Financier | Commitments |
---|---|
Borrower/Recipient | 5.50 |
International Bank for Reconstruction and Development | 18.50 |
P074543
Closed
Michael Carroll
N/A
August 6, 2001
(as of board presentation)
July 31, 2001
August 30, 2001
US$ 24.00 million
N/A
2002
US$ 18.50 million
B
Not Applicable
December 31, 2009
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Borrower/Recipient | 5.50 |
International Bank for Reconstruction and Development | 18.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 18.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 18.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 24.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 31, 2001 | IBRD-70700 | Loan Commitment | 18,500,000.00 |
Apr 15, 2014 | IBRD-74210 | Loan Repay | 236,669.23 |
Mar 15, 2014 | IBRD-70700 | Int Charges | 15,851.71 |
Mar 15, 2014 | IBRD-70700 | Loan Repay | 927,165.90 |
Apr 15, 2014 | IBRD-74210 | Int Charges | 11,677.80 |
Oct 15, 2013 | IBRD-74210 | Int Charges | 14,112.03 |
Oct 15, 2013 | IBRD-74210 | Loan Repay | 236,669.23 |
Sep 15, 2013 | IBRD-70700 | Int Charges | 21,043.10 |
Sep 15, 2013 | IBRD-70700 | Loan Repay | 927,165.90 |
Mar 15, 2016 | IBRD-70700 | Int Charges | 3,940.27 |
Mar 15, 2016 | IBRD-70700 | Loan Repay | 927,850.40 |
Sep 15, 2015 | IBRD-70700 | Loan Repay | 927,165.90 |
Sep 15, 2015 | IBRD-70700 | Int Charges | 6,636.86 |
Oct 15, 2015 | IBRD-74210 | Int Charges | 10,322.32 |
Oct 15, 2015 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2015 | IBRD-74210 | Int Charges | 9,548.07 |
Apr 15, 2015 | IBRD-74210 | Loan Repay | 236,669.23 |
Sep 15, 2014 | IBRD-70700 | Int Charges | 0.01 |
Sep 15, 2014 | IBRD-70700 | Int Charges | 11,944.09 |
Sep 15, 2014 | IBRD-70700 | Loan Repay | 927,165.90 |
Mar 15, 2015 | IBRD-70700 | Int Charges | 8,812.57 |
Mar 15, 2015 | IBRD-70700 | Loan Repay | 927,165.90 |
Oct 15, 2016 | IBRD-74210 | Int Charges | 15,218.84 |
Oct 15, 2016 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2016 | IBRD-74210 | Int Charges | 11,116.35 |
Apr 15, 2016 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2018 | IBRD-74210 | Int Charges | 108.27 |
Apr 15, 2018 | IBRD-74210 | Int Charges | 17,038.07 |
Apr 15, 2018 | IBRD-74210 | Loan Repay | 236,669.23 |
Oct 15, 2017 | IBRD-74210 | Int Charges | 17,865.56 |
Oct 15, 2017 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2017 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2017 | IBRD-74210 | Int Charges | 18,067.03 |
Apr 15, 2019 | IBRD-74210 | Int Charges | 20,747.20 |
Apr 15, 2019 | IBRD-74210 | Loan Repay | 236,669.23 |
Oct 15, 2018 | IBRD-74210 | Int Charges | 22,990.63 |
Oct 15, 2018 | IBRD-74210 | Loan Repay | 236,669.23 |
Oct 15, 2020 | IBRD-74210 | Int Charges | 5,341.61 |
Oct 15, 2020 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2020 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2020 | IBRD-74210 | Int Charges | 10,731.37 |
Oct 15, 2019 | IBRD-74210 | Int Charges | 17,324.20 |
Oct 15, 2019 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2021 | IBRD-74210 | Loan Repay | 236,669.23 |
Apr 15, 2021 | IBRD-74210 | Int Charges | 1,196.51 |
Oct 15, 2021 | IBRD-74210 | Int Charges | 565.42 |
Oct 15, 2021 | IBRD-74210 | Loan Repay | 236,669.16 |
Dec 19, 2006 | IBRD-74210 | Loan Commitment | 6,500,000.00 |
Oct 15, 2014 | IBRD-74210 | Loan Repay | 236,669.23 |
Oct 15, 2014 | IBRD-74210 | Int Charges | 10,286.25 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2010-05-28 |
Counterpart Funding | Satisfactory | 2010-05-28 |
Project Management | Satisfactory | 2010-05-28 |
Overall Safeguards Rating | Satisfactory | 2010-05-28 |
Progress towards achievement of PDO | Satisfactory | 2010-05-28 |
Financial Management | Satisfactory | 2010-05-28 |
Monitoring and Evaluation | Satisfactory | 2010-05-28 |
Overall Implementation Progress (IP) | Satisfactory | 2010-05-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2010 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 01-04-2011 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |