Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 193.00 |
Borrower/Recipient | 96.24 |
P074290
Closed
Mitsuyoshi Asada
N/A
October 10, 2002
(as of board presentation)
June 22, 2004
October 21, 2004
US$ 289.24 million
N/A
2004
US$ 193.00 million
B
Not Applicable
September 30, 2011
BANK APPROVED
March 11, 2021
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 193.00 |
Borrower/Recipient | 96.24 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 193.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 193.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 289.24 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2018 | IBRD-77650 | Int Charges | 1,218,006.40 |
May 15, 2018 | IBRD-77650 | Loan Repay | 2,761,471.00 |
May 15, 2018 | IBRD-77650 | Loan Repay | 3,728,885.80 |
May 15, 2018 | IBRD-77650 | Int Charges | 485,725.28 |
Nov 15, 2019 | IBRD-77650 | Loan Repay | 2,830,042.50 |
Nov 15, 2019 | IBRD-77650 | Loan Repay | 3,819,136.20 |
Nov 15, 2019 | IBRD-77650 | Int Charges | 531,366.56 |
Nov 15, 2019 | IBRD-77650 | Int Charges | 948,490.56 |
May 15, 2019 | IBRD-77650 | Int Charges | 1,039,034.56 |
May 15, 2019 | IBRD-77650 | Loan Repay | 2,803,236.00 |
May 15, 2019 | IBRD-77650 | Loan Repay | 3,788,454.80 |
May 15, 2019 | IBRD-77650 | Int Charges | 616,213.10 |
Nov 15, 2020 | IBRD-77650 | Int Charges | 765,148.10 |
May 15, 2021 | IBRD-77650 | Loan Repay | 3,915,642.00 |
Nov 15, 2020 | IBRD-77650 | Loan Repay | 2,878,449.50 |
Nov 15, 2020 | IBRD-77650 | Loan Repay | 3,882,685.50 |
May 15, 2020 | IBRD-77650 | Int Charges | 384,773.20 |
May 15, 2020 | IBRD-77650 | Int Charges | 857,213.20 |
May 15, 2020 | IBRD-77650 | Loan Repay | 2,853,396.50 |
May 15, 2020 | IBRD-77650 | Loan Repay | 3,852,093.00 |
Nov 15, 2021 | IBRD-77650 | Int Charges | 578,768.10 |
Nov 15, 2021 | IBRD-77650 | Int Charges | 103,447.88 |
Nov 15, 2021 | IBRD-77650 | Loan Repay | 2,926,906.20 |
Nov 15, 2021 | IBRD-77650 | Loan Repay | 3,948,599.80 |
May 15, 2021 | IBRD-77650 | Int Charges | 124,428.49 |
May 15, 2021 | IBRD-77650 | Int Charges | 672,351.94 |
May 15, 2021 | IBRD-77650 | Loan Repay | 2,901,803.50 |
Nov 15, 2020 | IBRD-77650 | Int Charges | 196,271.44 |
Nov 15, 2022 | IBRD-77650 | Loan Repay | 2,974,707.20 |
Nov 15, 2022 | IBRD-77650 | Loan Repay | 4,014,514.00 |
Nov 15, 2022 | IBRD-77650 | Int Charges | 180,120.23 |
Nov 15, 2022 | IBRD-77650 | Int Charges | 389,237.40 |
May 15, 2022 | IBRD-77650 | Loan Repay | 3,981,556.20 |
May 15, 2022 | IBRD-77650 | Int Charges | 88,325.22 |
May 15, 2022 | IBRD-77650 | Int Charges | 484,396.60 |
May 15, 2022 | IBRD-77650 | Loan Repay | 2,950,260.20 |
May 15, 2023 | IBRD-77650 | Int Charges | 293,290.47 |
May 15, 2023 | IBRD-77650 | Loan Repay | 4,047,470.50 |
May 15, 2023 | IBRD-77650 | Loan Repay | 2,998,667.20 |
May 15, 2023 | IBRD-77650 | Int Charges | 278,581.56 |
Jun 22, 2004 | IBRD-47440 | Loan Commitment | 200,000,000.00 |
May 15, 2024 | IBRD-77650 | Int Charges | 99,033.70 |
May 15, 2024 | IBRD-77650 | Int Charges | 108,499.99 |
May 15, 2024 | IBRD-77650 | Loan Repay | 3,198,694.00 |
May 15, 2024 | IBRD-77650 | Loan Repay | 4,143,670.00 |
Nov 15, 2023 | IBRD-77650 | Loan Repay | 3,022,021.20 |
Nov 15, 2023 | IBRD-77650 | Int Charges | 199,671.16 |
Nov 15, 2023 | IBRD-77650 | Int Charges | 196,555.95 |
Nov 15, 2023 | IBRD-77650 | Loan Repay | 4,080,428.00 |
Nov 15, 2014 | IBRD-77650 | Loan Repay | 2,608,415.50 |
Nov 15, 2014 | IBRD-77650 | Loan Repay | 3,520,157.00 |
Nov 15, 2014 | IBRD-77650 | Int Charges | 361,553.40 |
Nov 15, 2014 | IBRD-77650 | Int Charges | 1,821,536.60 |
Nov 15, 2013 | IBRD-77650 | Int Charges | 429,200.00 |
Nov 15, 2013 | IBRD-77650 | Int Charges | 1,987,699.50 |
Nov 15, 2013 | IBRD-77650 | Loan Repay | 2,569,492.00 |
Nov 15, 2013 | IBRD-77650 | Loan Repay | 3,462,858.00 |
May 15, 2015 | IBRD-77650 | Loan Repay | 2,624,590.80 |
May 15, 2015 | IBRD-77650 | Loan Repay | 3,546,769.20 |
May 15, 2015 | IBRD-77650 | Int Charges | 341,979.50 |
May 15, 2015 | IBRD-77650 | Int Charges | 1,737,404.90 |
May 15, 2014 | IBRD-77650 | Int Charges | 383,805.88 |
May 15, 2014 | IBRD-77650 | Int Charges | 1,904,937.20 |
May 15, 2014 | IBRD-77650 | Loan Repay | 2,585,061.50 |
May 15, 2014 | IBRD-77650 | Loan Repay | 3,489,565.20 |
Nov 15, 2015 | IBRD-77650 | Int Charges | 1,652,637.10 |
Nov 15, 2015 | IBRD-77650 | Loan Repay | 2,649,037.80 |
Nov 15, 2015 | IBRD-77650 | Loan Repay | 3,577,451.00 |
Nov 15, 2015 | IBRD-77650 | Int Charges | 351,744.97 |
Nov 15, 2016 | IBRD-77650 | Int Charges | 432,937.28 |
