Financier | Commitments |
---|---|
Borrower/Recipient | 42.52 |
IDA Credit | 106.25 |
UK: British Department for International Development (DFID) | 24.50 |
P075407
Closed
Phuong Tran
N/A
February 12, 2004
(as of board presentation)
February 21, 2006
May 17, 2007
US$ 173.27 million
N/A
2006
US$ 130.75 million
B
March 11, 2021
June 30, 2014
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 42.52 |
IDA Credit | 106.25 |
UK: British Department for International Development (DFID) | 24.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 106.25 |
IBRD + IDA Commitment | 106.25 |
Lending Instrument | |
---|---|
Grant Amount | 24.50 |
Total Project Cost** | 173.27 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 12, 2014 | IDA-50320 | Loan Cancel | 1,884,726.10 |
Nov 12, 2014 | IDA-50320 | Loan Disb | -1,884,726.10 |
Jun 1, 2015 | IDA-50320 | Int Charges | 13,770.92 |
Jun 1, 2015 | IDA-50320 | Int Charges | 13,770.92 |
Jun 1, 2015 | IDA-50320 | Int Charges | 303,378.94 |
Jun 1, 2015 | IDA-50320 | Int Charges | 303,378.94 |
Jun 1, 2015 | IDA-50320 | Int Charges | 523,344.28 |
Jun 1, 2015 | IDA-41500 | Int Charges | 5,108.60 |
Jun 1, 2015 | IDA-41500 | Int Charges | 5,108.60 |
Jun 1, 2015 | IDA-41500 | Int Charges | 363,543.97 |
Jun 1, 2015 | IDA-41500 | Int Charges | 363,543.97 |
Jul 3, 2014 | IDA-50320 | Loan Disb | 2,902,819.00 |
Jun 1, 2014 | IDA-41500 | Int Charges | 411,145.80 |
Jun 1, 2014 | IDA-41500 | Int Charges | 411,145.80 |
Jun 1, 2014 | IDA-41500 | Int Charges | 446.20 |
Jun 1, 2014 | IDA-41500 | Int Charges | 446.20 |
Jun 1, 2017 | IDA-41500 | Int Charges | 335,380.70 |
Jun 1, 2017 | IDA-50320 | Loan Repay | 1,365,984.00 |
Jun 1, 2016 | IDA-50320 | Int Charges | 16,175.29 |
Jun 1, 2016 | IDA-50320 | Int Charges | 304,273.16 |
Jun 1, 2016 | IDA-50320 | Int Charges | 304,273.16 |
Jun 1, 2016 | IDA-50320 | Int Charges | 534,080.75 |
Dec 1, 2016 | IDA-50320 | Int Charges | 305,291.80 |
Dec 1, 2016 | IDA-50320 | Int Charges | 305,291.80 |
Dec 1, 2016 | IDA-50320 | Int Charges | 515,246.28 |
Dec 1, 2016 | IDA-50320 | Int Charges | 3,855.98 |
Dec 1, 2016 | IDA-50320 | Int Charges | 3,855.98 |
Dec 1, 2016 | IDA-41500 | Loan Repay | 6,201.39 |
Jun 1, 2016 | IDA-41500 | Loan Repay | 7,094.72 |
Jun 1, 2016 | IDA-41500 | Loan Repay | 992,394.70 |
Jun 1, 2016 | IDA-41500 | Int Charges | 374,808.53 |
Jun 1, 2016 | IDA-41500 | Int Charges | 374,808.53 |
Jun 1, 2016 | IDA-50320 | Int Charges | 16,175.29 |
Dec 1, 2016 | IDA-41500 | Loan Repay | 958,040.80 |
Dec 1, 2016 | IDA-41500 | Int Charges | 357,974.90 |
Dec 1, 2016 | IDA-41500 | Int Charges | 357,974.90 |
Dec 1, 2015 | IDA-41500 | Int Charges | 2,273.89 |
Dec 1, 2015 | IDA-41500 | Int Charges | 367,092.20 |
Dec 1, 2015 | IDA-41500 | Int Charges | 367,092.20 |
Dec 1, 2015 | IDA-50320 | Int Charges | 5,184.28 |
Dec 1, 2015 | IDA-50320 | Int Charges | 313,851.25 |
