Multi-Sectoral AIDS Project (MAP)

Abstract*

The Multi-Sectoral AIDS Project (MAP) for Guinea is part of the Multi-Country HIV/AIDS Program for the Africa Region (report no. 20727). In accordance with the main goal of MAP2, the overall objective of the project is to limit and reverse the trend of the epidemic by preventing new infections. There are four main components. The first component empowers communities to address HIV/AIDS prevention, care, mitigation, and support. Grant resources will...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

New PDOs have been approved by the Board on June 29, 2007, and are as follows: - Increase HIV/AIDS knowledge and low risks behaviors; and - Improve the coverage and the use of HIV/AIDS prevention, care treatment and support services.

Key Details

Project Details

  • P073378

  • Closed

  • Haidara Ousmane Diadie

  • N/A

  • Guinea

  • March 19, 2002

  • (as of board presentation)

    December 13, 2002

  • March 28, 2003

  • US$ 20.30 million

  • B

  • Not Applicable

  • December 31, 2008

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 2.00
IDA GRANT FOR HIV/AIDS 20.30

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.30
IBRD + IDA Commitment 20.30
Lending Instrument
Grant Amount N/A
Total Project Cost** 22.30

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 13, 2002 IDA-H0140 Loan Commitment 20,300,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2008-08-07
Procurement Moderately Satisfactory 2008-08-07
Counterpart Funding Satisfactory 2008-08-07
Project Management Satisfactory 2008-08-07
Progress towards achievement of PDO Satisfactory 2008-08-07
Financial Management Satisfactory 2008-08-07
Monitoring and Evaluation Satisfactory 2008-08-07
Overall Implementation Progress (IP) Satisfactory 2008-08-07

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2011
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-12-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • At least 95% of sex workers, 75% of mining workers and 60% of truck drivers reporting the use of a condom in their latest sexual encounter.ValueSex workers: 72%; Miners : 60%; Truck drivers : Sex workers 99.8% Miners : 49.7% Truck drivers: 7Sex workers: 95%; Miners: 75%;Truck drivers: 60%
    DateJune 29, 2007October 24, 2008July 31, 2008
    Comment
  • 40% women and 55% of men aged 15-49 who had more than one sexual partner in the past 12 months reporting the use of a condom duringtheir last sexual intercourseValue25.2% of women and 39.5% of men reported having haWomen: 25.2%, Men: 39.5%(2005 DHS )40% women; 55% men
    DateJune 29, 2007October 24, 2008July 31, 2008
    Comment
  • Number of women and men aged 15-24 having had sex with more than one partner in the last 12 months reduced to 3.8% for women and 30.1% for menValue4.1% of all sexually active women, and 33.4% of Women: 24.4% Men: 31.2%(BSS 2007)3.8% women; 30.1% men
    DateJune 29, 2007December 1, 2007July 31, 2008
    Comment
  • 10% of persons aged 15 and older received counseling and testing for HIV and received their test resultsValueWomen : 2.1% Men : 6.0% (DHS 2005)1.5% General population(source: CNLS - UNGASS) Women: 10%; Men: 10%
    DateDecember 15, 2005October 24, 2008July 31, 2008
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1) Prevention of sexual HIV transmission and transmission through contaminated blood or medical material:Value
    Date
    Comment
  • 1a) 18 youth information centers are equippedValue020 Source: CNLS (see explanation below)18
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 1b) 100% of truck stops offer an HIV/AIDS prevention program to truck driversValue0100% of identified stops(27)(Source: CNLS)100%
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 1c) 80% of prefectures have at least one health center offering a service packet against Sexually Transmitted DiseasesValue0100%(MoH report 2007)80%
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 1d) 100% of blood units in hospitals are regularly and adequately screenedValue2/9 hospitals9/9 (100%)(MoH June report 08)100%
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 2) Antiretroviral treatment of infected pregnant women and persons living with advanced HIV infection:Value
    Date
    Comment
  • 2a) 4,500 pregnant women living with HIV receiving antiretrovirals to reduce the risk of MTCT (SC/U)Value01,145 (Source: CNLS-UNGASS)4,500
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 2b) 500 adults and children with advanced HIV infection receiving antiretroviral combination therapy (SC/U)Value0)720500
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 3) Support of orphaned and vulnerable children:Value
    Date
    Comment
  • 3a) 7,000 orphaned and vulnerable children aged 0-17 whose households received free basic external support in caring for the child in the past 12 monthsValue08300 (nutritional support,Source: CNLS)7,000
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 3b) A cohort of 7,000 orphans is sent yearly to schoolValue018,185(source:CNLS)7,000
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 4) Decentralization of the response and enhanced participation of all sectors:Value
    Date
    Comment
  • 4a) 7 regional action plans are prepared and financed each yearValue08 plans (source:CNLS)7
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 4b) 26 public sector organizations supported and total amount of fundingValue036 public sector organization supported for a tot26
    DateJanuary 1, 2001March 31, 2008July 31, 2008
    Comment
  • 4c) 268 Civil Society Organizations supported for subprojects (includes NGO, CBO, FBO) and total amount of fundingValue0471 Civil society organisations supported with a t268
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment
  • 5) Operational national monitoring & evaluation system with regular dissemination of strategic information:Value
    Date
    Comment
  • 5a) National AIDS Coordinating Authority reports annually on at least 75% of the indicators in its national HIV M&E framework and disseminates the report nation-wide (public/private/NGOs)Value0100% (64/64)(Source:CNLS)75%
    DateJanuary 1, 2001October 24, 2008July 31, 2008
    Comment