Skip to Main Navigation

AO-Econ Mgmt TA (FY03)

Abstract*

The Economic Management Technical Assistance Project for Angola aims to strengthen the Government's capacity to formulate sound analysis and to implement sound policies in areas which are critical to the management of public resources, including: poverty analysis; setting-up a monitoring and evaluation system; formulation of a sound Public Investment Program (PIP); and the establishment of a more transparent and efficient public finance framework...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

EMTA supports GoA efforts to improve efficiency and transparency of public resource management, by improving the institutional framework and building capacity in relevant public institutions to articulate and implement public investment and financial policies and processes.

Key Details

Project Details

  • P072205

  • Closed

  • Roberto O. Panzardi

  • N/A

  • Angola

  • June 27, 2002

  • (as of board presentation)

    March 27, 2003

  • December 4, 2003

  • US$ 16.60 million

  • C

  • Not Applicable

  • February 28, 2011

  • BANK APPROVED

  • August 1, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 16.60
Borrower/Recipient 3.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 16.60
IBRD + IDA Commitment 16.60
Lending Instrument
Grant Amount N/A
Total Project Cost** 20.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 1, 2023 IDA-37440 Int Charges 8,708.60
Jun 1, 2023 IDA-37440 Int Charges 8,708.60
Jun 1, 2023 IDA-37440 Loan Repay 91,695.31
Jun 1, 2023 IDA-37440 Loan Repay 407,040.16
Jun 1, 2023 IDA-37440 Int Charges 30,391.69
Jun 1, 2023 IDA-37440 Int Charges 30,391.69
Dec 1, 2022 IDA-37440 Loan Repay 0.01
Dec 1, 2022 IDA-37440 Loan Repay 17,824.13
Dec 1, 2022 IDA-37440 Int Charges 22,463.14
Dec 1, 2022 IDA-37440 Int Charges 22,463.14
Dec 1, 2022 IDA-37440 Loan Repay 6,615.21
Dec 1, 2022 IDA-37440 Loan Repay 223,218.40
Jun 1, 2022 IDA-37440 Loan Repay 250,343.40
Jun 1, 2022 IDA-37440 Int Charges 32,726.71
Jun 1, 2022 IDA-37440 Int Charges 32,726.71
Jun 1, 2022 IDA-37440 Loan Repay 2,616.78
Jun 1, 2018 IDA-37440 Int Charges 3,041.89
Jun 1, 2018 IDA-37440 Int Charges 3,041.89
Jan 5, 2018 IDA-37440 Int Charges 5,942.03
Jan 5, 2018 IDA-37440 Int Charges 5,942.03
Jan 5, 2018 IDA-37440 Loan Repay 267,581.22
Jan 5, 2018 IDA-37440 Int Charges 64.49
Jan 5, 2018 IDA-37440 Int Charges 64.49
Jan 5, 2018 IDA-37440 Int Charges 39,583.41
Jan 5, 2018 IDA-37440 Int Charges 39,583.41
Jun 1, 2017 IDA-37440 Loan Repay 9,294.03