Dec 1, 2015 | IDA-50320 | Int Charges | 313,851.25 |
Dec 1, 2015 | IDA-50320 | Int Charges | 523,085.38 |
Dec 1, 2015 | IDA-41500 | Int Charges | 2,273.89 |
Jun 1, 2018 | IDA-41500 | Int Charges | 5,270.06 |
Jun 1, 2018 | IDA-41500 | Int Charges | 5,270.06 |
Jun 1, 2018 | IDA-41500 | Loan Repay | 1,010,041.44 |
Jun 1, 2018 | IDA-50320 | Int Charges | 521,908.56 |
Jun 1, 2018 | IDA-50320 | Int Charges | 313,145.12 |
Jun 1, 2018 | IDA-50320 | Int Charges | 313,145.12 |
Jun 1, 2018 | IDA-50320 | Int Charges | 8,701.49 |
Jun 1, 2018 | IDA-50320 | Loan Repay | 1,424,858.90 |
Jun 1, 2018 | IDA-41500 | Int Charges | 363,614.90 |
Jun 1, 2018 | IDA-41500 | Int Charges | 363,614.90 |
Dec 1, 2017 | IDA-41500 | Int Charges | 27,878.28 |
Dec 1, 2017 | IDA-41500 | Loan Repay | 1,010,761.06 |
Dec 1, 2017 | IDA-41500 | Int Charges | 362,390.53 |
Dec 1, 2017 | IDA-41500 | Int Charges | 362,390.53 |
Dec 1, 2017 | IDA-50320 | Loan Repay | 1,425,874.10 |
Dec 1, 2017 | IDA-50320 | Int Charges | 318,715.22 |
Dec 1, 2017 | IDA-50320 | Int Charges | 318,715.22 |
Dec 1, 2017 | IDA-50320 | Int Charges | 46,188.44 |
Dec 1, 2017 | IDA-50320 | Int Charges | 522,484.40 |
Dec 1, 2017 | IDA-41500 | Int Charges | 27,878.28 |
Jun 1, 2017 | IDA-41500 | Loan Repay | 41,503.39 |
Jun 1, 2017 | IDA-50320 | Loan Repay | 25,877.11 |
Jun 1, 2017 | IDA-50320 | Int Charges | 316,332.06 |
Jun 1, 2017 | IDA-50320 | Int Charges | 316,332.06 |
Jun 1, 2017 | IDA-50320 | Int Charges | 482,133.40 |
Jun 1, 2017 | IDA-41500 | Loan Repay | 945,146.80 |
Jun 1, 2017 | IDA-41500 | Int Charges | 335,380.70 |
Dec 1, 2019 | IDA-50320 | Int Charges | 287,744.75 |
Dec 1, 2019 | IDA-50320 | Int Charges | 287,744.75 |
Dec 1, 2019 | IDA-50320 | Int Charges | 462,558.10 |
Jun 1, 2019 | IDA-41500 | Int Charges | 345,995.94 |
Jun 1, 2019 | IDA-41500 | Int Charges | 345,995.94 |
Jun 1, 2019 | IDA-41500 | Loan Repay | 12,127.34 |
Jun 1, 2019 | IDA-41500 | Loan Repay | 969,421.40 |
Jun 23, 2014 | IDA-50320 | Loan Disb | 6,541,751.50 |
May 29, 2014 | IDA-50320 | Loan Disb | 6,375,758.50 |
Jun 1, 2014 | IDA-50320 | Int Charges | 8,252.48 |
Jun 1, 2014 | IDA-50320 | Int Charges | 258,974.90 |
Jun 1, 2014 | IDA-50320 | Int Charges | 258,974.90 |
Jun 1, 2014 | IDA-50320 | Int Charges | 426,989.60 |
Mar 19, 2014 | IDA-50320 | Loan Disb | 5,273,413.50 |
May 5, 2014 | IDA-50320 | Loan Disb | 4,232,354.50 |
Jan 15, 2014 | IDA-50320 | Loan Disb | 7,425,596.00 |
Dec 1, 2013 | IDA-41500 | Int Charges | -56.51 |
Dec 1, 2013 | IDA-41500 | Int Charges | 56.51 |
Sep 26, 2013 | IDA-50320 | Loan Disb | 4,598,936.00 |
Dec 1, 2013 | IDA-41500 | Int Charges | 408,888.06 |
Dec 1, 2013 | IDA-41500 | Int Charges | 408,888.06 |
Dec 1, 2013 | IDA-50320 | Int Charges | 13,266.56 |
Dec 1, 2013 | IDA-50320 | Int Charges | 152,848.12 |
Dec 1, 2013 | IDA-50320 | Int Charges | 152,848.12 |
Dec 1, 2013 | IDA-50320 | Int Charges | 246,522.55 |
