Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 84.29 |
Borrower/Recipient | 62.10 |
P075173
Closed
Chanin Manopiniwes
N/A
February 5, 2002
(as of board presentation)
December 9, 2003
March 15, 2004
US$ 146.39 million
N/A
2004
US$ 84.29 million
B
March 11, 2021
June 30, 2013
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 84.29 |
Borrower/Recipient | 62.10 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 84.29 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 84.29 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 146.39 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2017 | IBRD-47210 | Int Charges | 258,189.55 |
Feb 15, 2017 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Aug 15, 2016 | IBRD-47210 | Int Charges | 216,332.08 |
Aug 15, 2016 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Feb 15, 2018 | IBRD-47210 | Int Charges | 238,574.40 |
Feb 15, 2018 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Aug 15, 2017 | IBRD-47210 | Int Charges | 249,796.23 |
Aug 15, 2017 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Feb 15, 2019 | IBRD-47210 | Int Charges | 267,492.20 |
Feb 15, 2019 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Aug 15, 2018 | IBRD-47210 | Int Charges | 265,830.56 |
Aug 15, 2018 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Feb 15, 2020 | IBRD-47210 | Int Charges | 135,438.30 |
Feb 15, 2020 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Aug 15, 2019 | IBRD-47210 | Int Charges | 228,326.58 |
Aug 15, 2019 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Feb 15, 2021 | IBRD-47210 | Int Charges | 15,069.88 |
Feb 15, 2021 | IBRD-47210 | Loan Repay | 3,552,359.00 |
Aug 15, 2020 | IBRD-47210 | Int Charges | 77,751.98 |
Aug 15, 2020 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Dec 9, 2003 | IBRD-47210 | Loan Commitment | 84,290,000.00 |
Mar 18, 2010 | IBRD-77750 | Loan Commitment | 79,300,000.00 |
Aug 15, 2013 | IBRD-47210 | Int Charges | 200,497.05 |
Aug 15, 2013 | IBRD-47210 | Loan Repay | 3,502,468.50 |
Feb 15, 2014 | IBRD-47210 | Int Charges | 177,393.08 |
Feb 15, 2014 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Oct 21, 2013 | IBRD-77750 | Loan Disb | 4,026.57 |
Dec 15, 2013 | IBRD-77750 | Int Charges | 748.59 |
Oct 31, 2013 | IBRD-77750 | Loan Cancel | 79,076,416.00 |
Jul 5, 2013 | IBRD-47210 | Loan Disb | -2.00 |
Jul 5, 2013 | IBRD-47210 | Loan Cancel | 32.00 |
Aug 26, 2013 | IBRD-77750 | Loan Disb | -615.88 |
Jun 15, 2015 | IBRD-77750 | Loan Repay | 11,179.09 |
Jun 15, 2015 | IBRD-77750 | Int Charges | 723.42 |
Aug 15, 2014 | IBRD-47210 | Int Charges | 145,603.45 |
Aug 15, 2014 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Dec 15, 2014 | IBRD-77750 | Int Charges | 670.56 |
Feb 15, 2015 | IBRD-47210 | Int Charges | 144,444.19 |
Feb 15, 2015 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Jun 15, 2014 | IBRD-77750 | Int Charges | 4.13 |
Jun 15, 2014 | IBRD-77750 | Int Charges | 689.50 |
Feb 15, 2014 | IBRD-47210 | Int Charges | 0.04 |
Aug 15, 2015 | IBRD-47210 | Int Charges | 148,096.42 |
Aug 15, 2015 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Feb 15, 2016 | IBRD-47210 | Loan Repay | 3,502,466.50 |
Feb 15, 2016 | IBRD-47210 | Int Charges | 0.01 |
Feb 15, 2016 | IBRD-47210 | Int Charges | 169,567.45 |
Sep 15, 2015 | IBRD-77750 | Int Charges | 417.95 |
Sep 15, 2015 | IBRD-77750 | Loan Repay | 212,402.45 |
Name | Review | Date |
---|---|---|
Procurement | Unsatisfactory | 2013-06-26 |
Financial Management | Satisfactory | 2013-06-26 |
Monitoring and Evaluation | Satisfactory | 2013-06-26 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2013-06-26 |
Project Management | Moderately Unsatisfactory | 2013-06-26 |
Counterpart Funding | Satisfactory | 2013-06-26 |
Overall Implementation Progress (IP) | Unsatisfactory | 2013-06-26 |
Overall Safeguards Rating | Satisfactory | 2013-06-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2013 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Unsatisfactory |
Government Performance | Unsatisfactory |
Implementing Agency | Moderately Unsatisfactory |
INDICATOR | ICR REVIEW: 06-27-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduced average unit cost/km of maintenance in real terms | Value | 403 | 325.6 | 362.7 |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | on the baseline of 403 Baht/M2 | 117km of additional maintenance in late 2011 | Achieved (362.7 Baht/m2 = Baseline - 10%) |
Asset value of road network increased by 0.2% by EOP (or decline reversed) | Value | 323.60 | 331.62 | 324.25 |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | 291.28 million Baht/km for maintenance project sections + 32.32 million Baht/ km for 3 widening projects | Not updated as it was achieved under original loan | Achieved under original loan (324.25 Baht/km = Baseline + 0.2%) |
Reduce vehicle operating costs by 10-15% on target roads | Value | 4.68 | 4.53 | 3.978-4.212 |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | 4.68 Baht per vehicle-km | Based on target roads for the case study with control factors | 3.978-4.212 Baht/v-km represent 10-15% reduction from baseline |
