Financier | Commitments |
---|---|
PROTOTYPE CARBON FUND | 3.50 |
P074619
Closed
Javier Freire Coloma
N/A
March 14, 2002
(as of board presentation)
February 4, 2002
February 4, 2002
US$ 3.50 million
N/A
2002
US$ 3.50 million
N/A
December 19, 2024
December 31, 2022
BANK APPROVED
Financier | Commitments |
---|---|
PROTOTYPE CARBON FUND | 3.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.50 |
Total Project Cost** | 3.50 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2012-11-18 |
Overall Implementation Progress (IP) | Satisfactory | 2012-11-18 |
Progress towards achievement of PDO | Moderately Satisfactory | 2012-11-18 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-11-18 |
Overall Safeguards Rating | Moderately Satisfactory | 2012-11-18 |
Project Management | Satisfactory | 2012-11-18 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Cumulated CERs (tCO2e) | Value | 0 | 0 | 1000000 |
Date | August 31, 2002 | August 2, 2011 | December 31, 2012 | |
Comment | No CER have been paid yet. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Emission Reductions | Value | 0.00 | 0.00 | 1000000.00 |
Date | August 2, 2011 | December 31, 2012 | ||
Comment |