Nov 15, 2016 | IBRD-77650 | Int Charges | 1,480,903.90 |
Nov 15, 2016 | IBRD-77650 | Loan Repay | 2,697,494.50 |
Nov 15, 2016 | IBRD-77650 | Loan Repay | 3,638,629.00 |
May 15, 2016 | IBRD-77650 | Int Charges | 376,763.53 |
May 15, 2016 | IBRD-77650 | Int Charges | 1,567,136.00 |
May 15, 2016 | IBRD-77650 | Loan Repay | 2,673,534.50 |
May 15, 2016 | IBRD-77650 | Loan Repay | 3,608,042.50 |
May 15, 2017 | IBRD-77650 | Int Charges | 477,186.38 |
May 15, 2017 | IBRD-77650 | Int Charges | 1,393,940.50 |
May 15, 2017 | IBRD-77650 | Loan Repay | 2,714,156.80 |
May 15, 2017 | IBRD-77650 | Loan Repay | 3,665,336.50 |
Nov 15, 2017 | IBRD-77650 | Loan Repay | 2,738,117.00 |
Nov 15, 2017 | IBRD-77650 | Loan Repay | 3,695,928.00 |
Nov 15, 2017 | IBRD-77650 | Int Charges | 492,088.90 |
Nov 15, 2017 | IBRD-77650 | Int Charges | 1,306,339.00 |
Nov 15, 2018 | IBRD-77650 | Loan Repay | 2,785,967.50 |
Nov 15, 2018 | IBRD-77650 | Loan Repay | 3,759,472.20 |
Nov 15, 2018 | IBRD-77650 | Int Charges | 619,355.90 |
Nov 15, 2018 | IBRD-77650 | Int Charges | 1,128,886.00 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2011-02-11 |
Progress towards achievement of PDO | Moderately Satisfactory | 2011-02-11 |
Financial Management | Moderately Satisfactory | 2011-02-11 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-02-11 |
Counterpart Funding | Satisfactory | 2011-02-11 |
Project Management | Moderately Satisfactory | 2011-02-11 |
Overall Safeguards Rating | Satisfactory | 2011-02-11 |
Procurement | Moderately Satisfactory | 2011-02-11 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2011-02-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-29-2012 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 08-03-2012 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage reduction in vehicle operating costs on national and provincial roads included in the Project. | Value | 0.00 | 17.00 | 11.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment |
Percengate reduction in vehicle operating costs on Kabupaten roads included in the Project. | Value | 0.00 | 0.00 | 25.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | No data yet. VOC savings for remote and fragmented kabupaten roads have been difficult, and will be done together at end of project. |
Number of provinces using economic based priority setting procedures with staff who can apply them. | Value | 0.00 | 0.00 | 11.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | No data yet. |
Percentage of Project Kabupaten with adequate funding of routine maintenance of JJP network (based on budget allocations). | Value | 0.00 | 48.00 | 85.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | This needs more analysis at ICR. |
Percentage of works packages reported by the RDSCs in environmental monitoring reports. | Value | 0.00 | 43.00 | 100.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | This needs more analysis at ICR. |
Percentage of bid openings attended by one or more representatives of Civil Society. | Value | 0.00 | 100.00 | 100.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment |
Compliance with tender schedule at time of bidding. | Value | 0.00 | 0.00 | 90.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | No data yet, as it needs detailed analysis as the tender schedule has been substantially changed from start. |
Ratio of technical audits carried out by Inspectorate General. | Value | 0.00 | 0.00 | 52.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | No data yet. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Cumulative percent of project roads receiving betterment. | Value | 0.00 | 100.00 | 100.00 |
Date | May 1, 2004 | November 30, 2010 | January 31, 2011 | |
Comment | The achieved value is against the initially intended length, not against the revised achievable length. |
Cumulative percent of project roads receiving rehabilitation. | Value | 0.00 | 78.40 | 100.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | The achieved value is against the initially intended length, not against the revised achievable length. |
Cumulative percent of project bridges receiving rehabilitation or replacement. | Value | 0.00 | 91.80 | 100.00 |
Date | May 1, 2004 | November 30, 2010 | March 31, 2011 | |
Comment | The achieved value is against the initially intended length, not against the revised achievable length. |
Number of agreed technical assistance activities completed as planned. | Value | 0.00 | 2.00 | 4.00 |
Date | January 1, 2005 | November 30, 2010 | March 31, 2011 | |