Skip to Main Navigation

Renewable Energy Resources Project

Abstract*

The Renewable Energy Resources Project for Croatia aims at reducing greenhouse gas emissions on a continuous basis by overcoming barriers to implementation of renewable energy. Performance indicators for the global objective include: Reductions in carbon dioxide emissions at the national and project levels; and Increased share of new Renewable Energy Resources (RER) in national energy supply. The project will achieve the objectives by: (i) Overcoming...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the proposed project is to help develop an economically and env ironmentally sustainable market for renewable energy resources in Croatia. Devel opment of this market will support Croatia in its EU accession efforts. In addi tion, the project will help make Croatia?s economy less reliant on imported elec tricity and fossil fuels, reduce overall emissions, lead to a higher degree of l ocal equipment manufacturing, and create an attractive climate for private inves tment in renewable energy, and generate local industry and employment. The proje ct will in principle deal with both the production of electricity and heat from RER. However, most of the emphasis will be on electricity production (from wind farms and biomass fired cogeneration plants).

Key Details

Project Details

  • P071464

  • Closed

  • Peter Johansen

  • N/A

  • Croatia

  • June 13, 2002

  • (as of board presentation)

    June 23, 2005

  • November 24, 2005

  • US$ 8.50 million

  • C

  • January 15, 2013

  • May 31, 2010

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 5.50
Croatia: Govt. of 3.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.50
Total Project Cost** 8.50

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2010-03-25
Monitoring and Evaluation Satisfactory 2010-03-25
Summary Global Objective Rating Moderately Unsatisfactory 2010-03-25
Overall Implementation Progress (IP) Moderately Unsatisfactory 2010-03-25
Overall Safeguards Rating Satisfactory 2010-03-25
Procurement Satisfactory 2010-03-25
Counterpart Funding Satisfactory 2010-03-25
Project Management Satisfactory 2010-03-25

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 11-29-2010
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-16-2011PROJECT PERFORMANCE ASSESSMENT REPORT: 06-27-2013
Outcome RatingModerately Unsatisfactory Moderately Unsatisfactory
Risk To Development OutcomeSignificantModerate
Bank PerformanceModerately UnsatisfactoryModerately Unsatisfactory
Borrower PerformanceModerately UnsatisfactoryModerately Unsatisfactory
Government PerformanceModerately UnsatisfactoryModerately Unsatisfactory
Implementing AgencyModerately UnsatisfactoryNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityModestNegligible

Results Framework

No data available.