Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 47.34 |
P073002
Closed
Kin Bing Wu
N/A
May 20, 2002
(as of board presentation)
September 9, 2003
May 20, 2004
US$ 147.34 million
N/A
2004
US$ 100.00 million
C
Not Applicable
December 31, 2009
BANK APPROVED
August 15, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 47.34 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 147.34 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2014 | IBRD-71940 | Int Charges | 159,031.64 |
Sep 9, 2003 | IBRD-71940 | Loan Commitment | 100,000,000.00 |
Sep 15, 2013 | IBRD-71940 | Int Charges | 186,394.92 |
Sep 15, 2013 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2015 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2014 | IBRD-71940 | Int Charges | 140,993.73 |
Sep 15, 2014 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2015 | IBRD-71940 | Int Charges | 130,979.82 |
Mar 15, 2016 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2015 | IBRD-71940 | Int Charges | 140,431.08 |
Sep 15, 2015 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2016 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2016 | IBRD-71940 | Int Charges | 219,243.42 |
Mar 15, 2016 | IBRD-71940 | Int Charges | 158,255.95 |
Sep 15, 2017 | IBRD-71940 | Int Charges | 272,089.60 |
Mar 15, 2017 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2017 | IBRD-71940 | Int Charges | 258,929.14 |
Mar 15, 2018 | IBRD-71940 | Int Charges | 249,686.48 |
Mar 15, 2018 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2017 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2019 | IBRD-71940 | Int Charges | 336,740.60 |
Mar 15, 2019 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2018 | IBRD-71940 | Int Charges | 344,028.66 |
Sep 15, 2018 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2019 | IBRD-71940 | Int Charges | 316,054.16 |
Sep 15, 2019 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2020 | IBRD-71940 | Int Charges | 214,636.88 |
Mar 15, 2020 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2021 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2021 | IBRD-71940 | Int Charges | 35,087.96 |
Sep 15, 2020 | IBRD-71940 | Int Charges | 80,015.20 |
Sep 15, 2020 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2022 | IBRD-71940 | Int Charges | 15,839.93 |
Mar 15, 2022 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2021 | IBRD-71940 | Int Charges | 23,662.56 |
Sep 15, 2021 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Sep 15, 2022 | IBRD-71940 | Int Charges | 36,892.50 |
Sep 15, 2022 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Mar 15, 2023 | IBRD-71940 | Int Charges | 53,153.02 |
Mar 15, 2023 | IBRD-71940 | Loan Repay | 2,584,809.50 |
Mar 15, 2014 | IBRD-71940 | Loan Repay | 2,645,694.50 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2010-06-28 |
Counterpart Funding | Satisfactory | 2010-06-28 |
Procurement | Satisfactory | 2010-06-28 |
Project Management | Satisfactory | 2010-06-28 |
Progress towards achievement of PDO | Satisfactory | 2010-06-28 |
Financial Management | Satisfactory | 2010-06-28 |
Monitoring and Evaluation | Satisfactory | 2010-06-28 |
Overall Implementation Progress (IP) | Satisfactory | 2010-06-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2010 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Highly Satisfactory |
Government Performance | Highly Satisfactory |
Implementing Agency | Highly Satisfactory |
INDICATOR | ICR REVIEW: 01-12-2011 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Highly Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Highly Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |