Education Reform for Knowledge Economy I Program

Abstract*

The objective of the Education Reform for Knowledge Economy Project (ERfKE) is to support the Government of Jordan to transform the education system at the early childhood, basic, and secondary levels to produce graduates with the skills needed for te knowledge economy. There are four project components. Component 1 re-orients education policy objectives and strategies through governance and administrative reform. The five sub-components consist of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Transform the education system at the early childhood, basic and secondary levels to produce graduates with the skills necessary for the knowledge economy.

Key Details

Project Details

  • P075829

  • Closed

  • Juan Moreno Olmedilla

  • N/A

  • Jordan

  • May 24, 2002

  • (as of board presentation)

    May 8, 2003

  • May 28, 2003

  • US$ 240.00 million

  • B

  • Not Applicable

  • June 30, 2009

  • BANK APPROVED

  • July 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
UK: British Department for International Development (DFID) 2.00
Arab Fund for Economic and Social Development 28.00
Borrower/Recipient 130.00
CANADA: Canadian International Development Agency (CIDA) 4.00
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 10.00
Islamic Development Bank 18.00
International Bank for Reconstruction and Development 120.00
JAPAN: Japan International Cooperation Agency (JICA) 1.00
EC: European Investment Bank 43.00
US: Agency for International Development (USAID) 14.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 120.00
IDA Commitment N/A
IBRD + IDA Commitment 120.00
Lending Instrument
Grant Amount 120.00
Total Project Cost** 370.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 1, 2014 IBRD-71700 Int Charges 205,480.70
May 8, 2003 IBRD-71700 Loan Commitment 120,000,000.00
Oct 1, 2013 IBRD-71700 Int Charges 247,649.45
Oct 1, 2013 IBRD-71700 Loan Repay 5,049,984.50
Oct 1, 2014 IBRD-71700 Int Charges 178,391.05
Oct 1, 2014 IBRD-71700 Loan Repay 5,049,984.50
Apr 1, 2015 IBRD-71700 Loan Repay 5,049,984.50
Apr 1, 2016 IBRD-71700 Int Charges 179,835.62
Apr 1, 2016 IBRD-71700 Loan Repay 5,049,984.50
Oct 1, 2015 IBRD-71700 Int Charges 166,549.02
Oct 1, 2015 IBRD-71700 Loan Repay 5,049,984.50
Apr 1, 2015 IBRD-71700 Int Charges 162,608.55
Apr 1, 2018 IBRD-71700 Int Charges 223,831.05
Apr 1, 2018 IBRD-71700 Loan Repay 5,049,984.50
Oct 1, 2017 IBRD-71700 Int Charges 256,422.23
Oct 1, 2017 IBRD-71700 Loan Repay 5,049,984.50
Apr 1, 2017 IBRD-71700 Int Charges 265,574.16
Apr 1, 2017 IBRD-71700 Loan Repay 5,049,984.50
Oct 1, 2016 IBRD-71700 Int Charges 235,620.94
Oct 1, 2016 IBRD-71700 Loan Repay 5,049,984.50
Apr 1, 2019 IBRD-71700 Int Charges 216,929.95
Apr 1, 2019 IBRD-71700 Loan Repay 5,049,984.50
Oct 1, 2018 IBRD-71700 Int Charges 274,930.75
Oct 1, 2018 IBRD-71700 Loan Repay 5,049,984.50
Apr 1, 2020 IBRD-71700 Loan Repay 4,955,897.00
Apr 1, 2020 IBRD-71700 Int Charges 58,194.64
Oct 1, 2019 IBRD-71700 Loan Repay 5,049,984.50
Oct 1, 2019 IBRD-71700 Int Charges 146,994.75
Apr 1, 2014 IBRD-71700 Loan Repay 5,049,984.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2009-06-28
Project Management Highly Satisfactory 2009-06-28
Financial Management Satisfactory 2009-06-28
Overall Safeguards Rating Satisfactory 2009-06-28
Monitoring and Evaluation Moderately Unsatisfactory 2009-06-28
Counterpart Funding Satisfactory 2009-06-28
Overall Implementation Progress (IP) Satisfactory 2009-06-28
Procurement Satisfactory 2009-06-28

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2009
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-27-2011PROJECT PERFORMANCE ASSESSMENT REPORT: 06-30-2011
Outcome RatingSatisfactory Satisfactory
Risk To Development OutcomeModerateModerate
Bank PerformanceSatisfactorySatisfactory
Borrower PerformanceSatisfactorySatisfactory
Government PerformanceSatisfactorySatisfactory
Implementing AgencyNot RatedSatisfactory
Icr QualityNot RatedSatisfactory
M&e QualitySubstantialSubstantial

Results Framework