ENERGY ACCESS PROJECT

Development Objective

The Energy Access Project Global Environment Facility is associated with the IDA financed Energy Access Project. The project development objectives (PDO) are to: (i) establish a sustainable program for expansion of access to electricity and for improvement of thequality and adequacy of the electricity supply in the Borrower's territory; (ii) reduce environmental degradation, and improve the supply and efficient use of energy; (iii) reduce the barrier to the wide spread use of renewable energy technologies; and (iv) provide technical support to the Borrower for the institutional and capacity building of key sector agencies, and for regulatory, fiscal and institutional reforms in the mining sector to attract private investment.

Key Details

Project Details

  • P077380

  • Closed

  • Issa Diaw

  • N/A

  • Ethiopia

  • July 28, 2005

  • (as of board presentation)

    July 28, 2005

  • April 28, 2006

  • US$ 4.93 million

  • B

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • P049395

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
GLOBAL ENVIRONMENT - Associated IDA Fund 7.37
Sub-borrower(s) 2.50
Global Environment Facility (GEF) 4.93
Borrower/Recipient 0.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 4.93
Total Project Cost** 15.30

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2013-05-17
Overall Implementation Progress (IP) Moderately Unsatisfactory 2013-05-17
Procurement Moderately Unsatisfactory 2013-05-17
Counterpart Funding Satisfactory 2013-05-17
Overall Safeguards Rating Satisfactory 2013-05-17
Summary Global Objective Rating Satisfactory 2013-05-17
Project Management Moderately Unsatisfactory 2013-05-17
Monitoring and Evaluation Satisfactory 2013-05-17
Overall Low 2013-05-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-30-2014
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.