Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 49.00 |
P077756
Closed
Christine Pena
N/A
July 28, 2005
(as of board presentation)
January 19, 2006
June 26, 2007
US$ 49.00 million
N/A
2006
US$ 49.00 million
B
January 15, 2013
May 30, 2013
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 49.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 49.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 49.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 49.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 19, 2006 | IBRD-73570 | Loan Commitment | 49,000,000.00 |
Nov 15, 2019 | IBRD-73570 | Int Charges | 202,755.00 |
Nov 15, 2019 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2019 | IBRD-73570 | Int Charges | 249,696.02 |
May 15, 2019 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2020 | IBRD-73570 | Int Charges | 131,288.20 |
May 15, 2020 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2022 | IBRD-73570 | Int Charges | 9,566.84 |
May 15, 2022 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2021 | IBRD-73570 | Int Charges | 13,414.53 |
Nov 15, 2021 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2020 | IBRD-73570 | Int Charges | 47,374.29 |
Nov 15, 2020 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2021 | IBRD-73570 | Int Charges | 20,024.98 |
May 15, 2021 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2022 | IBRD-73570 | Int Charges | 22,177.46 |
Nov 15, 2022 | IBRD-73570 | Loan Repay | 1,963,377.20 |
May 15, 2016 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2017 | IBRD-73570 | Int Charges | 181,994.58 |
May 15, 2017 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2017 | IBRD-73570 | Int Charges | 189,782.97 |
Nov 15, 2017 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2018 | IBRD-73570 | Int Charges | 254,410.94 |
Nov 15, 2018 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2018 | IBRD-73570 | Int Charges | 187,761.38 |
May 15, 2018 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2015 | IBRD-73570 | Int Charges | 93,243.32 |
May 15, 2015 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2015 | IBRD-73570 | Int Charges | 101,113.76 |
Nov 15, 2015 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2016 | IBRD-73570 | Int Charges | 153,990.14 |
Nov 15, 2016 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2016 | IBRD-73570 | Int Charges | 120,208.98 |
Nov 15, 2014 | IBRD-73570 | Int Charges | 98,983.45 |
Nov 15, 2014 | IBRD-73570 | Loan Repay | 2,000,789.60 |
Nov 15, 2013 | IBRD-73570 | Int Charges | 648.99 |
Nov 15, 2013 | IBRD-73570 | Int Charges | 135,241.05 |
Dec 23, 2013 | IBRD-73570 | Loan Disb | -885,239.25 |
Dec 23, 2013 | IBRD-73570 | Loan Cancel | 1,400,191.00 |
Nov 15, 2013 | IBRD-73570 | Loan Repay | 2,050,020.80 |
May 15, 2014 | IBRD-73570 | Int Charges | 110,908.86 |
May 15, 2014 | IBRD-73570 | Loan Repay | 2,000,789.60 |
May 15, 2014 | IBRD-73570 | Int Charges | 134.04 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Moderately Satisfactory | 2013-05-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2013-05-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-05-29 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2013-05-29 |
Procurement | Moderately Satisfactory | 2013-05-29 |
Project Management | Moderately Satisfactory | 2013-05-29 |
Financial Management | Moderately Satisfactory | 2013-05-29 |
Overall Safeguards Rating | Moderately Satisfactory | 2013-05-29 |
Overall Safeguards Rating | Moderately Satisfactory | 2013-05-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-26-2013 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 12-08-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Indigenous/non indigenous infant mortality ratio in project area. | Value | 1.2 | 1.22 | Reduce by 10 percent with respect to the baseline. |
Date | December 31, 2007 | December 31, 2010 | May 30, 2013 | |
Comment | Final target not achieved. Latest available reliable data is from 2010. Improved from 2009 but slightly higher than 2007 data. |
Indigenous/non indigenous maternal mortality ratio in project area. | Value | 3.2 | 1.24 | Reduce by 10 percent with respect to the baseline. |
Date | June 30, 2006 | December 31, 2012 | May 30, 2013 | |
Comment | Source: SIGSA | Target surpassed. indigenous to non-indigenous MMR reduced to less than half of baseline. Latest available reliable informationsource from National Center of Epidemiology. Most recently available comparable information from SIGSA also show target has beensurpassed in 2010 and 2011 with the ratios being 1.59 and 1.44, respectively. |
Percentage of institutional deliveries in the areas of intervention. | Value | 22.3% | 42% | Increase by 20 percent with respect to the baselin |
Date | June 30, 2006 | December 31, 2012 | May 30, 2013 | |
Comment | Target surpassed (increase is 88%). Data from MOH SIGSA. |
Percentage of children under 2 with weight for age <-2Z in project areas. | Value | 21.9 (2008 cohort) and 27.4 (2009 cohort) | NA until July 2013 | reduce by 5 percentage points relative to 2011 bas |
Date | March 31, 2011 | April 19, 2013 | March 31, 2013 | |
