Financier | Commitments |
---|---|
African Development Bank | 10.00 |
Bilateral Agencies (unidentified) | 24.27 |
Borrower/Recipient | 3.99 |
Global Environment Facility (GEF) | 21.74 |
Financier | Commitments |
---|---|
African Development Bank | 10.00 |
Bilateral Agencies (unidentified) | 24.27 |
Borrower/Recipient | 3.99 |
Global Environment Facility (GEF) | 21.74 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 56.01 |
Total Project Cost** | 60.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Moderately Satisfactory | 2012-06-28 |
Financial Management | Satisfactory | 2012-06-28 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2012-06-28 |
Summary Global Objective Rating | Moderately Unsatisfactory | 2012-06-28 |
Procurement | Moderately Unsatisfactory | 2012-06-28 |
Project Management | Moderately Unsatisfactory | 2012-06-28 |
Monitoring and Evaluation | Satisfactory | 2012-06-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2013 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 09-29-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: 10-17-2014 |
---|---|---|
Outcome Rating | Unsatisfactory | Unsatisfactory |
Risk To Development Outcome | Modest | Not Rated |
Bank Performance | Unsatisfactory | Unsatisfactory |
Borrower Performance | Moderately Unsatisfactory | Moderately Unsatisfactory |
Government Performance | Not Rated | Moderately Satisfactory |
Implementing Agency | Moderately Unsatisfactory | Moderately Unsatisfactory |
Icr Quality | Not Rated | Satisfactory |
M&e Quality | Negligible | Negligible |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
An inventory database is in place in 7 ASP countries, accepted by the ASP partnership and being used and updated by gov. staff | Value | 0 | 6 | 7 |
Date | July 1, 2006 | June 11, 2012 | December 31, 2012 | |
Comment | Ethiopia, Mali, Morocco, Nigeria, Tanzania and Tunisia. FAO has not introduced PSMS in South Africa because Government does notwant to use it or appreciate its usefulness. | Ethiopia, Mali, Morocco, Nigeria, South Africa, Tanzania and Tunisia. |
Strategic studies delivered | Value | 0% | 100% | 100% |
Date | July 1, 2006 | June 11, 2012 | December 31, 2012 | |
Comment | The Disposal Technology Options study is available and utilized. Locust study is addressed under the Locust Project. All expectedtoolkits have been delivered. | Disposal Technology Options study; Locust study, and tool kits such as the Environmental Management Tool Kit (EMTK), communicationtoolkit and CESA guidelines. |
CESA in 7 countries disclosed and activities implemented. | Value | 0 | 6 | 7 |
Date | July 1, 2006 | June 11, 2012 | December 31, 2012 | |
Comment | Ethiopia, Mali, Nigeria, South Africa, Tanzania and Tunisia.Morocco closed without a finalized and disclosed CESA. South Africaprepared a specific EMP for the disposal activities only. This has been considered adequate by the Bank to meet the needs of theCESA and approved in the Board Level Restructuring | Ethiopia, Mali, Morocco, Nigeria, South Africa, Tanzania and Tunisia. |
Disposal contract completed in 6 ASP counties in line with national and international regulations. | Value | 0 | 4 | 6 |
Date | July 1, 2006 | June 11, 2012 | December 31, 2012 | |
Comment | Ethiopia, Mali, Tanzania and Tunisia. South Africa completed and implemented a disposal contract for 2 of out of 4 plannedprovinces.Morocco closed without a disposal contract. Nigeria is not included in this indicator. | Ethiopia, Mali, Morocco, South Africa, Tanzania and TunisiaNigeria is not included in this indicator |
Communication Strategy implemented. | Value | 0 | 5 | 6 |
Date | July 1, 2006 | June 11, 2012 | December 31, 2012 | |
Comment | No adapted strategies in any of the countries. | ASP-Morocco closed without having implemented its communication strategy. | Ethiopia, Mali, Morocco, Nigeria, Tanzania and Tunisia.Based on the ASP toolkit. ASP-South Africa is not included in thisindicator following the Board Level Restructuring. |
Inventoried publicly-held obsolete pesticide stockpiles in 6 ASP-P1 countries eliminated. (Goal = 100% removed). | Value | 0 | 6 | |
Date | July 1, 2006 | June 11, 2012 | December 31, 2012 | |
Comment | Ethiopia: disposal contractor procured and the activities to start in July;Mali: depending on extension under OP/BP 7.30 andresumption of activities, ASP-Mali may be able to complete its disposal contract;Morocco: the project closed withoutelimination;South Africa: half of the planned provinces have been cleaned up. Full elimination is at risk due to procurementissues;Tanzania: disposal contractor procured and the activities to start in July;Tunisia: elimination is expected by theclosing date. |