Rural Access and Mobility Project (RAMP)

Abstract*

The objectives of the Rural Access and Mobility Project in Nigeria are to improve road access for rural communities in Kaduna state and improve management of the state road network in a sustainable manner. There are two components to the project. The first component is the upgrading, rehabilitation and maintenance of transport infrastructure component. The rural transport infrastructure component of the project will support the upgrading, rehabilitation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve road access for rural communities in Kaduna State and improve management of State road network in a sustainable manner.

Key Details

Project Details

  • P072644

  • Closed

  • Olatunji Ahmed

  • FEDERAL MINISTRY OF FINANCE (IERD)

  • Nigeria

  • January 11, 2006

  • (as of board presentation)

    April 1, 2008

  • December 16, 2008

  • US$ 72.00 million

  • KADUNA STATE MINISTRY OF WORKS AND TRANSPORT

  • Western and Central Africa

  • 2008

  • US$ 60.00 million

  • B

  • September 23, 2022

  • June 30, 2016

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 12.00
IDA Credit 60.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 60.00
IBRD + IDA Commitment 60.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 72.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 23, 2013 IDA-44080 Loan Disb 205,962.58
Dec 23, 2013 IDA-44080 Loan Disb 198,457.69
Dec 5, 2013 IDA-44080 Loan Disb 507,485.25
Sep 11, 2013 IDA-44080 Loan Disb 47,446.30
Oct 4, 2013 IDA-44080 Loan Disb 384,212.22
Jan 6, 2014 IDA-44080 Loan Disb 158,303.20
Jan 6, 2014 IDA-44080 Loan Disb 60,703.44
Sep 18, 2013 IDA-44080 Loan Disb 548,228.94
Sep 18, 2013 IDA-44080 Loan Disb 441,669.03
Jul 11, 2013 IDA-44080 Loan Disb 800,110.50
Jul 11, 2013 IDA-44080 Loan Disb 559,311.90
Jul 11, 2013 IDA-44080 Loan Disb 289,688.28
Jul 11, 2013 IDA-44080 Loan Disb 601,600.70
Aug 26, 2013 IDA-44080 Loan Disb 343,974.10
Sep 29, 2014 IDA-44080 Loan Disb 51,409.55
Nov 18, 2014 IDA-44080 Loan Disb 282,989.10
Nov 6, 2014 IDA-44080 Loan Disb 161,381.84
Nov 7, 2014 IDA-44080 Loan Disb 55,942.74
Dec 4, 2014 IDA-44080 Loan Disb 284,920.10
Sep 15, 2015 IDA-44080 Int Charges 6,191.54
Sep 15, 2015 IDA-44080 Int Charges 6,191.54
Sep 30, 2015 IDA-44080 Loan Disb 220,000.00
Jul 9, 2015 IDA-44080 Loan Disb 72,268.83
Jul 24, 2015 IDA-44080 Loan Disb 348,467.12
May 12, 2015 IDA-44080 Loan Disb 132,096.73
May 12, 2015 IDA-44080 Loan Disb 655,737.70
Aug 24, 2015 IDA-44080 Loan Disb 963,917.56
Aug 14, 2015 IDA-44080 Loan Disb 332,227.84
Jun 24, 2015 IDA-44080 Loan Disb 916,257.50
Jun 29, 2015 IDA-44080 Loan Disb 810,976.94
May 7, 2015 IDA-44080 Loan Disb 67,324.73
Sep 15, 2014 IDA-44080 Int Charges 1,755.87
Sep 15, 2014 IDA-44080 Int Charges 1,755.87
Sep 15, 2014 IDA-44080 Int Charges 167,007.81
Sep 15, 2014 IDA-44080 Int Charges 167,007.81
Jul 23, 2014 IDA-44080 Loan Disb 56,209.29
Sep 3, 2014 IDA-44080 Loan Disb 557,770.60
Feb 24, 2015 IDA-44080 Loan Disb 575,157.06
Feb 26, 2015 IDA-44080 Loan Disb 314,883.10
Mar 15, 2015 IDA-44080 Int Charges 4,897.48
Mar 15, 2015 IDA-44080 Int Charges 4,897.48
Mar 15, 2015 IDA-44080 Int Charges 154,195.34
Mar 15, 2015 IDA-44080 Int Charges 154,195.34
Mar 20, 2015 IDA-44080 Loan Disb 110,397.12
Jun 26, 2014 IDA-44080 Loan Disb 890,406.44
May 5, 2014 IDA-44080 Loan Disb 406,267.06
Apr 10, 2014 IDA-44080 Loan Disb 457,820.22
Jan 10, 2014 IDA-44080 Loan Disb 234,688.02
Mar 14, 2014 IDA-44080 Loan Disb 108,511.80
Mar 7, 2014 IDA-44080 Loan Disb 217,822.27
Mar 12, 2014 IDA-44080 Loan Disb 391,946.94
Mar 15, 2014 IDA-44080 Int Charges 2,065.81
Mar 15, 2014 IDA-44080 Int Charges 2,065.81
Mar 15, 2014 IDA-44080 Int Charges 161,012.45
Mar 15, 2014 IDA-44080 Int Charges 161,012.45
Sep 15, 2013 IDA-44080 Int Charges 2,216.40
Sep 15, 2013 IDA-44080 Int Charges 2,216.40
Sep 15, 2013 IDA-44080 Int Charges 137,883.14
Sep 15, 2013 IDA-44080 Int Charges 137,883.14
Mar 15, 2017 IDA-44080 Int Charges 189,109.19
Mar 15, 2017 IDA-44080 Int Charges 189,109.19
