Provincial and Peri-Urban Water and Sanitation Project

Abstract*

The Cambodia Provincial and Peri-Urban Water and Sanitation Project aims to assist the country in moving forward to fulfill the Millennium Development Goals (MDGs) in water supply and sanitation by 2015. The project design aims at building partnerships witht the private sector anduser groups in financing, operating, and maintaining constructed facilities, after designing specific instruments that ensure inclusion of low income communities residing...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

While the proposed changes in the restructured project have been assessed to be in accordance with the original development objective as formulated in the Project Appraisal Document (PAD), the updated legal agreement has been amended so that the wording of the objective reads exactly the same as that in the PAD.

Key Details

Project Details

  • P073311

  • Closed

  • Lixin Gu

  • N/A

  • Cambodia

  • November 7, 2002

  • (as of board presentation)

    April 22, 2003

  • February 14, 2003

  • US$ 19.90 million

  • B

  • Not Applicable

  • June 30, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Communities 0.25
IDA Credit 16.90
Borrower/Recipient 1.87
IDA GRANT FOR POOREST COUNTRY 3.00
Foreign Private Commercial Sources (unidentified) 1.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 19.90
IBRD + IDA Commitment 19.90
Lending Instrument
Grant Amount N/A
Total Project Cost** 23.27

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 1, 2024 IDA-37460 Int Charges 37,565.49
Aug 1, 2024 IDA-37460 Loan Repay 266,307.60
Aug 1, 2024 IDA-37460 Loan Repay 781.67
Aug 1, 2018 IDA-37460 Int Charges 4,895.49
Aug 1, 2018 IDA-37460 Int Charges 4,895.49
Aug 1, 2018 IDA-37460 Loan Repay 48,247.26
Aug 1, 2018 IDA-37460 Int Charges 47,703.32
Aug 1, 2018 IDA-37460 Int Charges 47,703.32
Aug 1, 2018 IDA-37460 Loan Repay 93,095.33
Feb 1, 2019 IDA-37460 Loan Repay 2,005.63
Feb 1, 2019 IDA-37460 Loan Repay 83,979.06
Feb 1, 2020 IDA-37460 Int Charges 44,038.52
Feb 1, 2020 IDA-37460 Int Charges 44,038.52
Feb 1, 2020 IDA-37460 Loan Repay 1,082.17
Feb 1, 2020 IDA-37460 Loan Repay 137,626.19
Feb 1, 2020 IDA-37460 Int Charges 674.20
Feb 1, 2020 IDA-37460 Int Charges 674.20
Aug 1, 2019 IDA-37460 Int Charges 2,002.76
Aug 1, 2019 IDA-37460 Int Charges 2,002.76
Aug 1, 2019 IDA-37460 Loan Repay 136,773.10
Aug 1, 2019 IDA-37460 Loan Repay 1,197.88
Aug 1, 2019 IDA-37460 Int Charges 45,530.61
Aug 1, 2019 IDA-37460 Int Charges 45,530.61
Feb 1, 2021 IDA-37460 Loan Repay 6,624.45
Feb 1, 2021 IDA-37460 Int Charges 44,911.18
Feb 1, 2021 IDA-37460 Int Charges 44,911.18
Aug 1, 2020 IDA-37460 Int Charges 555.27
Aug 1, 2020 IDA-37460 Int Charges 555.27
Aug 1, 2020 IDA-37460 Loan Repay 137,578.88
Aug 1, 2020 IDA-37460 Loan Repay 4,768.05
Aug 1, 2020 IDA-37460 Int Charges 40,319.24
Aug 1, 2020 IDA-37460 Int Charges 40,319.24
Feb 1, 2021 IDA-37460 Int Charges 5,687.61
Feb 1, 2021 IDA-37460 Int Charges 5,687.61
Feb 1, 2021 IDA-37460 Loan Repay 138,264.05
Aug 1, 2021 IDA-37460 Int Charges 1,263.80
Aug 1, 2021 IDA-37460 Int Charges 1,263.80
Aug 1, 2021 IDA-37460 Loan Repay 45,868.02
Aug 1, 2021 IDA-37460 Loan Repay 98,060.47
Aug 1, 2021 IDA-37460 Int Charges 45,337.67
Aug 1, 2021 IDA-37460 Int Charges 45,337.67
Feb 1, 2023 IDA-37460 Loan Repay 132,936.19
Feb 1, 2023 IDA-37460 Int Charges 37,325.99
Feb 1, 2023 IDA-37460 Int Charges 37,325.99
Feb 1, 2023 IDA-37460 Loan Repay 3,212.48
Feb 1, 2022 IDA-37460 Loan Repay 2,168.32
Feb 1, 2022 IDA-37460 Loan Repay 138,656.48