Dec 1, 2021 IDA-37440 Loan Repay 1,053.05
Dec 1, 2021 IDA-37440 Int Charges 34,932.36
Dec 1, 2021 IDA-37440 Int Charges 34,932.36
Dec 1, 2021 IDA-37440 Int Charges 3,336.77
Dec 1, 2021 IDA-37440 Int Charges 3,336.77
Dec 1, 2021 IDA-37440 Loan Repay 261,349.50
Jun 1, 2021 IDA-37440 Loan Repay 49,694.86
Jun 1, 2021 IDA-37440 Int Charges 5.64
Jun 1, 2021 IDA-37440 Int Charges 5.64
Jun 1, 2021 IDA-37440 Int Charges 33,131.47
Jun 1, 2021 IDA-37440 Int Charges 33,131.47
Jun 1, 2021 IDA-37440 Int Charges 3,189.22
Jun 1, 2021 IDA-37440 Int Charges 3,189.22
Jun 1, 2021 IDA-37440 Loan Repay 85,774.80
Dec 3, 2020 IDA-37440 Int Charges 2,170.66
Dec 3, 2020 IDA-37440 Int Charges 2,170.66
Dec 3, 2020 IDA-37440 Loan Repay 130,063.73
Dec 3, 2020 IDA-37440 Int Charges 33,701.11
Dec 3, 2020 IDA-37440 Int Charges 33,701.11
Dec 3, 2020 IDA-37440 Loan Repay 4,628.75
Dec 3, 2020 IDA-37440 Int Charges 16.84
Dec 3, 2020 IDA-37440 Int Charges 16.84
Jun 4, 2020 IDA-37440 Int Charges 2,962.91
Jun 4, 2020 IDA-37440 Int Charges 2,962.91
Jun 4, 2020 IDA-37440 Loan Repay 257,908.23
Jun 4, 2020 IDA-37440 Int Charges 10.72
Jun 4, 2020 IDA-37440 Int Charges 10.72
Jun 4, 2020 IDA-37440 Int Charges 34,190.17
Jun 4, 2020 IDA-37440 Int Charges 34,190.17
Dec 1, 2019 IDA-37440 Loan Repay 890.98
Dec 3, 2019 IDA-37440 Loan Repay 212,706.80
Dec 3, 2019 IDA-37440 Loan Repay 44,366.68
Dec 3, 2019 IDA-37440 Int Charges 15.96
Dec 3, 2019 IDA-37440 Int Charges 15.96
Dec 3, 2019 IDA-37440 Int Charges 34,280.36
Dec 3, 2019 IDA-37440 Int Charges 34,280.36
Jun 1, 2019 IDA-37440 Loan Repay 0.61
Jun 1, 2018 IDA-37440 Int Charges 0.06
Jun 1, 2018 IDA-37440 Int Charges 0.06
Jun 5, 2024 IDA-37440 Loan Repay 10,720.63
Jun 5, 2024 IDA-37440 Int Charges 10,075.64
Jun 5, 2024 IDA-37440 Int Charges 10,075.64
Jun 5, 2024 IDA-37440 Loan Repay 486,297.38
Jun 5, 2024 IDA-37440 Int Charges 25,866.71
Jun 5, 2024 IDA-37440 Int Charges 25,866.71
Mar 27, 2003 IDA-37440 Loan Commitment 16,600,000.00
Jun 5, 2024 IDA-37440 Int Charges 143.17
Jun 5, 2024 IDA-37440 Int Charges 143.17
Dec 1, 2023 IDA-37440 Loan Repay 0.03
Dec 1, 2023 IDA-37440 Loan Repay 6,167.00
Dec 15, 2023 IDA-37440 Loan Repay 9,210.49
Dec 15, 2023 IDA-37440 Loan Repay 487,372.16
Dec 15, 2023 IDA-37440 Int Charges 18,560.64
Dec 15, 2023 IDA-37440 Int Charges 18,560.64
Jun 1, 2023 IDA-37440 Int Charges 0.01
Jun 1, 2023 IDA-37440 Int Charges 0.01
Jun 1, 2014 IDA-37440 Loan Repay 274.73
Dec 4, 2013 IDA-37440 Int Charges 53,407.04
Dec 4, 2013 IDA-37440 Int Charges 53,407.04
