Financier | Commitments |
---|---|
Borrower/Recipient | 0.53 |
IDA Credit | 4.76 |
P074762
Closed
Carmen Machicado
N/A
March 7, 2002
(as of board presentation)
December 17, 2002
May 23, 2003
US$ 5.29 million
N/A
2003
US$ 4.76 million
C
Not Applicable
July 12, 2007
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Borrower/Recipient | 0.53 |
IDA Credit | 4.76 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 4.76 |
IBRD + IDA Commitment | 4.76 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 5.29 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2019 | IDA-37260 | Int Charges | 10,494.99 |
Jun 15, 2022 | IDA-37260 | Loan Repay | 31,727.72 |
Jun 15, 2022 | IDA-37260 | Int Charges | 9,907.01 |
Jun 15, 2022 | IDA-37260 | Int Charges | 9,907.01 |
Jun 15, 2022 | IDA-37260 | Loan Repay | 490.24 |
Jun 15, 2021 | IDA-37260 | Int Charges | 852.72 |
Jun 15, 2021 | IDA-37260 | Int Charges | 852.72 |
Jun 15, 2021 | IDA-37260 | Int Charges | 10,624.17 |
Jun 15, 2021 | IDA-37260 | Int Charges | 10,624.17 |
Jun 15, 2021 | IDA-37260 | Loan Repay | 34,814.86 |
Dec 15, 2020 | IDA-37260 | Int Charges | 10,236.02 |
Dec 15, 2020 | IDA-37260 | Int Charges | 10,236.02 |
Jun 15, 2023 | IDA-37260 | Int Charges | 1,717.79 |
Jun 15, 2023 | IDA-37260 | Int Charges | 1,717.79 |
Jun 15, 2023 | IDA-37260 | Loan Repay | 64,571.87 |
Jun 15, 2023 | IDA-37260 | Int Charges | 9,685.78 |
Jun 15, 2023 | IDA-37260 | Int Charges | 9,685.78 |
Dec 15, 2022 | IDA-37260 | Loan Repay | 1,093.77 |
Dec 15, 2022 | IDA-37260 | Loan Repay | 31,099.77 |
Dec 15, 2022 | IDA-37260 | Int Charges | 8,065.92 |
Dec 15, 2022 | IDA-37260 | Int Charges | 8,065.92 |
Dec 15, 2021 | IDA-37260 | Int Charges | 10,515.11 |
Dec 15, 2021 | IDA-37260 | Int Charges | 10,515.11 |
Dec 15, 2021 | IDA-37260 | Int Charges | 332.36 |
Dec 15, 2021 | IDA-37260 | Int Charges | 332.36 |
Dec 15, 2021 | IDA-37260 | Loan Repay | 33,783.60 |
Dec 17, 2002 | IDA-37260 | Loan Commitment | 4,165,909.50 |
Dec 17, 2002 | IDA-3726A | Loan Commitment | 594,090.50 |
Jun 15, 2024 | IDA-37260 | Int Charges | 1,682.39 |
Jun 15, 2024 | IDA-37260 | Int Charges | 1,682.39 |
Jun 15, 2024 | IDA-37260 | Loan Repay | 63,748.89 |
Jun 15, 2024 | IDA-37260 | Int Charges | 9,013.54 |
Jun 15, 2024 | IDA-37260 | Int Charges | 9,013.54 |
Dec 15, 2023 | IDA-37260 | Loan Repay | 1,136.25 |
Dec 15, 2023 | IDA-37260 | Loan Repay | 63,733.65 |
Dec 15, 2023 | IDA-37260 | Int Charges | 7,775.24 |
Dec 15, 2023 | IDA-37260 | Int Charges | 7,775.24 |
Dec 15, 2013 | IDA-37260 | Int Charges | 577.16 |
Dec 15, 2013 | IDA-37260 | Int Charges | 577.16 |
Dec 15, 2013 | IDA-37260 | Int Charges | 13,548.05 |
Dec 15, 2013 | IDA-37260 | Int Charges | 13,548.05 |
Dec 15, 2013 | IDA-37260 | Loan Repay | 37,202.51 |
Dec 15, 2014 | IDA-37260 | Loan Repay | 35,069.08 |
Dec 15, 2014 | IDA-37260 | Int Charges | 12,859.38 |
Dec 15, 2014 | IDA-37260 | Int Charges | 12,859.38 |
Dec 15, 2014 | IDA-37260 | Loan Repay | 283.31 |
Jun 15, 2014 | IDA-37260 | Int Charges | 263.63 |
Jun 15, 2014 | IDA-37260 | Int Charges | 263.63 |
Jun 15, 2014 | IDA-37260 | Loan Repay | 37,242.42 |
Jun 15, 2014 | IDA-37260 | Int Charges | 13,686.59 |
Jun 15, 2014 | IDA-37260 | Int Charges | 13,686.59 |
Jun 15, 2015 | IDA-37260 | Loan Repay | 757.13 |