Sep 15, 2017 IDA-44080 Int Charges 194,903.66
Sep 15, 2017 IDA-44080 Int Charges 194,903.66
Sep 15, 2017 IDA-44080 Int Charges 232.22
Sep 15, 2017 IDA-44080 Int Charges 232.22
Jun 1, 2016 IDA-44080 Loan Disb 141,145.52
Mar 15, 2017 IDA-44080 Int Charges 845.88
Mar 15, 2017 IDA-44080 Int Charges 845.88
Oct 5, 2016 IDA-44080 Loan Disb 157,229.69
Oct 5, 2016 IDA-44080 Loan Disb 103,398.45
Oct 5, 2016 IDA-44080 Loan Disb 106,268.67
Jun 27, 2016 IDA-44080 Loan Disb 196,787.69
Jun 3, 2016 IDA-44080 Loan Disb 190,598.73
May 10, 2016 IDA-44080 Loan Disb 384,907.70
May 9, 2016 IDA-44080 Loan Disb 282,981.22
May 27, 2016 IDA-44080 Loan Disb 663,029.94
May 9, 2016 IDA-44080 Loan Disb 534,926.50
Sep 15, 2016 IDA-44080 Int Charges 1,368.47
Sep 15, 2016 IDA-44080 Int Charges 1,368.47
Sep 15, 2016 IDA-44080 Int Charges 190,084.31
Sep 15, 2016 IDA-44080 Int Charges 190,084.31
Nov 4, 2016 IDA-44080 Loan Cancel 521,562.60
Nov 4, 2016 IDA-44080 Loan Disb 143,769.97
Jun 30, 2016 IDA-44080 Loan Disb 152,794.50
Sep 15, 2015 IDA-44080 Int Charges 165,471.00
Sep 15, 2015 IDA-44080 Int Charges 165,471.00
Oct 23, 2015 IDA-44080 Loan Disb 160,520.48
Sep 17, 2015 IDA-44080 Loan Disb 40,893.87
Mar 15, 2016 IDA-44080 Int Charges 182,372.55
Mar 15, 2016 IDA-44080 Int Charges 182,372.55
Mar 15, 2016 IDA-44080 Int Charges 2,560.23
Mar 15, 2016 IDA-44080 Int Charges 2,560.23
Dec 18, 2015 IDA-44080 Loan Disb 85,375.13
Dec 10, 2015 IDA-44080 Loan Disb 67,151.54
Sep 15, 2020 IDA-44080 Loan Repay 528,471.94
Sep 15, 2020 IDA-44080 Int Charges 177,490.92
Sep 15, 2020 IDA-44080 Int Charges 177,490.92
Sep 15, 2020 IDA-44080 Loan Repay 1,684.19
Mar 15, 2021 IDA-44080 Int Charges 190,446.64
Mar 15, 2021 IDA-44080 Int Charges 190,446.64
Sep 15, 2019 IDA-44080 Int Charges 188,853.90
Sep 15, 2019 IDA-44080 Int Charges 188,853.90
Mar 15, 2020 IDA-44080 Int Charges 187,606.08
Mar 15, 2020 IDA-44080 Int Charges 187,606.08
Mar 15, 2020 IDA-44080 Loan Repay 5,921.13
Mar 15, 2020 IDA-44080 Loan Repay 509,834.40
Sep 15, 2019 IDA-44080 Loan Repay 1,519.76
Sep 15, 2019 IDA-44080 Loan Repay 512,368.34
Mar 15, 2019 IDA-44080 Int Charges 193,447.10
Mar 15, 2019 IDA-44080 Int Charges 193,447.10
Mar 15, 2019 IDA-44080 Int Charges 364.07
Mar 15, 2019 IDA-44080 Int Charges 364.07
Mar 15, 2019 IDA-44080 Loan Repay 521,069.70
Sep 15, 2018 IDA-44080 Int Charges 196,485.45
Sep 15, 2018 IDA-44080 Int Charges 196,485.45
Sep 15, 2018 IDA-44080 Loan Repay 524,939.25
Sep 15, 2018 IDA-44080 Int Charges 2,819.62
Sep 15, 2018 IDA-44080 Int Charges 2,819.62
Mar 15, 2018 IDA-44080 Int Charges 4,775.76
Mar 15, 2018 IDA-44080 Int Charges 4,775.76
Mar 15, 2018 IDA-44080 Int Charges 201,030.61
Mar 15, 2018 IDA-44080 Int Charges 201,030.61
Apr 1, 2008 IDA-44080 Loan Commitment 60,000,000.00
Mar 15, 2024 IDA-44080 Loan Repay 17,914.29
Mar 28, 2024 IDA-44080 Loan Repay 477,469.28
Mar 28, 2024 IDA-44080 Int Charges 165,297.60
Mar 28, 2024 IDA-44080 Int Charges 165,297.60
Mar 15, 2023 IDA-44080 Int Charges 170,009.55
Mar 15, 2023 IDA-44080 Int Charges 170,009.55
Mar 15, 2023 IDA-44080 Loan Repay 7,248.18
Mar 15, 2023 IDA-44080 Loan Repay 490,948.28
Sep 15, 2023 IDA-44080 Loan Repay 8,618.34
Sep 15, 2023 IDA-44080 Loan Repay 484,892.70
Sep 15, 2023 IDA-44080 Int Charges 166,559.98
Sep 15, 2023 IDA-44080 Int Charges 166,559.98
Sep 15, 2022 IDA-44080 Loan Repay 470,165.40
Sep 15, 2022 IDA-44080 Int Charges 167,187.20
Sep 15, 2022 IDA-44080 Int Charges 167,187.20
Sep 15, 2022 IDA-44080 Loan Repay 14,435.09
Mar 15, 2022 IDA-44080 Int Charges 180,022.44
Mar 15, 2022 IDA-44080 Int Charges 180,022.44
Sep 15, 2021 IDA-44080 Int Charges 187,396.05
Sep 15, 2021 IDA-44080 Int Charges 187,396.05
Sep 15, 2021 IDA-44080 Loan Repay 6,162.53
Sep 15, 2021 IDA-44080 Loan Repay 527,496.44
Mar 15, 2022 IDA-44080 Int Charges 695.22
Mar 15, 2022 IDA-44080 Int Charges 695.22
Mar 15, 2022 IDA-44080 Loan Repay 516,193.40
Mar 15, 2021 IDA-44080 Loan Repay 534,587.06
Mar 15, 2021 IDA-44080 Int Charges 13,476.98
Mar 15, 2021 IDA-44080 Int Charges 13,476.98

