The development objectives for the project are to improved access to and completion of affordable and quality basic education for poor boys and girls in Sichuan, Gansu, Yunnan Provinces, Ningxia Hui and Guangxi Zhuang Autonomous Regions. There are three components to the project. Component 1. The objective of this component is to improve access to quality primary and junior secondary education, by providing schools which are close to where children...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improved access to and completion of affordable and quality basic education for poor boys and girls in Sichuan, Gansu, Yunnan Provinces, Ningxia Hui and Guangxi Zhuang Autonomous Regions.

Key Details

Project Details

  • P073002

  • Closed

  • Kin Bing Wu

  • N/A

  • China

  • May 20, 2002

  • (as of board presentation)

    September 9, 2003

  • May 20, 2004

  • US$ 100.00 million

  • C

  • Not Applicable

  • December 31, 2009

  • BANK APPROVED

  • August 15, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 100.00
Borrower/Recipient 47.34

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 147.34

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 15, 2014 IBRD-71940 Int Charges 159,031.64
Sep 9, 2003 IBRD-71940 Loan Commitment 100,000,000.00
Sep 15, 2013 IBRD-71940 Int Charges 186,394.92
Sep 15, 2013 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2015 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2014 IBRD-71940 Int Charges 140,993.73
Sep 15, 2014 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2015 IBRD-71940 Int Charges 130,979.82
Mar 15, 2016 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2015 IBRD-71940 Int Charges 140,431.08
Sep 15, 2015 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2016 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2016 IBRD-71940 Int Charges 219,243.42
Mar 15, 2016 IBRD-71940 Int Charges 158,255.95
Sep 15, 2017 IBRD-71940 Int Charges 272,089.60
Mar 15, 2017 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2017 IBRD-71940 Int Charges 258,929.14
Mar 15, 2018 IBRD-71940 Int Charges 249,686.48
Mar 15, 2018 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2017 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2019 IBRD-71940 Int Charges 336,740.60
Mar 15, 2019 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2018 IBRD-71940 Int Charges 344,028.66
Sep 15, 2018 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2019 IBRD-71940 Int Charges 316,054.16
Sep 15, 2019 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2020 IBRD-71940 Int Charges 214,636.88
Mar 15, 2020 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2021 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2021 IBRD-71940 Int Charges 35,087.96
Sep 15, 2020 IBRD-71940 Int Charges 80,015.20
Sep 15, 2020 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2022 IBRD-71940 Int Charges 15,839.93
Mar 15, 2022 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2021 IBRD-71940 Int Charges 23,662.56
Sep 15, 2021 IBRD-71940 Loan Repay 2,645,694.50
Sep 15, 2022 IBRD-71940 Int Charges 36,892.50
Sep 15, 2022 IBRD-71940 Loan Repay 2,645,694.50
Mar 15, 2023 IBRD-71940 Int Charges 53,153.02
Mar 15, 2023 IBRD-71940 Loan Repay 2,584,809.50
Mar 15, 2014 IBRD-71940 Loan Repay 2,645,694.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2010-06-28
Counterpart Funding Satisfactory 2010-06-28
Procurement Satisfactory 2010-06-28
Project Management Satisfactory 2010-06-28
Progress towards achievement of PDO Satisfactory 2010-06-28
Financial Management Satisfactory 2010-06-28
Monitoring and Evaluation Satisfactory 2010-06-28
Overall Implementation Progress (IP) Satisfactory 2010-06-28

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2010
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceHighly Satisfactory
Government PerformanceHighly Satisfactory
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-12-2011PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceHighly SatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

No data available.