Dec 1, 2013 | IDA-41500 | Int Charges | 1,298.57 |
Dec 1, 2013 | IDA-41500 | Int Charges | 1,298.57 |
Dec 6, 2013 | IDA-50320 | Loan Disb | 5,830,455.00 |
Aug 8, 2013 | IDA-50320 | Loan Disb | 4,949,177.00 |
Oct 22, 2013 | IDA-50320 | Loan Disb | 4,016,356.50 |
Feb 25, 2014 | IDA-50320 | Loan Disb | 4,965,817.00 |
Aug 21, 2013 | IDA-50320 | Loan Disb | 5,979,146.50 |
Dec 1, 2014 | IDA-50320 | Int Charges | 559,921.40 |
Dec 1, 2014 | IDA-50320 | Int Charges | 4,403.79 |
Dec 1, 2014 | IDA-50320 | Int Charges | 335,952.84 |
Dec 1, 2014 | IDA-50320 | Int Charges | 335,952.84 |
Dec 1, 2014 | IDA-41500 | Int Charges | 1,274.47 |
Dec 1, 2014 | IDA-41500 | Int Charges | 1,274.47 |
Dec 1, 2014 | IDA-41500 | Int Charges | 389,765.60 |
Dec 1, 2014 | IDA-41500 | Int Charges | 389,765.60 |
Jun 1, 2019 | IDA-50320 | Loan Repay | 19,880.70 |
Jun 1, 2019 | IDA-50320 | Int Charges | 293,926.53 |
Jun 1, 2019 | IDA-50320 | Int Charges | 293,926.53 |
Jun 1, 2019 | IDA-50320 | Int Charges | 489,877.47 |
Jun 1, 2019 | IDA-50320 | Loan Repay | 1,364,783.80 |
Dec 1, 2018 | IDA-50320 | Loan Repay | 58,011.21 |
Dec 1, 2018 | IDA-50320 | Loan Repay | 1,332,291.90 |
Dec 1, 2018 | IDA-41500 | Loan Repay | 35,260.83 |
Dec 1, 2018 | IDA-41500 | Loan Repay | 950,285.00 |
Dec 1, 2018 | IDA-50320 | Int Charges | 300,337.06 |
Dec 1, 2018 | IDA-50320 | Int Charges | 300,337.06 |
Dec 1, 2018 | IDA-50320 | Int Charges | 500,561.75 |
Dec 1, 2018 | IDA-41500 | Int Charges | 351,100.72 |
Dec 1, 2018 | IDA-41500 | Int Charges | 351,100.72 |
Jun 1, 2020 | IDA-50320 | Int Charges | 16,996.05 |
Jun 1, 2020 | IDA-50320 | Loan Repay | 1,378,261.90 |
Jun 1, 2020 | IDA-50320 | Int Charges | 282,230.47 |
Jun 1, 2020 | IDA-50320 | Int Charges | 282,230.47 |
Jun 1, 2020 | IDA-50320 | Int Charges | 462,019.75 |
Jun 1, 2020 | IDA-41500 | Int Charges | 10,442.88 |
Jun 1, 2020 | IDA-41500 | Int Charges | 10,442.88 |
Jun 1, 2020 | IDA-41500 | Loan Repay | 977,010.10 |
Jun 1, 2020 | IDA-41500 | Int Charges | 331,910.47 |
Jun 1, 2020 | IDA-41500 | Int Charges | 331,910.47 |
Dec 1, 2019 | IDA-41500 | Loan Repay | 10,147.25 |
Dec 1, 2019 | IDA-41500 | Loan Repay | 968,038.50 |
Dec 1, 2019 | IDA-41500 | Int Charges | 330,686.84 |
Dec 1, 2019 | IDA-41500 | Int Charges | 330,686.84 |
Dec 1, 2019 | IDA-50320 | Loan Repay | 1,363,345.40 |
Dec 1, 2019 | IDA-50320 | Loan Repay | 16,574.95 |
Jun 1, 2022 | IDA-41500 | Int Charges | 313,610.06 |
Jun 1, 2022 | IDA-41500 | Loan Repay | 20,483.93 |
Dec 1, 2021 | IDA-50320 | Int Charges | 453,700.00 |
Dec 1, 2021 | IDA-50320 | Int Charges | 42,755.59 |
Dec 1, 2021 | IDA-50320 | Loan Repay | 2,813,312.80 |
Dec 1, 2021 | IDA-50320 | Int Charges | 272,220.00 |
Dec 1, 2021 | IDA-50320 | Int Charges | 272,220.00 |
Dec 1, 2021 | IDA-41500 | Int Charges | 26,562.02 |
Dec 1, 2021 | IDA-41500 | Int Charges | 26,562.02 |
Dec 1, 2021 | IDA-41500 | Loan Repay | 1,994,276.20 |
