Northern Gaza Emergency Sewage Treatment (NGEST) Project

Development Objective

The project objectives are to: (i) mitigate the immediate gathering health and environmental safety threats to the communities surrounding the effluent lake at BLWTP; and (ii) Provide a satisfactory long-term solution to the treatment of wastewater for the Northern Government in Gaza.

Key Details

Project Details

  • P074595

  • Closed

  • Jean-Martin Brault , Adnan Ghosheh

  • Palestinian Leberation Organization

  • West Bank and Gaza

  • April 1, 2004

  • (as of board presentation)

    September 7, 2004

  • November 17, 2004

  • US$ 73.89 million

  • A

  • November 14, 2022

  • June 30, 2018

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
SWEDEN: Swedish Intl. Dev. Cooperation Agency (SIDA) 6.86
EC: European Investment Bank 5.40
FRANCE: French Agency for Development 21.60
EC: European Commission 7.94
BELGIUM: MOFA-Directorate-General for Int. Coop.(DGIC) 5.29
Special Financing 26.80
Borrower/Recipient 0.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 73.89
Total Project Cost** 74.39

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2018-06-29
Project Management Moderately Satisfactory 2018-06-29
Procurement Moderately Satisfactory 2018-06-29
Overall Implementation Progress (IP) Moderately Unsatisfactory 2018-06-29
Progress towards achievement of PDO Moderately Satisfactory 2018-06-29
Financial Management Satisfactory 2018-06-29
Monitoring and Evaluation Moderately Satisfactory 2018-06-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-20-2018
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-26-2019PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Effluent lake is drained and no longer a threat to the surrounding communities at Beit-Lahia WWTPValueNoYesYes
    DateOctober 29, 2004December 31, 2017November 7, 2018
    Comment
  • Wastewater collected and treated in accordance with Palestinian environmental standards suitable for groundwater infiltration and reuse (M3/day)Value0.0025000.0033000.00
    DateMarch 17, 2014December 31, 2017November 7, 2018
    Comment
  • Less than 5% increase in salinity and nitrate levels at monitoring wells within project site compared to before commissioning the plantValueNoYesYes
    DateMarch 17, 2014December 31, 2017November 7, 2018
    Comment
  • Establishment of O&M plan, including gradual increases of O&M financing and cost recovery for the NGEST WWTPValueNoYesYes
    DateMarch 17, 2014December 31, 2017November 7, 2018
    Comment
  • CMWU manages plant so that effluent standards are met at all timesValueNoYesYes
    DateMarch 17, 2014December 31, 2017November 7, 2018
    Comment
  • Direct project beneficiariesValue200000.00350000.00368978.00
    DateMarch 17, 2014December 31, 2017November 7, 2018
    Comment
  • Female beneficiariesValue50.0050.0050.00
    DateMarch 17, 2014December 31, 2017November 7, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • EIA, EMP and supplementary ESIA and remedial works studies are completed and their implementation is monitoredValueYesYesYes
    DateOctober 29, 2004December 31, 2017November 8, 2018
    Comment
  • North Gaza WWTP with a capacity of 35,000 cubic meters per days is constructed and operationalValueNoYesYes
    DateOctober 29, 2004December 31, 2017October 18, 2018
    Comment
  • Effluent recovery wells constructed and functionalValueNoYesYes
    DateOctober 29, 2004December 31, 2017November 8, 2018
    Comment
  • Volume(mass) of BOD pollution load removed by treatment plant under the projectValue1000.007000.002600.00
    DateOctober 29, 2004December 31, 2017November 8, 2018
    Comment
  • One and a half million M3 of effluent drained from the lake to the proposed NGWTP siteValueNoYesYes
    DateSeptember 29, 2004December 31, 2017November 8, 2018
    Comment
  • Wastewater pipeline installed (8 km), terminal pump station and infiltration basins are constructedValueNoYesYes
    DateSeptember 30, 2010December 31, 2017November 8, 2018
    Comment
  • Operation and maintenance of the infiltration basins are adequately supervisedValueNoYesYes
    DateMarch 17, 2014December 31, 2017November 8, 2018
    Comment
  • The NGWWTP is operated and maintained according to industry standardsValueNoYesYes
    DateMarch 17, 2014December 31, 2017November 8, 2018
    Comment
  • Effluent lake partially cleaned and leveledValueNoYesNo
    DateMarch 17, 2014December 31, 2017November 8, 2018
    Comment
  • Identified packages are tendered and completed satisfactorily in accordance with the project planValueYesYesYes
    DateDecember 31, 2013December 31, 2017November 8, 2018
    Comment
  • A construction manager to supervise the NGWWTP civil works is hired and adequately supervises the workValueNoYesYes
    DateMarch 17, 2014December 31, 2017November 8, 2018
    Comment
  • EA, EMP and supplementary ESIA implementation are adequately supervisedValueYesYesYes
    DateMarch 17, 2014December 31, 2017November 8, 2018
    Comment