Jun 15, 2015 | IDA-37260 | Loan Repay | 33,216.62 |
Dec 15, 2015 | IDA-37260 | Int Charges | 1,038.00 |
Dec 15, 2015 | IDA-37260 | Int Charges | 1,038.00 |
Dec 15, 2015 | IDA-37260 | Loan Repay | 33,718.04 |
Dec 15, 2015 | IDA-37260 | Int Charges | 12,012.08 |
Dec 15, 2015 | IDA-37260 | Int Charges | 12,012.08 |
Jun 15, 2015 | IDA-37260 | Int Charges | 11,184.71 |
Jun 15, 2015 | IDA-37260 | Int Charges | 11,184.71 |
Jun 15, 2016 | IDA-37260 | Loan Repay | 808.30 |
Jun 15, 2016 | IDA-37260 | Loan Repay | 33,209.22 |
Jun 15, 2016 | IDA-37260 | Int Charges | 11,970.88 |
Jun 15, 2016 | IDA-37260 | Int Charges | 11,970.88 |
Dec 15, 2016 | IDA-37260 | Loan Repay | 32,410.52 |
Dec 15, 2016 | IDA-37260 | Int Charges | 19.33 |
Dec 15, 2016 | IDA-37260 | Int Charges | 19.33 |
Dec 15, 2016 | IDA-37260 | Int Charges | 11,303.19 |
Dec 15, 2016 | IDA-37260 | Int Charges | 11,303.19 |
Jun 15, 2017 | IDA-37260 | Loan Repay | 1,268.47 |
Jun 15, 2017 | IDA-37260 | Int Charges | 10,767.48 |
Jun 15, 2017 | IDA-37260 | Int Charges | 10,767.48 |
Jun 15, 2017 | IDA-37260 | Loan Repay | 32,168.23 |
Dec 15, 2017 | IDA-37260 | Int Charges | 11,673.29 |
Dec 15, 2017 | IDA-37260 | Int Charges | 11,673.29 |
Dec 15, 2017 | IDA-37260 | Int Charges | 785.91 |
Dec 15, 2017 | IDA-37260 | Int Charges | 785.91 |
Dec 15, 2017 | IDA-37260 | Loan Repay | 34,207.43 |
Dec 15, 2018 | IDA-37260 | Loan Repay | 1,403.25 |
Dec 15, 2018 | IDA-37260 | Loan Repay | 31,955.80 |
Dec 15, 2018 | IDA-37260 | Int Charges | 11,133.58 |
Dec 15, 2018 | IDA-37260 | Int Charges | 11,133.58 |
Jun 15, 2018 | IDA-37260 | Loan Repay | 23.42 |
Jun 15, 2018 | IDA-37260 | Loan Repay | 34,111.19 |
Jun 15, 2018 | IDA-37260 | Int Charges | 11,520.43 |
Jun 15, 2018 | IDA-37260 | Int Charges | 11,520.43 |
Jun 15, 2019 | IDA-37260 | Loan Repay | 608.53 |
Jun 15, 2019 | IDA-37260 | Loan Repay | 32,855.51 |
Jun 15, 2019 | IDA-37260 | Int Charges | 11,043.12 |
Jun 15, 2019 | IDA-37260 | Int Charges | 11,043.12 |
Dec 15, 2020 | IDA-37260 | Int Charges | 429.02 |
Dec 15, 2020 | IDA-37260 | Int Charges | 429.02 |
Dec 15, 2020 | IDA-37260 | Loan Repay | 34,786.07 |
Jun 15, 2020 | IDA-37260 | Int Charges | 427.17 |
Jun 15, 2020 | IDA-37260 | Int Charges | 427.17 |
Jun 15, 2020 | IDA-37260 | Loan Repay | 33,367.76 |
Jun 15, 2020 | IDA-37260 | Int Charges | 10,349.55 |
Jun 15, 2020 | IDA-37260 | Int Charges | 10,349.55 |
Dec 15, 2019 | IDA-37260 | Loan Repay | 231.03 |
Dec 15, 2019 | IDA-37260 | Loan Repay | 33,251.39 |
Dec 15, 2019 | IDA-37260 | Int Charges | 10,494.99 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2007-08-28 |
Monitoring and Evaluation | Satisfactory | 2007-08-28 |
Project Management | Moderately Satisfactory | 2007-08-28 |
Financial Management | Satisfactory | 2007-08-28 |
Overall Implementation Progress (IP) | Satisfactory | 2007-08-28 |
Counterpart Funding | Satisfactory | 2007-08-28 |
Procurement | Satisfactory | 2007-08-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-22-2008 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Substantial |
Borrower Performance | Moderately Satisfactory |
Government Performance | Not Applicable |
Implementing Agency | Not Applicable |
INDICATOR | ICR REVIEW: 07-11-2008 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Non-evaluable | N/a |