Highways Management Project

Abstract*

The development objective of the Highways Management Project forThailand is to enhance the efficiency, productive use, and management of the road network. Specifically, it supports the commercialization of the road sector, strengthens the operations of the Department of Highways, helps preserve road assets, and improves competition and transparency in the award of contracts. Furthermore, the project will reduce traffic accidents and fatalities on...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective/outcomes have not been changed.

Key Details

Project Details

  • P075173

  • Closed

  • Chanin Manopiniwes

  • N/A

  • Thailand

  • February 5, 2002

  • (as of board presentation)

    December 9, 2003

  • March 15, 2004

  • US$ 84.29 million

  • B

  • March 11, 2021

  • June 30, 2013

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 84.29
Borrower/Recipient 62.10

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 84.29
IDA Commitment N/A
IBRD + IDA Commitment 84.29
Lending Instrument
Grant Amount N/A
Total Project Cost** 146.39

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 15, 2017 IBRD-47210 Int Charges 258,189.55
Feb 15, 2017 IBRD-47210 Loan Repay 3,502,466.50
Aug 15, 2016 IBRD-47210 Int Charges 216,332.08
Aug 15, 2016 IBRD-47210 Loan Repay 3,502,466.50
Feb 15, 2018 IBRD-47210 Int Charges 238,574.40
Feb 15, 2018 IBRD-47210 Loan Repay 3,502,466.50
Aug 15, 2017 IBRD-47210 Int Charges 249,796.23
Aug 15, 2017 IBRD-47210 Loan Repay 3,502,466.50
Feb 15, 2019 IBRD-47210 Int Charges 267,492.20
Feb 15, 2019 IBRD-47210 Loan Repay 3,502,466.50
Aug 15, 2018 IBRD-47210 Int Charges 265,830.56
Aug 15, 2018 IBRD-47210 Loan Repay 3,502,466.50
Feb 15, 2020 IBRD-47210 Int Charges 135,438.30
Feb 15, 2020 IBRD-47210 Loan Repay 3,502,466.50
Aug 15, 2019 IBRD-47210 Int Charges 228,326.58
Aug 15, 2019 IBRD-47210 Loan Repay 3,502,466.50
Feb 15, 2021 IBRD-47210 Int Charges 15,069.88
Feb 15, 2021 IBRD-47210 Loan Repay 3,552,359.00
Aug 15, 2020 IBRD-47210 Int Charges 77,751.98
Aug 15, 2020 IBRD-47210 Loan Repay 3,502,466.50
Dec 9, 2003 IBRD-47210 Loan Commitment 84,290,000.00
Mar 18, 2010 IBRD-77750 Loan Commitment 79,300,000.00
Aug 15, 2013 IBRD-47210 Int Charges 200,497.05
Aug 15, 2013 IBRD-47210 Loan Repay 3,502,468.50
Feb 15, 2014 IBRD-47210 Int Charges 177,393.08
Feb 15, 2014 IBRD-47210 Loan Repay 3,502,466.50
Oct 21, 2013 IBRD-77750 Loan Disb 4,026.57
Dec 15, 2013 IBRD-77750 Int Charges 748.59
Oct 31, 2013 IBRD-77750 Loan Cancel 79,076,416.00
Jul 5, 2013 IBRD-47210 Loan Disb -2.00
Jul 5, 2013 IBRD-47210 Loan Cancel 32.00
Aug 26, 2013 IBRD-77750 Loan Disb -615.88
Jun 15, 2015 IBRD-77750 Loan Repay 11,179.09
Jun 15, 2015 IBRD-77750 Int Charges 723.42
Aug 15, 2014 IBRD-47210 Int Charges 145,603.45
Aug 15, 2014 IBRD-47210 Loan Repay 3,502,466.50
Dec 15, 2014 IBRD-77750 Int Charges 670.56
Feb 15, 2015 IBRD-47210 Int Charges 144,444.19
Feb 15, 2015 IBRD-47210 Loan Repay 3,502,466.50
Jun 15, 2014 IBRD-77750 Int Charges 4.13
Jun 15, 2014 IBRD-77750 Int Charges 689.50
Feb 15, 2014 IBRD-47210 Int Charges 0.04
Aug 15, 2015 IBRD-47210 Int Charges 148,096.42
Aug 15, 2015 IBRD-47210 Loan Repay 3,502,466.50
Feb 15, 2016 IBRD-47210 Loan Repay 3,502,466.50
Feb 15, 2016 IBRD-47210 Int Charges 0.01
Feb 15, 2016 IBRD-47210 Int Charges 169,567.45
Sep 15, 2015 IBRD-77750 Int Charges 417.95
Sep 15, 2015 IBRD-77750 Loan Repay 212,402.45

