Financier | Commitments |
---|---|
Borrower/Recipient | 2.38 |
International Bank for Reconstruction and Development | 99.40 |
P075231
Closed
Kateryna Petryna
N/A
February 2, 2004
(as of board presentation)
November 17, 2005
April 4, 2006
US$ 101.78 million
N/A
2006
US$ 99.40 million
C
Not Applicable
January 1, 2013
BANK APPROVED
September 12, 2013
Financier | Commitments |
---|---|
Borrower/Recipient | 2.38 |
International Bank for Reconstruction and Development | 99.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 99.40 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 99.40 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 101.78 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 17, 2005 | IBRD-48070 | Loan Commitment | 99,400,000.00 |
May 15, 2024 | IBRD-48070 | Int Charges | 3,827.70 |
May 15, 2024 | IBRD-48070 | Int Charges | 498,119.84 |
May 15, 2024 | IBRD-48070 | Loan Repay | 3,804,145.80 |
Nov 15, 2023 | IBRD-48070 | Int Charges | 13,817.61 |
Nov 15, 2023 | IBRD-48070 | Int Charges | 582,273.20 |
Nov 15, 2023 | IBRD-48070 | Loan Repay | 3,725,852.20 |
May 15, 2023 | IBRD-48070 | Int Charges | 37,360.95 |
May 15, 2023 | IBRD-48070 | Int Charges | 571,920.50 |
May 15, 2023 | IBRD-48070 | Loan Repay | 3,652,164.20 |
Nov 15, 2022 | IBRD-48070 | Int Charges | 395,726.62 |
Nov 15, 2022 | IBRD-48070 | Loan Repay | 3,573,870.50 |
May 15, 2022 | IBRD-48070 | Int Charges | 113,664.32 |
May 15, 2022 | IBRD-48070 | Loan Repay | 3,504,788.00 |
Nov 15, 2021 | IBRD-48070 | Int Charges | 121,836.78 |
Nov 15, 2021 | IBRD-48070 | Loan Repay | 3,431,100.00 |
Nov 15, 2020 | IBRD-48070 | Loan Repay | 3,292,934.80 |
May 15, 2021 | IBRD-48070 | Int Charges | 137,422.94 |
May 15, 2021 | IBRD-48070 | Loan Repay | 3,362,017.50 |
Nov 15, 2020 | IBRD-48070 | Int Charges | 238,513.69 |
May 15, 2020 | IBRD-48070 | Int Charges | 527,284.70 |
May 15, 2020 | IBRD-48070 | Loan Repay | 3,228,457.80 |
Nov 15, 2019 | IBRD-48070 | Int Charges | 733,926.10 |
Nov 15, 2019 | IBRD-48070 | Loan Repay | 3,163,980.80 |
May 15, 2019 | IBRD-48070 | Loan Repay | 3,099,503.80 |
May 15, 2019 | IBRD-48070 | Int Charges | 834,953.94 |
Nov 15, 2018 | IBRD-48070 | Int Charges | 803,533.10 |
Nov 15, 2018 | IBRD-48070 | Loan Repay | 3,035,026.80 |
May 15, 2018 | IBRD-48070 | Loan Repay | 2,975,155.20 |
May 15, 2018 | IBRD-48070 | Int Charges | 580,022.40 |
Nov 15, 2017 | IBRD-48070 | Loan Repay | 2,915,283.50 |
Nov 15, 2017 | IBRD-48070 | Int Charges | 563,527.50 |
May 15, 2017 | IBRD-48070 | Int Charges | 513,301.62 |
May 15, 2017 | IBRD-48070 | Loan Repay | 2,855,412.00 |
Nov 15, 2016 | IBRD-48070 | Int Charges | 417,361.75 |
Nov 15, 2016 | IBRD-48070 | Loan Repay | 2,795,540.50 |
May 15, 2016 | IBRD-48070 | Int Charges | 318,578.10 |
May 15, 2016 | IBRD-48070 | Loan Repay | 2,740,274.50 |
Nov 15, 2015 | IBRD-48070 | Int Charges | 260,143.19 |
Nov 15, 2015 | IBRD-48070 | Loan Repay | 2,685,008.50 |
May 15, 2015 | IBRD-48070 | Int Charges | 225,538.69 |
May 15, 2015 | IBRD-48070 | Loan Repay | 2,629,742.50 |
May 15, 2014 | IBRD-48070 | Int Charges | 241,431.20 |
May 15, 2014 | IBRD-48070 | Loan Repay | 2,523,815.80 |
Nov 15, 2013 | IBRD-48070 | Int Charges | 134.83 |
Nov 15, 2013 | IBRD-48070 | Int Charges | 291.67 |
Nov 15, 2013 | IBRD-48070 | Int Charges | 326.66 |
Nov 15, 2013 | IBRD-48070 | Int Charges | 277,784.30 |
Nov 15, 2013 | IBRD-48070 | Loan Repay | 2,473,155.20 |
Nov 15, 2014 | IBRD-48070 | Int Charges | 222,116.73 |
Nov 15, 2014 | IBRD-48070 | Loan Repay | 2,574,476.20 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2012-12-25 |
Procurement | Moderately Unsatisfactory | 2012-12-25 |
Counterpart Funding | Satisfactory | 2012-12-25 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2012-12-25 |
