Charges | 4.54 |
Aug 20, 2018 | IDA-42330 | Int Charges | 79,324.18 |
Aug 20, 2018 | IDA-42330 | Int Charges | 79,324.18 |
Aug 20, 2018 | IDA-42330 | Int Charges | 9,509.28 |
Aug 20, 2018 | IDA-42330 | Int Charges | 9,509.28 |
Aug 20, 2018 | IDA-42330 | Loan Repay | 218,073.38 |
Aug 20, 2018 | IDA-45500 | Int Charges | 861.77 |
Aug 20, 2018 | IDA-45500 | Int Charges | 861.77 |
Aug 20, 2018 | IDA-45500 | Int Charges | 27,026.86 |
Aug 20, 2018 | IDA-45500 | Int Charges | 27,026.86 |
Feb 16, 2018 | IDA-42330 | Int Charges | 74,220.16 |
Feb 16, 2018 | IDA-42330 | Int Charges | 74,220.16 |
Feb 16, 2018 | IDA-42330 | Int Charges | 5,678.41 |
Feb 16, 2018 | IDA-42330 | Int Charges | 5,678.41 |
Feb 16, 2018 | IDA-42330 | Loan Repay | 229,149.55 |
Sep 3, 2019 | IDA-45500 | Int Charges | 26,510.34 |
Sep 3, 2019 | IDA-45500 | Int Charges | 26,510.34 |
Sep 3, 2019 | IDA-42330 | Int Charges | 43.58 |
Sep 3, 2019 | IDA-42330 | Int Charges | 43.58 |
Sep 3, 2019 | IDA-42330 | Int Charges | 76,203.89 |
Sep 3, 2019 | IDA-42330 | Int Charges | 76,203.89 |
Sep 3, 2019 | IDA-42330 | Int Charges | 3,143.94 |
Jul 18, 2013 | IDA-45500 | Loan Disb | 716,209.90 |
Aug 15, 2013 | IDA-42330 | Int Charges | 973.79 |
Aug 15, 2013 | IDA-42330 | Int Charges | 973.79 |
Aug 23, 2013 | IDA-42330 | Int Charges | 81,146.97 |
Aug 23, 2013 | IDA-42330 | Int Charges | 81,146.97 |
Aug 23, 2013 | IDA-45500 | Int Charges | 493.18 |
Aug 23, 2013 | IDA-45500 | Int Charges | 493.18 |
Aug 23, 2013 | IDA-45500 | Int Charges | 5,061.96 |
Aug 23, 2013 | IDA-45500 | Int Charges | 5,061.96 |
Jul 3, 2013 | IDA-45500 | Loan Disb | 500,000.00 |
Jul 25, 2013 | IDA-45500 | Loan Disb | 1,287,050.20 |
Jul 18, 2013 | IDA-42330 | Loan Disb | 5,112.98 |
Jul 18, 2013 | IDA-42330 | Loan Disb | 8,226.69 |
Jul 18, 2013 | IDA-42330 | Loan Disb | 405,105.25 |
Jul 3, 2013 | IDA-42330 | Loan Disb | 555,166.00 |
Jul 18, 2013 | IDA-45500 | Loan Disb | 1,352,711.20 |
Jul 19, 2013 | IDA-45500 | Loan Disb | 268,599.34 |
Feb 15, 2015 | IDA-42330 | Int Charges | 557.34 |
Feb 15, 2015 | IDA-42330 | Int Charges | 557.34 |
Feb 15, 2014 | IDA-42330 | Int Charges | 538.65 |
Feb 15, 2014 | IDA-42330 | Int Charges | 538.65 |
Feb 15, 2014 | IDA-42330 | Int Charges | 90,538.69 |
Feb 15, 2014 | IDA-42330 | Int Charges | 90,538.69 |
Feb 15, 2014 | IDA-45500 | Int Charges | 3,200.72 |
Feb 15, 2014 | IDA-45500 | Int Charges | 3,200.72 |
Dec 23, 2013 | IDA-42330 | Loan Cancel | 3,781.08 |
Feb 15, 2014 | IDA-45500 | Int Charges | 28,444.27 |
Feb 15, 2014 | IDA-45500 | Int Charges | 28,444.27 |
Nov 27, 2013 | IDA-45500 | Loan Cancel | 2,014,315.20 |
Sep 30, 2013 | IDA-45500 | Loan Disb | 165,879.27 |
Nov 1, 2013 | IDA-45500 | Loan Disb | 41,519.19 |
Nov 7, 2013 | IDA-45500 | Loan Disb | 365,955.34 |
Oct 9, 2013 | IDA-45500 | Loan Disb | 38,825.76 |
Dec 23, 2013 | IDA-42330 | Loan Disb | -3,452.42 |
Sep 11, 2013 | IDA-45500 | Loan Disb | 43,327.89 |
Nov 7, 2013 | IDA-45500 | Loan Disb | 128,636.20 |
Sep 11, 2013 | IDA-45500 | Loan Disb | 115,867.22 |
Nov 7, 2013 | IDA-45500 | Loan Disb | 124,109.26 |
Aug 7, 2013 | IDA-42330 | Loan Disb | 99,662.24 |
Oct 29, 2013 | IDA-45500 | Loan Disb | 31,088.81 |
Aug 15, 2015 | IDA-45500 | Int Charges | 27,307.40 |