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Unsatisfactory 2013-06-26
Financial Management Satisfactory 2013-06-26
Monitoring and Evaluation Satisfactory 2013-06-26
Progress towards achievement of PDO Moderately Unsatisfactory 2013-06-26
Project Management Moderately Unsatisfactory 2013-06-26
Counterpart Funding Satisfactory 2013-06-26
Overall Implementation Progress (IP) Unsatisfactory 2013-06-26
Overall Safeguards Rating Satisfactory 2013-06-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2013
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-27-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduced average unit cost/km of maintenance in real termsValue403325.6362.7
    DateMarch 15, 2004June 12, 2013June 30, 2013
    Commenton the baseline of 403 Baht/M2117km of additional maintenance in late 2011Achieved (362.7 Baht/m2 = Baseline - 10%)
  • Asset value of road network increased by 0.2% by EOP (or decline reversed)Value323.60331.62324.25
    DateMarch 15, 2004June 12, 2013June 30, 2013
    Comment291.28 million Baht/km for maintenance project sections + 32.32 million Baht/ km for 3 widening projectsNot updated as it was achieved under original loanAchieved under original loan (324.25 Baht/km = Baseline + 0.2%)
  • Reduce vehicle operating costs by 10-15% on target roadsValue4.684.533.978-4.212
    DateMarch 15, 2004June 12, 2013June 30, 2013
    Comment4.68 Baht per vehicle-kmBased on target roads for the case study with control factors3.978-4.212 Baht/v-km represent 10-15% reduction from baseline
  • National road database established, updated annually, and used for planning, programming, budgeting, and monitoring of highway investments and maintenance expenditureValueNo databaseDatabase functionalEstablished and functional
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentDOH continues to improve the database.Achieved under original loan
  • Road user costs reduced by at least 10% on target roads under additional financingValue6.356.355.72
    DateMarch 15, 2004June 12, 2013June 30, 2013
    Comment6.35 Baht/km. for vehicle type: Car<7 passengersNot updated as the additional financing loan is canceled.Not achieved under the additional financing loan (5.715 Baht/km = Baseline - 10%)
  • Roads rehabilitated, Non-ruralValue0.001556.00960.00
    DateMarch 3, 2004June 12, 2013June 30, 2013
    CommentAchieved using conventional methods with SMEsAchieved under original loan

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average roughness of target roads less than 3.5 IRI.Value4.432.24less than 3.5 IRI
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentIRINot updated. All maintenance works completed as per specification.Achieved for targeted roads
  • 73 km of priority national highways widened to four lanes as per specificationsValue0 km86.27 km73 km
    DateMarch 15, 2004June 12, 2013June 30, 2009
    CommentAchieved. The actual length was longer than length at Appraisal due to addition of a bypass.Achieved
  • Number of fatalities reduced by 80% at improved locationsValue50 fatalities at 38 locations10 fatalities at improved locations10 fatalities at improved locations
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentNo more safety works have been carried out under the project since the update.Achieved
  • Periodic maintenance of 960 km of project roads completed using conventional contracting methods with SMEsValue0 Km1,556 km960 Km
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentAchieved using conventional methods with SMEsAchieved
  • Pilot long-term performance-based management and maintenance contract designed forValueNo design.Design work substantially completed and will be coDesign completed
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentTo be completed by June 30, 2013Substantially achieved
  • Three overpasses constructed at critical locations as per specificationsValue033
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentAchieved with original loanAchieved
  • Average travel time reduced on widened sections by 20-30%ValueTotal of 74.46 minutes of travel time on three wid53.60 minutes (avg 96.57 km/hr)Total of 52.2-59.6 minutes of travel time on three
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentAchieved for the completed sections with original loan.Achieved
  • Average delays reduced at improved intersections by 60%Value76.17 seconds average delay in three improved loca27.08 seconds average delay in three improved loca30.47 seconds average delay in three improved loca
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentNo update as the works were completed.Achieved
  • 66 hazardous locations improved as per specificationsValue0Over 10066
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentSimilar works are taken by DOH as routine.Achieved
  • Road safety awareness campaigns carried outValueNo campaignsCampaigns carried outCampaigns carried out
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentAchieved with original loanAchieved
  • Accident Research Center established at AIT in collaboration with GRSPValueCenter not establishedCenter established and well regarded in ThailandCenter established
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentAchieved with original loanAchieved
  • Modern centralized database, road maintenance management system and bridge management system implemented and operationalValueNoSystems are operational.System operational
    DateApril 30, 2004June 12, 2013June 30, 2013
    CommentAchieved
  • Framework and case study for PPP in highways developed and results adopted by DOHValueFramework and study not developedStudy completed, and framework being followed by DFramework and study adopted
    DateMarch 15, 2004June 12, 2013June 30, 2013
    CommentAchieved with original loanAchieved
  • Annual report covering DOH#s environmental performance disseminated to the publicValueNot available for disseminationReports disseminatedReports disseminated
    DateJune 12, 2013June 30, 2013
    CommentAchieved under original loanAchieved
  • Additional 216 km of priority national highways widened for four lanes as per specificationValue0.000.00216.00
    DateMay 21, 2010June 12, 2013June 30, 2013
    CommentCivil Works not started prior to loan cancellation.Not achieved
  • PPP financing for the proposed Bang Pa-in to Nakhon Ratchasima Motorway reached bidding stageValueNoNoNo
    DateMay 21, 2010June 12, 2013June 30, 2013
    CommentProcurement process canceled due to loan cancellation.Not achieved