Dec 1, 2021 | IDA-41500 | Int Charges | 332,794.88 |
Dec 1, 2021 | IDA-41500 | Int Charges | 332,794.88 |
Jun 1, 2021 | IDA-50320 | Int Charges | 28,965.60 |
Jun 1, 2021 | IDA-50320 | Loan Repay | 1,452,419.10 |
Jun 1, 2021 | IDA-41500 | Loan Repay | 1,029,578.06 |
Jun 1, 2021 | IDA-41500 | Int Charges | 320,056.44 |
Jun 1, 2021 | IDA-41500 | Int Charges | 320,056.44 |
Jun 1, 2021 | IDA-41500 | Int Charges | 17,928.53 |
Jun 1, 2021 | IDA-41500 | Int Charges | 17,928.53 |
Jun 1, 2021 | IDA-50320 | Int Charges | 286,522.66 |
Jun 1, 2021 | IDA-50320 | Int Charges | 286,522.66 |
Jun 1, 2021 | IDA-50320 | Int Charges | 433,391.25 |
Dec 1, 2020 | IDA-50320 | Int Charges | 452,573.03 |
Dec 1, 2020 | IDA-41500 | Loan Repay | 1,018,156.75 |
Dec 1, 2020 | IDA-50320 | Int Charges | 8,716.63 |
Dec 1, 2020 | IDA-50320 | Loan Repay | 1,436,307.10 |
Dec 1, 2020 | IDA-50320 | Int Charges | 288,730.38 |
Dec 1, 2020 | IDA-50320 | Int Charges | 288,730.38 |
Dec 1, 2020 | IDA-41500 | Int Charges | 329,716.38 |
Dec 1, 2020 | IDA-41500 | Int Charges | 329,716.38 |
Dec 1, 2020 | IDA-41500 | Int Charges | 5,375.25 |
Dec 1, 2020 | IDA-41500 | Int Charges | 5,375.25 |
Jun 1, 2023 | IDA-41500 | Int Charges | 68,170.53 |
Jun 1, 2023 | IDA-50320 | Loan Repay | 2,673,561.80 |
Jun 1, 2023 | IDA-50320 | Int Charges | 228,619.89 |
Jun 1, 2023 | IDA-50320 | Int Charges | 228,619.89 |
Jun 1, 2023 | IDA-50320 | Int Charges | 381,033.22 |
Jun 1, 2023 | IDA-50320 | Int Charges | 102,692.01 |
Dec 1, 2022 | IDA-41500 | Int Charges | 232,274.94 |
Dec 1, 2022 | IDA-41500 | Int Charges | 232,274.94 |
Dec 1, 2022 | IDA-41500 | Loan Repay | 51,778.54 |
Dec 1, 2022 | IDA-41500 | Loan Repay | 1,830,436.40 |
Dec 1, 2022 | IDA-50320 | Int Charges | 237,009.28 |
Dec 1, 2022 | IDA-50320 | Int Charges | 237,009.28 |
Dec 1, 2022 | IDA-50320 | Int Charges | 293,027.66 |
Dec 1, 2022 | IDA-50320 | Loan Repay | 78,375.65 |
Dec 1, 2022 | IDA-50320 | Loan Repay | 2,576,852.80 |
Jun 1, 2022 | IDA-50320 | Loan Repay | 2,680,903.20 |
Jun 1, 2022 | IDA-50320 | Int Charges | 252,254.08 |
Jun 1, 2022 | IDA-50320 | Int Charges | 252,254.08 |
Jun 1, 2022 | IDA-50320 | Int Charges | 420,423.40 |
Jun 1, 2022 | IDA-50320 | Loan Repay | 31,174.43 |
Jun 1, 2022 | IDA-41500 | Loan Repay | 1,902,029.80 |
Jun 1, 2022 | IDA-41500 | Int Charges | 313,610.06 |
Dec 15, 2011 | IDA-50320 | Loan Commitment | 97,000,000.00 |
Jun 1, 2024 | IDA-41500 | Int Charges | 28,177.95 |
Jun 1, 2024 | IDA-41500 | Int Charges | 28,177.95 |
Jun 1, 2024 | IDA-50320 | Loan Repay | 2,660,615.80 |
Feb 21, 2006 | IDA-41500 | Loan Commitment | 106,250,000.00 |
Jun 1, 2024 | IDA-50320 | Int Charges | 207,558.28 |
Jun 1, 2024 | IDA-50320 | Int Charges | 207,558.28 |
Jun 1, 2024 | IDA-50320 | Int Charges | 345,930.40 |
Jun 1, 2024 | IDA-41500 | Loan Repay | 1,886,033.90 |
Jun 1, 2024 | IDA-41500 | Int Charges | 279,368.78 |
Jun 1, 2024 | IDA-41500 | Int Charges | 279,368.78 |