Aug 15, 2015 | IDA-45500 | Int Charges | 27,307.40 |
Aug 15, 2015 | IDA-42330 | Int Charges | 82,626.34 |
Aug 15, 2015 | IDA-42330 | Int Charges | 82,626.34 |
Feb 15, 2015 | IDA-42330 | Int Charges | 82,767.14 |
Feb 15, 2015 | IDA-42330 | Int Charges | 82,767.14 |
Feb 15, 2015 | IDA-45500 | Int Charges | 27,353.89 |
Feb 15, 2015 | IDA-45500 | Int Charges | 27,353.89 |
Feb 15, 2024 | IDA-45500 | Int Charges | 23,418.91 |
Feb 15, 2024 | IDA-45500 | Int Charges | 23,418.91 |
Aug 15, 2024 | IDA-45500 | Loan Repay | 68,193.50 |
Aug 15, 2024 | IDA-45500 | Int Charges | 21,983.70 |
Aug 15, 2024 | IDA-45500 | Int Charges | 21,983.70 |
Aug 15, 2024 | IDA-42330 | Loan Repay | 206,391.81 |
Aug 15, 2024 | IDA-42330 | Loan Repay | 3,730.74 |
Aug 15, 2024 | IDA-45500 | Loan Repay | 1,250.47 |
Aug 15, 2024 | IDA-42330 | Int Charges | 62,639.69 |
Aug 15, 2024 | IDA-42330 | Int Charges | 62,639.69 |
Sep 15, 2021 | IDA-45500 | Int Charges | 26,632.72 |
Sep 15, 2021 | IDA-45500 | Int Charges | 26,632.72 |
Sep 15, 2021 | IDA-45500 | Loan Repay | 73,329.17 |
Aug 15, 2021 | IDA-42330 | Loan Repay | 1,933.83 |
Aug 15, 2021 | IDA-45500 | Loan Repay | 648.02 |
Mar 22, 2021 | IDA-45500 | Loan Repay | 74,136.96 |
Mar 22, 2021 | IDA-45500 | Int Charges | 78.63 |
Mar 22, 2021 | IDA-45500 | Int Charges | 78.63 |
Mar 22, 2021 | IDA-45500 | Int Charges | 26,967.34 |
Mar 22, 2021 | IDA-45500 | Int Charges | 26,967.34 |
Mar 22, 2021 | IDA-45500 | Int Charges | 2,285.98 |
Mar 22, 2021 | IDA-45500 | Int Charges | 2,285.98 |
Aug 18, 2023 | IDA-42330 | Loan Repay | 208,758.44 |
Aug 18, 2023 | IDA-42330 | Int Charges | 67.53 |
Aug 18, 2023 | IDA-42330 | Int Charges | 67.53 |
Aug 18, 2023 | IDA-42330 | Int Charges | 68,107.46 |
Aug 18, 2023 | IDA-42330 | Int Charges | 68,107.46 |
Aug 18, 2023 | IDA-45500 | Int Charges | 218.96 |
Aug 18, 2023 | IDA-45500 | Int Charges | 218.96 |
Aug 18, 2023 | IDA-45500 | Loan Repay | 68,993.14 |
Aug 18, 2023 | IDA-45500 | Int Charges | 22.30 |
Aug 18, 2023 | IDA-45500 | Int Charges | 22.30 |
Aug 18, 2023 | IDA-45500 | Int Charges | 23,802.64 |
Aug 18, 2023 | IDA-45500 | Int Charges | 23,802.64 |
Aug 18, 2023 | IDA-42330 | Int Charges | 653.32 |
Aug 18, 2023 | IDA-42330 | Int Charges | 653.32 |
Feb 15, 2023 | IDA-42330 | Loan Repay | 6,207.33 |
Feb 15, 2023 | IDA-45500 | Loan Repay | 0.01 |
Feb 15, 2023 | IDA-45500 | Loan Repay | 2,080.32 |
Mar 1, 2023 | IDA-42330 | Int Charges | 68,441.72 |
Mar 1, 2023 | IDA-42330 | Int Charges | 68,441.72 |
Mar 1, 2023 | IDA-45500 | Int Charges | 19.82 |
Mar 1, 2023 | IDA-45500 | Int Charges | 19.82 |
Mar 1, 2023 | IDA-45500 | Loan Repay | 67,125.26 |
Mar 1, 2023 | IDA-45500 | Int Charges | 23,913.93 |
Mar 1, 2023 | IDA-45500 | Int Charges | 23,913.93 |
Mar 1, 2023 | IDA-42330 | Loan Repay | 203,193.73 |
Mar 1, 2023 | IDA-42330 | Int Charges | 59.97 |
Mar 1, 2023 | IDA-42330 | Int Charges | 59.97 |
Aug 15, 2022 | IDA-45500 | Loan Repay | 1,251.54 |
Aug 29, 2022 | IDA-45500 | Loan Repay | 66,309.57 |
Aug 29, 2022 | IDA-45500 | Int Charges | 52.78 |
Aug 29, 2022 | IDA-45500 | Int Charges | 52.78 |
Aug 29, 2022 | IDA-42330 | Loan Repay | 200,690.19 |
Aug 29, 2022 | IDA-42330 | Int Charges | 159.75 |
Aug 29, 2022 | IDA-42330 | Int Charges | 159.75 |