Dec 4, 2013 IDA-37440 Loan Repay 141,057.06
Dec 4, 2013 IDA-37440 Loan Repay 2,800.29
Dec 4, 2013 IDA-37440 Int Charges 35.92
Dec 4, 2013 IDA-37440 Int Charges 35.92
Dec 4, 2013 IDA-37440 Int Charges 3,023.41
Dec 4, 2013 IDA-37440 Int Charges 3,023.41
Dec 1, 2014 IDA-37440 Loan Repay 611.54
Dec 5, 2014 IDA-37440 Loan Repay 272,529.94
Dec 5, 2014 IDA-37440 Int Charges 49,677.06
Dec 5, 2014 IDA-37440 Int Charges 49,677.06
Jun 13, 2017 IDA-37440 Loan Repay 250,064.73
Jun 13, 2017 IDA-37440 Int Charges 36,546.94
Jun 13, 2017 IDA-37440 Int Charges 36,546.94
Dec 1, 2016 IDA-37440 Loan Repay 1,389.38
Jun 1, 2016 IDA-37440 Loan Repay 52,449.89
Jun 1, 2016 IDA-37440 Int Charges 44,878.04
Jun 1, 2016 IDA-37440 Int Charges 44,878.04
Jun 1, 2016 IDA-37440 Loan Repay 5,847.00
Jun 1, 2016 IDA-37440 Loan Repay 204,724.40
Dec 1, 2016 IDA-37440 Loan Repay 252,356.42
Dec 1, 2016 IDA-37440 Int Charges 42,343.83
Dec 1, 2016 IDA-37440 Int Charges 42,343.83
Dec 1, 2015 IDA-37440 Loan Repay 45,819.02
Dec 1, 2015 IDA-37440 Loan Repay 211,787.34
Dec 1, 2015 IDA-37440 Int Charges 44,920.09
Dec 1, 2015 IDA-37440 Int Charges 44,920.09
Dec 1, 2015 IDA-37440 Int Charges 1,880.09
Dec 1, 2015 IDA-37440 Int Charges 1,880.09
Jun 1, 2015 IDA-37440 Int Charges 44,468.57
Jun 1, 2015 IDA-37440 Int Charges 44,468.57
Jun 1, 2015 IDA-37440 Loan Repay 5,738.76
Jun 1, 2015 IDA-37440 Loan Repay 254,575.08
Jun 1, 2015 IDA-37440 Int Charges 21.64
Jun 1, 2015 IDA-37440 Int Charges 21.64
Jun 1, 2014 IDA-37440 Loan Repay 144,142.30
Jun 1, 2014 IDA-37440 Int Charges 9.01
Jun 1, 2014 IDA-37440 Int Charges 9.01
Jun 1, 2014 IDA-37440 Int Charges 53,073.29
Jun 1, 2014 IDA-37440 Int Charges 53,073.29
Jun 1, 2019 IDA-37440 Loan Repay 2,710.45
Jun 4, 2019 IDA-37440 Int Charges 3,488.74
Jun 4, 2019 IDA-37440 Int Charges 3,488.74
Jun 4, 2019 IDA-37440 Int Charges 34,951.09
Jun 4, 2019 IDA-37440 Int Charges 34,951.09
Jun 4, 2019 IDA-37440 Loan Repay 256,785.72
Dec 1, 2018 IDA-37440 Int Charges 10,290.28
Dec 1, 2018 IDA-37440 Int Charges 10,290.28
Dec 1, 2018 IDA-37440 Int Charges 29,098.83
Dec 1, 2018 IDA-37440 Int Charges 29,098.83
Dec 1, 2018 IDA-37440 Loan Repay 251,414.78
Dec 1, 2018 IDA-37440 Loan Repay 0.06
Dec 1, 2018 IDA-37440 Loan Repay 7,937.14
Jun 1, 2018 IDA-37440 Loan Repay 265,798.12
Jun 1, 2018 IDA-37440 Int Charges 188.27
Jun 1, 2018 IDA-37440 Int Charges 188.27
Jun 1, 2018 IDA-37440 Int Charges 3,566.62
Jun 1, 2018 IDA-37440 Int Charges 3,566.62
Jun 1, 2018 IDA-37440 Int Charges 37,798.19
Jun 1, 2018 IDA-37440 Int Charges 37,798.19