Jun 1, 2024 | IDA-50320 | Int Charges | 42,033.46 |
Dec 1, 2023 | IDA-50320 | Int Charges | 322,637.60 |
Dec 1, 2023 | IDA-41500 | Int Charges | 259,964.98 |
Dec 1, 2023 | IDA-41500 | Int Charges | 259,964.98 |
Dec 1, 2023 | IDA-50320 | Loan Repay | 38,823.95 |
Dec 1, 2023 | IDA-50320 | Loan Repay | 2,639,321.00 |
Dec 1, 2023 | IDA-50320 | Int Charges | 218,968.80 |
Dec 1, 2023 | IDA-50320 | Int Charges | 218,968.80 |
Dec 1, 2023 | IDA-41500 | Loan Repay | 1,872,565.10 |
Dec 1, 2023 | IDA-41500 | Loan Repay | 25,894.70 |
Jun 1, 2023 | IDA-41500 | Loan Repay | 1,895,210.90 |
Jun 1, 2023 | IDA-41500 | Int Charges | 294,942.20 |
Jun 1, 2023 | IDA-41500 | Int Charges | 294,942.20 |
Jun 1, 2023 | IDA-41500 | Int Charges | 68,170.53 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2014-06-24 |
Procurement | Satisfactory | 2014-06-24 |
Financial Management | Moderately Satisfactory | 2014-06-24 |
Progress towards achievement of PDO | Satisfactory | 2014-06-24 |
Counterpart Funding | Moderately Satisfactory | 2014-06-24 |
Project Management | Satisfactory | 2014-06-24 |
Monitoring and Evaluation | Satisfactory | 2014-06-24 |
Overall | Low | 2014-06-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-24-2014 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 04-20-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in the percentage of people living within 2 km of an all weather road | Value | 76% | 87% | 86% |
Date | February 21, 2006 | February 24, 2014 | June 30, 2014 | |
Comment | The figures come from the results of 2012 Vietnam Household Living Standards Survey (VHLSS) which was available in February 2014. | Actual target is 1% higher. |
Reduction in travel times to nearest schools and markets | Value | 0 | 9% | 8% |
Date | February 21, 2006 | February 24, 2014 | June 30, 2014 | |
Comment | The figures come from the results of 2012 Vietnam Household Living Standards Survey (VHLSS) which was available in February 2014. | Actual target is 1% lower as most of roads financed under AF have not yet completed by the time of 2012 VHLS. |
Increase in households living in villages with access to motorized transport services for hire (%) | Value | 79% | 73% | 84% |
Date | February 21, 2006 | February 24, 2014 | June 30, 2014 | |
Comment | The figures come from the results of 2012 Vietnam Household Living Standards Survey (VHLSS) which was available in February 2014. | Actual target is 11% lower than the plan as there has been split-up of communes and villages during 2006 -2012. The percentagesare80%, 75%, 72% and 73% in 2006, 2008, 2010 and 2012 respectively. |
Share of rural population with access to an all-season road | Value | 76.00 | 81.00 | 81.00 |
Date | February 21, 2006 | February 24, 2014 | June 30, 2014 | |
Comment | The figures come from the results of 2012 Vietnam Household Living Standards Survey (VHLSS) which was available in February 2014. | Achieved . |