National road database established, updated annually, and used for planning, programming, budgeting, and monitoring of highway investments and maintenance expenditure | Value | No database | Database functional | Established and functional |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | DOH continues to improve the database. | Achieved under original loan |
Road user costs reduced by at least 10% on target roads under additional financing | Value | 6.35 | 6.35 | 5.72 |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | 6.35 Baht/km. for vehicle type: Car<7 passengers | Not updated as the additional financing loan is canceled. | Not achieved under the additional financing loan (5.715 Baht/km = Baseline - 10%) |
Roads rehabilitated, Non-rural | Value | 0.00 | 1556.00 | 960.00 |
Date | March 3, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved using conventional methods with SMEs | Achieved under original loan |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average roughness of target roads less than 3.5 IRI. | Value | 4.43 | 2.24 | less than 3.5 IRI |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | IRI | Not updated. All maintenance works completed as per specification. | Achieved for targeted roads |
73 km of priority national highways widened to four lanes as per specifications | Value | 0 km | 86.27 km | 73 km |
Date | March 15, 2004 | June 12, 2013 | June 30, 2009 | |
Comment | Achieved. The actual length was longer than length at Appraisal due to addition of a bypass. | Achieved |
Number of fatalities reduced by 80% at improved locations | Value | 50 fatalities at 38 locations | 10 fatalities at improved locations | 10 fatalities at improved locations |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | No more safety works have been carried out under the project since the update. | Achieved |
Periodic maintenance of 960 km of project roads completed using conventional contracting methods with SMEs | Value | 0 Km | 1,556 km | 960 Km |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved using conventional methods with SMEs | Achieved |
Pilot long-term performance-based management and maintenance contract designed for | Value | No design. | Design work substantially completed and will be co | Design completed |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | To be completed by June 30, 2013 | Substantially achieved |
Three overpasses constructed at critical locations as per specifications | Value | 0 | 3 | 3 |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved with original loan | Achieved |
Average travel time reduced on widened sections by 20-30% | Value | Total of 74.46 minutes of travel time on three wid | 53.60 minutes (avg 96.57 km/hr) | Total of 52.2-59.6 minutes of travel time on three |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved for the completed sections with original loan. | Achieved |
Average delays reduced at improved intersections by 60% | Value | 76.17 seconds average delay in three improved loca | 27.08 seconds average delay in three improved loca | 30.47 seconds average delay in three improved loca |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | No update as the works were completed. | Achieved |
66 hazardous locations improved as per specifications | Value | 0 | Over 100 | 66 |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Similar works are taken by DOH as routine. | Achieved |
Road safety awareness campaigns carried out | Value | No campaigns | Campaigns carried out | Campaigns carried out |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved with original loan | Achieved |
Accident Research Center established at AIT in collaboration with GRSP | Value | Center not established | Center established and well regarded in Thailand | Center established |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved with original loan | Achieved |
Modern centralized database, road maintenance management system and bridge management system implemented and operational | Value | No | Systems are operational. | System operational |
Date | April 30, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved |
Framework and case study for PPP in highways developed and results adopted by DOH | Value | Framework and study not developed | Study completed, and framework being followed by D | Framework and study adopted |
Date | March 15, 2004 | June 12, 2013 | June 30, 2013 | |
Comment | Achieved with original loan | Achieved |
Annual report covering DOH#s environmental performance disseminated to the public | Value | Not available for dissemination | Reports disseminated | Reports disseminated |
Date | June 12, 2013 | June 30, 2013 | ||
Comment | Achieved under original loan | Achieved |
Additional 216 km of priority national highways widened for four lanes as per specification | Value | 0.00 | 0.00 | 216.00 |
Date | May 21, 2010 | June 12, 2013 | June 30, 2013 | |
Comment | Civil Works not started prior to loan cancellation. | Not achieved |
PPP financing for the proposed Bang Pa-in to Nakhon Ratchasima Motorway reached bidding stage | Value | No | No | No |
Date | May 21, 2010 | June 12, 2013 | June 30, 2013 | |
Comment | Procurement process canceled due to loan cancellation. | Not achieved |