Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.00 |
P075932
Closed
Ellen Tynan
N/A
July 9, 2002
(as of board presentation)
July 9, 2002
December 4, 2002
US$ 8.00 million
N/A
2003
US$ 8.00 million
C
January 15, 2013
March 31, 2011
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.00 |
Total Project Cost** | 8.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2010-06-22 |
Monitoring and Evaluation | Satisfactory | 2010-06-22 |
Procurement | Satisfactory | 2010-06-22 |
Summary Global Objective Rating | Satisfactory | 2010-06-22 |
Counterpart Funding | Satisfactory | 2010-06-22 |
Overall Implementation Progress (IP) | Satisfactory | 2010-06-22 |
Project Management | Satisfactory | 2010-06-22 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2011 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Unsatisfactory |
Government Performance | Moderately Unsatisfactory |
Implementing Agency | Moderately Satisfactory |