Number of rural people with access to an all-season road | Value | 46039530.00 | 49068447.00 | 49068447.00 |
Date | February 21, 2006 | February 24, 2014 | June 30, 2014 | |
Comment | This indicator applies but the data will be available in December 2009 when the study on Vietnam Living Standards Survey (VLSS) iscompleted. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of rural bridges built using RT3 funds | Value | 0.00 | 36.00 | 40.00 |
Date | February 21, 2006 | May 24, 2014 | June 30, 2014 | |
Comment |
Roads rehabilitated, Rural | Value | 0.00 | 3283.00 | 3150.00 |
Date | February 21, 2006 | May 24, 2014 | June 30, 2014 | |
Comment | completed | completed |
Km of district roads maintained using RT3 funds | Value | 0.00 | 19902.00 | 17000.00 |
Date | February 21, 2006 | May 24, 2014 | June 30, 2014 | |
Comment |
Rural transport policy and strategy document approved by GoV and aligned by donors | Value | none | approved | approved |
Date | February 21, 2006 | December 31, 2008 | December 31, 2011 | |
Comment | completed |
Revised standards for rural roads approved by MOT and applied by relevant ministries and donors. | Value | current standards | revised standards approved | revised standards approved |
Date | February 21, 2006 | December 31, 2009 | December 31, 2011 | |
Comment | completed |
Guidelines for rural roads maintenance management drafted and adopted by MOT | Value | none | guidelines adopted by MOT | guidelines drafted and adopted by MOT |
Date | February 21, 2006 | December 31, 2010 | December 31, 2011 | |
Comment | completed |
Number of provinces with sufficient capacity for decentralized implementation | Value | 10.00 | 32.00 | 32.00 |
Date | February 21, 2006 | December 24, 2013 | June 30, 2014 | |
Comment | completed | completed |
Percentage of contracts awarded to the private sector (%) | Value | 65.00 | 100.00 | 98.00 |
Date | February 21, 2006 | May 30, 2014 | June 23, 2014 | |
Comment | completed | ahieved |
Number of staff trained | Value | 0.00 | 19189.00 | 16000.00 |
Date | February 21, 2006 | May 24, 2014 | June 30, 2014 | |
Comment |
Increasing the number of communities connected to basic access and improved all weather roads; | Value | 359 | 149 | 30 |
Date | February 21, 2006 | May 24, 2014 | June 30, 2014 | |
Comment | Number of communities lacking access | The figures come from the results of 2012 Vietnam Household Living Standards Survey (VHLSS) which was available in February 2014. | Number of communities lacking access. Original target of 50 communes revised to 30 communes |
Number of provinces with prioritized provincial transport plans using VPRoMMS | Value | 0 | 12 | 12 |
Date | February 21, 2006 | December 24, 2013 | June 30, 2014 | |
Comment | PRoMMs to be piloted in 12 provinces to provide effective planning and prioritization tool for rural road management. |