Comment | To be updated after nutrition survey analysis is completed by July 2013 |
Percentage of children under 2 with height for age <-2Z in project areas. | Value | 68.2 (2008 cohort) and 78.3% (2009 cohort) | Not available until July 2013 | reduce by 5 percentage points with respect to 2011 |
Date | March 31, 2011 | April 19, 2013 | March 31, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of Secondary level services with cartera ampliada and operating room fully operational. | Value | 0 | 8 | 10 areas |
Date | June 30, 2006 | July 1, 2013 | May 30, 2013 | |
Comment | Increased. | Target revised from 8 to 10 to take into account final Project restructuring. |
Number of secondary level services with cartera ampliada, but without operating room, fully operational. | Value | 0 | 27 | 27 areas |
Date | June 30, 2006 | April 19, 2013 | May 30, 2013 | |
Comment | Target achieved. The Project supported the rehabilitation of an additional CAP that will only be 80% complete by end of Projectdate which will bring total to 27.8%. | Target revised from 32 to 27 to support more areas with more CAIMI to improve access to surgical services than CAP whilemaintaining the total number of rehabilitated health facilities. |
Percentage of pregnant women with at least one prenatal care in project areas. | Value | 54.2% | 89% | 90% |
Date | June 30, 2006 | December 31, 2012 | May 30, 2013 | |
Comment | Target almost achieved. Source: SIGSA | Target revised to 90% as part of approved restructuring. |
Percentage of mothers receiving post-natal case within 10 days of delivery in the areas of intervention (information to be gatheredfrom CAIMI and PEC). | Value | 0% | 31% | 20% |
Date | June 30, 2006 | December 31, 2012 | May 30, 2013 | |
Comment | Earlier ISR had listed this as 45.54% but that was a typographical error. The PAD and other project docs indicate that this shouldbe 0 | Target surpassed.source: SIGSA |
Percentage of children under 2 years old who participate in the weighing sessions in the areas of intervention. | Value | 55% | 78% | 80 percent |
Date | June 30, 2006 | December 31, 2011 | May 30, 2013 | |
Comment | target almost achieved. This is the latest available updated information. | Target revised to 80% as part of approved Project restructuring |
Percentage of children for whom change in weight is measured in the areas of intervention. | Value | 0% | 78% | 80 percent |
Date | June 30, 2006 | December 31, 2011 | May 30, 2013 | |
Comment | target almost achieved. This is the latest available updated information. | Target revised to 80% as part of approved Project restructuring |
Percentage of families attended by Creciendo Bien in areas of intervention. | Value | 0% | 28% | 30% of total beneficiaries |
Date | June 30, 2006 | December 31, 2010 | December 31, 2012 | |
Comment | Target nearly achieved. |
Integrated strategy for the implementation of the three programs. | Value | N/A | Available | Available |
Date | June 30, 2006 | May 30, 2013 | December 31, 2012 | |
Comment | Target achieved for the 3 programs (AINM-C, PEC, and Cresciendo Bien) especially in terms of an integrated communications strategyand incorporation of the community educators trained in AINM-C in the PEC. | As part of the approved restructuring, the 3 programs (PEC, AINM-C, and Cresciendo Bien) were specified. |
Number of jurisdictions with AINM-C. | Value | 0 | 142 jurisdictions (community based) and 8 district | 112 jurisdictions. |
Date | June 30, 2006 | December 31, 2012 | December 31, 2012 | |
Comment | Target surpassed. Government supported 142 jurisdictions with AINM-C by financing community educators who link health staff andcommunities through the PEC and the Project continued to support 8 districts with AINM-C "institicional" or with MOH mobile healthteams instead of NGOs |
People with access to a basic package of health, nutrition, or reproductive health services (number) | Value | 0.00 | 950000.00 | 0.00 |
Date | November 4, 2009 | December 30, 2011 | May 30, 2013 | |
Comment | Total number of people with access is 950,000, of which 159,604 are children less than 5 years old. | Target: Increase since Project start date per approved Project restructuring |
Health facilities constructed, renovated, and/or equipped (number) | Value | 0.00 | 35.00 | 37.00 |
Date | November 4, 2009 | April 19, 2013 | May 30, 2013 | |
Comment | Target almost achieved but by end of Project, remaining CAIMI will be 76% rehabilitated and remaining CAP will be 80% rehabilitated. | Target reduced to 37 per approved Project restructuring |
Health personnel receiving training (number) | Value | 0.00 | 3064.00 | 2000.00 |
Date | November 4, 2009 | December 31, 2012 | December 31, 2012 | |
Comment | Target surpassed. | Yearly target specified per the approved Project restructuring |
Monitoring and evaluation of the Project done with regular reports providing required data | Value | 0.00 | 2.00 | 2.00 |
Date | December 31, 2012 | May 30, 2013 | ||
Comment | target achieved | revised description and target based on approved Project Restructuring. |