Feb 1, 2022 IDA-37460 Int Charges 43,831.92
Feb 1, 2022 IDA-37460 Int Charges 43,831.92
Aug 1, 2022 IDA-37460 Loan Repay 133,246.52
Aug 1, 2022 IDA-37460 Int Charges 41,036.04
Aug 1, 2022 IDA-37460 Int Charges 41,036.04
Aug 1, 2022 IDA-37460 Loan Repay 203.43
Aug 1, 2023 IDA-37460 Int Charges 3,994.08
Aug 1, 2023 IDA-37460 Int Charges 3,994.08
Aug 1, 2023 IDA-37460 Loan Repay 269,913.88
Aug 1, 2023 IDA-37460 Int Charges 38,203.89
Aug 1, 2023 IDA-37460 Int Charges 38,203.89
Apr 22, 2003 IDA-H0340 Loan Commitment 3,000,000.00
Apr 22, 2003 IDA-37460 Loan Commitment 16,900,000.00
Feb 1, 2024 IDA-37460 Int Charges 2,264.95
Feb 1, 2024 IDA-37460 Loan Repay 267,735.97
Feb 1, 2024 IDA-37460 Int Charges 2,264.95
Feb 1, 2024 IDA-37460 Int Charges 39,156.57
Feb 1, 2024 IDA-37460 Int Charges 39,156.57
Aug 1, 2024 IDA-37460 Int Charges 37,565.49
Aug 1, 2013 IDA-37460 Int Charges 123.03
Aug 1, 2013 IDA-37460 Int Charges 123.03
Aug 1, 2013 IDA-37460 Loan Repay 150,856.97
Aug 1, 2013 IDA-37460 Loan Repay 1,305.67
Feb 1, 2014 IDA-37460 Loan Repay 152,998.22
Feb 1, 2014 IDA-37460 Loan Repay 1,550.86
Feb 1, 2014 IDA-37460 Int Charges 57,376.47
Feb 1, 2014 IDA-37460 Int Charges 57,376.47
Feb 1, 2014 IDA-37460 Int Charges 1,652.61
Feb 1, 2014 IDA-37460 Int Charges 1,652.61
Aug 1, 2013 IDA-37460 Int Charges 55,434.03
Aug 1, 2013 IDA-37460 Int Charges 55,434.03
Feb 9, 2015 IDA-37460 Int Charges 44,908.55
Feb 9, 2015 IDA-37460 Int Charges 44,908.55
Feb 9, 2015 IDA-37460 Int Charges 6,739.81
Feb 9, 2015 IDA-37460 Int Charges 6,739.81
Feb 9, 2015 IDA-37460 Loan Repay 140,692.28
Feb 1, 2015 IDA-37460 Loan Repay 1,296.30
Aug 1, 2014 IDA-37460 Loan Repay 154,092.16
Aug 1, 2014 IDA-37460 Int Charges 1,088.54
Aug 1, 2014 IDA-37460 Loan Repay 140.61
Aug 1, 2014 IDA-37460 Int Charges 55,592.15
Aug 1, 2014 IDA-37460 Int Charges 55,592.15
Aug 1, 2014 IDA-37460 Int Charges 1,088.54
Aug 1, 2015 IDA-37460 Int Charges 49,710.13
Aug 1, 2015 IDA-37460 Int Charges 49,710.13
Aug 1, 2015 IDA-37460 Int Charges 23.21
Aug 1, 2015 IDA-37460 Int Charges 23.21
Aug 1, 2015 IDA-37460 Loan Repay 7,423.70
Aug 1, 2015 IDA-37460 Loan Repay 64,338.95
Aug 1, 2015 IDA-37460 Loan Repay 68,733.77
Feb 1, 2016 IDA-37460 Int Charges 858.18
Feb 1, 2016 IDA-37460 Int Charges 858.18
Feb 1, 2016 IDA-37460 Loan Repay 49,303.79
Feb 1, 2016 IDA-37460 Loan Repay 89,492.21
Feb 1, 2016 IDA-37460 Int Charges 48,910.92
Feb 1, 2016 IDA-37460 Int Charges 48,910.92
Aug 1, 2016 IDA-37460 Loan Repay 140,721.06
Feb 1, 2017 IDA-37460 Loan Repay 54,129.65
Feb 1, 2017 IDA-37460 Int Charges 46,571.73
Feb 1, 2017 IDA-37460 Int Charges 46,571.73
Feb 1, 2017 IDA-37460 Loan Repay 802.04
Feb 1, 2017 IDA-37460 Loan Repay 82,370.39
Aug 1, 2017 IDA-37460 Loan Repay 88,737.63
Aug 1, 2017 IDA-37460 Int Charges 45,366.51
Aug 1, 2017 IDA-37460 Int Charges 45,366.51
Aug 1, 2017 IDA-37460 Int Charges 1,359.59
Aug 1, 2017 IDA-37460 Int Charges 1,359.59
Aug 1, 2016 IDA-37460 Int Charges 48.61
Aug 1, 2016 IDA-37460 Int Charges 48.61
Aug 1, 2016 IDA-37460 Int Charges 49,555.67
Aug 1, 2016 IDA-37460 Int Charges 49,555.67
Aug 1, 2016 IDA-37460 Int Charges 542.69
Aug 1, 2016 IDA-37460 Int Charges 542.69
Feb 1, 2018 IDA-37460 Int Charges 3,817.60
Feb 1, 2018 IDA-37460 Int Charges 3,817.60
Feb 1, 2018 IDA-37460 Loan Repay 139,088.40
Feb 1, 2018 IDA-37460 Loan Repay 7,531.74
Feb 1, 2018 IDA-37460 Int Charges 44,955.97
Feb 1, 2018 IDA-37460 Int Charges 44,955.97
Aug 1, 2017 IDA-37460 Loan Repay 53,493.46
Feb 1, 2019 IDA-37460 Loan Repay 54,889.48
Feb 1, 2019 IDA-37460 Int Charges 44,972.05
Feb 1, 2019 IDA-37460 Int Charges 44,972.05