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2016-06-30
Financial Management Satisfactory 2016-06-30
Monitoring and Evaluation Satisfactory 2016-06-30
Overall Implementation Progress (IP) Satisfactory 2016-06-30
Progress towards achievement of PDO Moderately Satisfactory 2016-06-30
Procurement Satisfactory 2016-06-30
Counterpart Funding Satisfactory 2016-06-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-15-2017
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-01-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of trips per day, per selected road link increasedValue37 trips7650 trips
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Reduction of transportation unit cost Naira per tripValue232 Naira185220 Naira
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Increase in rural population in project areas with access to an all weather road within 2kmValue1.00 million1.60million1.50 million
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Increased amount of agricultural produce transported across improved river crossingsValue3.5 million tons4.6 million3.8 million tons
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Three year rolling plan produced and used for budget preparationValueNoneYesPlan prepared
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Share of rural population with access to an all-season roadValue1.0055.0050.00
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • The development and use of a Road Management SystemValueNoneNoneIn Use
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of kilometers of roads rehabilitated under OPRC contractsValue0470427
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Number of river crossing structures completedValue0146132
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Road network reclassification studyValue0YesYes
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Digitized state road map showing the complete road network of the StateValue0YesYes
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Simplified road management and road inventory system databaseValue0NoYes
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment
  • Roads rehabilitated, RuralValue0.00470.00427.00
    DateApril 4, 2008June 30, 2015June 30, 2016
    Comment