Aug 29, 2022 | IDA-42330 | Int Charges | 68,209.37 |
Aug 29, 2022 | IDA-42330 | Int Charges | 68,209.37 |
Aug 29, 2022 | IDA-45500 | Int Charges | 23,809.12 |
Aug 29, 2022 | IDA-45500 | Int Charges | 23,809.12 |
Aug 15, 2022 | IDA-42330 | Loan Repay | 3,734.55 |
Feb 15, 2022 | IDA-45500 | Loan Repay | 932.32 |
Apr 16, 2009 | IDA-45500 | Loan Commitment | 10,000,000.00 |
Oct 5, 2006 | IDA-42330 | Loan Commitment | 23,000,000.00 |
Feb 15, 2024 | IDA-42330 | Loan Repay | 206,658.73 |
Feb 15, 2024 | IDA-42330 | Int Charges | 12.98 |
Feb 15, 2024 | IDA-42330 | Int Charges | 12.98 |
Feb 15, 2024 | IDA-42330 | Int Charges | 66,967.21 |
Feb 15, 2024 | IDA-42330 | Int Charges | 66,967.21 |
Feb 15, 2024 | IDA-45500 | Loan Repay | 332.31 |
Feb 15, 2024 | IDA-42330 | Loan Repay | 991.47 |
Feb 15, 2024 | IDA-45500 | Loan Repay | 68,294.56 |
Feb 15, 2024 | IDA-45500 | Int Charges | 4.29 |
Feb 15, 2024 | IDA-45500 | Int Charges | 4.29 |
Sep 3, 2019 | IDA-42330 | Int Charges | 3,143.94 |
Sep 3, 2019 | IDA-42330 | Loan Repay | 213,905.67 |
Sep 3, 2019 | IDA-45500 | Int Charges | 286.49 |
Sep 3, 2019 | IDA-45500 | Int Charges | 286.49 |
Sep 3, 2019 | IDA-45500 | Loan Repay | 70,694.26 |
Feb 15, 2019 | IDA-42330 | Loan Repay | 4,822.75 |
Feb 25, 2019 | IDA-42330 | Loan Repay | 214,002.73 |
Feb 25, 2019 | IDA-42330 | Int Charges | 22.79 |
Feb 25, 2019 | IDA-42330 | Int Charges | 22.79 |
Feb 25, 2019 | IDA-42330 | Int Charges | 75,570.04 |
Feb 25, 2019 | IDA-42330 | Int Charges | 75,570.04 |
Feb 25, 2019 | IDA-45500 | Int Charges | 26,389.60 |
Feb 25, 2019 | IDA-45500 | Int Charges | 26,389.60 |
Feb 15, 2019 | IDA-45500 | Int Charges | 438.24 |
Feb 15, 2019 | IDA-45500 | Int Charges | 438.24 |
Mar 22, 2021 | IDA-42330 | Int Charges | 237.99 |
Mar 22, 2021 | IDA-42330 | Int Charges | 237.99 |
Mar 22, 2021 | IDA-42330 | Int Charges | 77,391.29 |
Mar 22, 2021 | IDA-42330 | Int Charges | 77,391.29 |
Aug 18, 2014 | IDA-42330 | Int Charges | 362.49 |
Aug 18, 2014 | IDA-42330 | Int Charges | 362.49 |
Aug 18, 2014 | IDA-42330 | Int Charges | 90,069.91 |
Aug 18, 2014 | IDA-42330 | Int Charges | 90,069.91 |
Aug 18, 2014 | IDA-45500 | Int Charges | 127.23 |
Aug 18, 2014 | IDA-45500 | Int Charges | 127.23 |
Aug 18, 2014 | IDA-45500 | Int Charges | 29,767.44 |
Aug 18, 2014 | IDA-45500 | Int Charges | 29,767.44 |
Feb 15, 2015 | IDA-45500 | Int Charges | 184.24 |
Feb 15, 2015 | IDA-45500 | Int Charges | 184.24 |
Aug 15, 2016 | IDA-42330 | Int Charges | 1,025.59 |
Aug 15, 2016 | IDA-42330 | Int Charges | 1,025.59 |
Aug 15, 2016 | IDA-42330 | Int Charges | 82,151.29 |
Aug 15, 2016 | IDA-42330 | Int Charges | 82,151.29 |
Feb 15, 2016 | IDA-45500 | Int Charges | 105.06 |
Feb 15, 2016 | IDA-45500 | Int Charges | 105.06 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2013-06-29 |
Financial Management | Satisfactory | 2013-06-29 |
Monitoring and Evaluation | Satisfactory | 2013-06-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2013-06-29 |
Procurement | Satisfactory | 2013-06-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-06-29 |
Counterpart Funding | Satisfactory | 2013-06-29 |