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2011-05-01
Procurement Moderately Unsatisfactory 2011-05-01
Counterpart Funding Satisfactory 2011-05-01
Financial Management Satisfactory 2011-05-01
Progress towards achievement of PDO Moderately Satisfactory 2011-05-01
Monitoring and Evaluation Moderately Satisfactory 2011-05-01
Overall Implementation Progress (IP) Moderately Satisfactory 2011-05-01

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 08-31-2011
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-14-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Minplan: 2009-2013 GoA program prepared: number of sectoral and provincial plans prepared with new methodologyValuenone - zero18 provinces and all sectors5 sectors and 5 provinces at least
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    CommentTarget Met. 2009-2013 Medium Term Development Framework applied in 5 sectors and 18 provinces. Provincial plans under elaboration.
  • INE: National accounts prepared and published according to SNA93Valuenot doneTarget met: The base year (2002) and 2003-07 are rNational Accounts SNA 93
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    Comment
  • INE: ECP/MDGs data produced and published annuallyValueno regular publicationTarget met: IDR1 published in 2008. IDR2 field woIDR2 final
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    Comment
  • Minfin: Produced and published General State Accounts and budget including non financial assetsValuenot producedTarget not met: A module which links purchase of naccounts published
    DateJanuary 5, 2004June 30, 2010February 15, 2011
    Comment
  • Minfin: Number of large contracts procured under the new public procurement LawValueold inadapted legal frameworkTarget partially met: The target was met. Large c3
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    Comment
  • Minfin: Number of audits by INF with follow up actionsValueold inadapted framework22 Inspections have been carried out so far in 20010 Audits with follow-up actions
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    CommentNo information provided during the mission.
  • BNA: Number of errors/downtime of RTGS system for two consecutive yearsValueno systemTarget Met: 2007and 2008: availability above 99%,0 minute downtime
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    Comment
  • BNA: Number of audits by Internal Audit (GAI) with follow up actionsValueOld inadapted departmentTarget Met: 2007: 11 audits and 37 specific tasks12
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 2007-2008 GoA program monitored: number of sectoral and provincial plans monitored with new methodologyValue0Minplan has used new methodologies to monitor progMonitoring for at least 3 sectors and 3 provinces
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    Comment
  • 2000-2001 Household survey publishedValue"dirty" dataTarget Met: Survey published and disseminated.Published and disseminated
    DateMarch 14, 2005February 15, 2011February 15, 2011
    Comment
  • Publication of first national Household survey draft reportValuenoneTarget metDraft report published
    DateDecember 31, 2002February 15, 2011February 15, 2011
    Comment
  • Publication of final report of first national household survey (IDR2)ValueNoneTarget met: Preliminary data from first 6 months rFinal report published and disseminated
    DateMarch 27, 2003February 15, 2011February 15, 2011
    Comment
  • New draft public procurement law presented to National AssemblyValueTarget met: Draft legal package: Procurement DecreNew law to Natiional Assembly
    DateJune 30, 2010February 15, 2011
    Comment
  • New public procurement institutional framework approved by MinfinValueno adequate organizationTarget met: New legal framework was approved by NAa new framework has been articulated and approved
    DateDecember 31, 2002February 15, 2011February 15, 2011
    Comment
  • MIS for Public debt management includes updated informationValueTarget not Met: The MIS sytem has not been set upupdated info
    DateFebruary 15, 2011February 15, 2011
    CommentNo information was provided.
  • New debt management framework approved by Council of MinistersValueTarget Partially met: Debt Management Unit managinnew framework approved
    DateFebruary 15, 2011February 15, 2011
    CommentInternal regulation to be approved in the first quarter FY11
  • Downtime for 2 consecutive yearsValueno systemTarget met: 99.55% functionality in December, 2010no downtime
    DateJanuary 5, 2004February 15, 2011February 15, 2011
    Comment
  • New organization of Central Bank Audit Department approved by BNA BoardValueobsolete organizationTarget met: New structure is in place.New structure for GAI
    DateJanuary 5, 2004July 29, 2005February 15, 2011
    Comment
  • BNA: New AML framework approved by Council of MinistersValueno frameworkTarget met. Law 12/10 of July 9, 2010.New AML framework approved by Council of Miinister
    DateJanuary 5, 2006August 29, 2008February 15, 2011
    Comment