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2011-06-16
Project Management Satisfactory 2011-06-16
Monitoring and Evaluation Satisfactory 2011-06-16
Procurement Satisfactory 2011-06-16
Financial Management Moderately Satisfactory 2011-06-16
Counterpart Funding Satisfactory 2011-06-16
Overall Implementation Progress (IP) Satisfactory 2011-06-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-06-2012
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-19-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualityUnsatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Resolution of conflicts between districts/customers and operators without resorting to contract cancellations in a majority of private sector participation contracts.Value0No conflict has arisen.Not available
    DateFebruary 28, 2002May 15, 2011June 30, 2011
    Comment
  • Operators own equity invested in the lease and OBA contractsValue0US$1.06 million$750,000
    DateFebruary 28, 2002May 15, 2011June 30, 2011
    Comment11 DBL and OBA water supply facilities were built in four project provinces.
  • Percentage of households with improved in-house sanitation facilities (%)Value0%1,075 toilets built under JSDF grant; remaining 6,100% 7,147 sanitation facilities
    DateFebruary 28, 2002May 15, 2011June 30, 2011
    Comment
  • Average no. of consumers satisfied with service performance after systems are operational.Value0%80% in 2 completed DBLs.80%
    DateDecember 31, 2003May 15, 2011June 30, 2011
    CommentNew data is being collected to determine the end of project satisfaction rate.
  • PPWSA maintains a Working Ratio of less than 0.50 during project implementationValue0.260.39<0.50
    DateFebruary 28, 2002May 15, 2011June 30, 2008
    CommentAchieved in 2008 and maintained ever since
  • PPWSA maintains a debt service ratio greater than 1.3 during project implementationValue03.18>1.3
    DateFebruary 28, 2002May 15, 2011June 30, 2008
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Communities with services managed through OBA, lease and management contractsValue011 OBA/DBL facilities.11 OBA/DBL facilities.
    DateFebruary 28, 2002May 15, 2011June 30, 2011
    Comment
  • Households in service area with improved water supply servicesValue01420015,200 households
    DateFebruary 28, 2002May 15, 2011June 30, 2011
    Comment15,200 poor households will be connected to clean water supplyies in Peri-urban Phnom Penh at the end of the project closing.