Project Management | Moderately Unsatisfactory | 2012-12-25 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-12-25 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2012-12-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2013 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 11-11-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in percentage of social assistance cash benefits received by poor families | Value | 42.6% in 2005 | 42.3% in 2011 | 60% |
Date | October 20, 2005 | December 11, 2012 | January 1, 2013 | |
Comment | This is the assessment of targeting accuracy of cash benefits in Ukraine in 2011 that is assessed on full set of 2011 HBS data. |
Reduction in time for client in-take in local welfare office | Value | 4.5 hours in 2005 | 1.2 hours in 2011 | 1.5 hours |
Date | October 20, 2005 | December 11, 2012 | January 1, 2013 | |
Comment | average time in 2011. |
Increase in number of benefits that are processed per month per staff of local welfare office | Value | 260 in 2005 | 498 in 2011 | 528 |
Date | October 20, 2005 | December 11, 2012 | January 1, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Standard office model is developed, piloted, evaluated and formally approved | Value | 0 | Formally approved model | Formally approved model |
Date | October 20, 2005 | June 30, 2011 | December 31, 2009 | |
Comment | 99% of the LWOs are using the Standard office model approved back in 2007. |
# of rayon/city welfare offices implemented new "single window" service model | Value | 20 in 2005 | 756 | 756 |
Date | October 20, 2005 | December 11, 2012 | January 1, 2013 | |
Comment | Initially, 754; since project approval in 2005, the number of the LWOs has increased to 756. |
# of oblast social welfare offices capable of carrying out analyses and monitoring of the benefit payments. | Value | 0 | 2 | 27 |
Date | October 20, 2005 | December 11, 2012 | January 1, 2013 | |
Comment | Not yet achieved; in progress. The underlying MIS software is in operational acceptance testing in Vinnytska oblast. The resultwill be only achieved after MIS has been rolled out in all oblasts. |
Functional review of DSDS completed and business plan prepared in 2006 | Value | 0 | 1 | 1 |
Date | October 20, 2005 | June 30, 2010 | December 31, 2006 | |
Comment |
Annual Social reports prepared, published and disseminated in 2007, 2008, 2009 and 2010 | Value | 0 | 4 | 4 |
Date | October 20, 2005 | June 1, 2011 | June 30, 2012 | |
Comment | All 4 Social reports have been released |
Social Development Database improved (monitoring indicators etc) | Value | 1 | 1 | 1 |
Date | October 20, 2008 | March 1, 2011 | June 30, 2011 | |
Comment | Social Development Database will improve even further after MIS national roll-out in completed in 2012 |
Evaluation of social assistance programs completed | Value | no evaluation | 1 | 1 |
Date | October 20, 2005 | June 30, 2011 | June 30, 2011 | |
Comment | Delivered in June 2011 |
Public information and education strategy developed and approved in 2006 | Value | no strategy | 1 | 1 |
Date | October 20, 2005 | June 1, 2011 | June 30, 2011 | |
Comment | The strategy has been developed and approved at the beginning of 2011 |
% of population aware of eligibility criteria for social assistance benefits. | Value | less than 20% | 72% | 60% |
Date | October 20, 2005 | June 30, 2010 | June 30, 2011 | |
Comment | The 2009 number used in the last ISR is updated based on 2010 project impact evaluation |
Project impact evaluation completed | Value | 0 | Project impact evaluation completed in 2010 | Two rounds of project impact evaluation—baseline i |
Date | October 20, 2005 | June 30, 2010 | December 31, 2009 | |
Comment | Follow-up evaluation completed in 2010 |