Overall Safeguards Rating | Satisfactory | 2013-06-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-20-2013 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 02-27-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: 12-19-2016 |
---|---|---|
Outcome Rating | Moderately Satisfactory | Moderately Unsatisfactory |
Risk To Development Outcome | Significant | High |
Bank Performance | Moderately Satisfactory | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory | Moderately Unsatisfactory |
Government Performance | Moderately Unsatisfactory | Not Rated |
Implementing Agency | Moderately Satisfactory | Moderately Unsatisfactory |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | High | Substantial |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 4450.00 | 5000.00 |
Date | May 31, 2008 | May 13, 2013 | June 30, 2013 | |
Comment | 89 kiosks are operational serving 50 people per kiosk = 4450 (however, it should be noted that more realistic usage is 1,000peopleper kiosk) |
Number of metered customers | Value | 26,086 | 54000 | 54000 |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment | Figure provided by Lusaka Water and Sewerage Company |
Drinking water quality - biological samples failing | Value | 17.7% | 3.6% | from 10% to 5% |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment | Latest figures from LWSC for Lusaka |
National Investment Program for WSS agreed by MLGH and contributing donors; | Value | Not agreed | Rural agreed; Urban pending | Agreed |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment | Framework developed in December 2011 and agreed by MLGH, but not all donors |
Operating cost coverage ratio in utilities targeted by the project | Value | 93.00 | 121.00 | 100.00 |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment | Defined as the sum of revenue from water and sewerage charges less 1/6 of such amount (as provisions against uncollectablerevenues), divided by all expenses related to operations, excluding debt service requirements and provisions for depreciation andother non-cash operating charges. | As reported by LWSC (and verified by FMS), but to be validated by Special Audit |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Leakage Control | Value | 55.00 | 48.00 | 46.00 |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment | Based on LWSC |
Reduction in energy usage per m3 sewerage discharge | Value | 15% decrease | ||
Date | June 22, 2012 | June 30, 2011 | ||
Comment | No investments have been made in sewerage rehabilitation. |
Collection ratio (collect/billed current period per billing cycle) | Value | 70% | 91% | 95% |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment | Based on figure from LWSC |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 89.00 | 100.00 |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment | 89 functional water kiosks |
Number of water utilities that the project is supporting | Value | 0.00 | 1.00 | 1.00 |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment |
Installation of new meters | Value | 0.00 | 30000.00 | 20000.00 |
Date | October 5, 2006 | May 13, 2013 | June 30, 2013 | |
Comment |
Reduction in energy usage per m3 water produced | Value | 1.2 KWh/m3 | 15% | 5% reduction |
Date | April 15, 2011 | May 13, 2013 | June 30, 2013 | |
Comment | Based on LWSC |