Financier | Commitments |
---|---|
Borrower/Recipient | 21.00 |
P074426
Closed
Claudia Croce
N/A
March 13, 2002
(as of board presentation)
December 10, 2002
March 10, 2003
US$ 21.00 million
Empresas Publicas de Medellin
2003
US$ 0.00 million
B
Not Applicable
May 31, 2020
BANK APPROVED
December 19, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 21.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 21.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2014-02-15 |
Project Management | Satisfactory | 2014-02-15 |
Monitoring and Evaluation | Satisfactory | 2014-02-15 |
Overall | Low | 2014-02-15 |
Overall Safeguards Rating | Satisfactory | 2014-02-15 |
Counterpart Funding | Satisfactory | 2014-02-15 |
Overall Implementation Progress (IP) | Satisfactory | 2014-02-15 |
Overall Safeguards Rating | Satisfactory | 2014-02-15 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Emission Reductions Delivered to the Bank | Value | 0.00 | 153.52 | 433.69 |
Date | May 30, 2013 | December 31, 2013 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Wind based electricity generation facility generates electricity with a capacity of 19.5 MW and delivers its output to the nationalinterconnected grid. | Value | 0.00 | 18.20 | 19.50 |
Date | January 27, 2003 | May 30, 2013 | December 31, 2013 | |
Comment | No wind based electricity generation. | The current production averages around 54.85 GWh. Unit 15 is under maintenance. |
Improved access to potable water through water desalinization unit. | Value | No water service | The water desalinization plant has been in operati | Adequate functioning of the water desalinization p |
Date | January 27, 2003 | May 30, 2013 | December 31, 2013 | |
Comment |