Financier | Commitments |
---|---|
IDA GRANT FOR POST-CONFLICT | 37.00 |
P077779
Closed
Julia Fraser
N/A
April 9, 2002
(as of board presentation)
June 6, 2002
June 11, 2002
US$ 37.00 million
N/A
2002
US$ 37.00 million
B
Not Applicable
June 30, 2006
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
IDA GRANT FOR POST-CONFLICT | 37.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 37.00 |
IBRD + IDA Commitment | 37.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 37.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 6, 2002 | IDA-H0070 | Loan Commitment | 33,000,000.00 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2006-06-26 |
Counterpart Funding | Satisfactory | 2006-06-26 |
Procurement | Satisfactory | 2006-06-26 |
Project Management | Moderately Satisfactory | 2006-06-26 |
Overall Safeguards Rating | Satisfactory | 2006-06-26 |
Progress towards achievement of PDO | Satisfactory | 2006-06-26 |
Financial Management | Satisfactory | 2006-06-26 |
Monitoring and Evaluation | Satisfactory | 2006-06-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-29-2007 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | High |
Bank Performance | Substantial |
Borrower Performance | Moderately Satisfactory |
Government Performance | Not Applicable |
Implementing Agency | Not Applicable |
INDICATOR | ICR REVIEW: 06-27-2007 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Municipal Public Works - Number of packages implemented with community endorsement | Value | Actual: 100 | 100 | |
Date | February 28, 2005 | December 31, 2004 | ||
Comment |
Municipal Public Works - Number of person-days of employment generated | Value | Actual: 43,000 people for an average of 10 days | 18,000 | |
Date | February 28, 2005 | December 30, 2004 | ||
Comment |
Municipal public works - Km roads cleared, km access roads constructed, km drains cleared, structures constructed/repaired, trees planted, m2 land treated with soil conservation measures | Value | Over 43,000 meters of road gravelling/levelling in | targets to be defined in subprojects | |
Date | February 28, 2005 | December 31, 2004 | ||
Comment |
Urban Water Supply - Number of cities receiving improvements to water supply | Value | 11 provincial cities with about 132 km of pipes la | 11 | |
Date | June 22, 2006 | December 30, 2005 | ||
Comment |
Urban Water Supply - No. of cities for which planning info. (identification of future bulk water sources, outline plan of network expansion needs, household survey data, has been provided | Value | Feasibility studies were compiled for 11 provincia | 11 | |
Date | June 22, 2005 | December 30, 2005 | ||
Comment |
Kabul Sanitation - Improvement in the sanitary and environmental aspects of the existing solid waste collection and disposal systemin Kabul | Value | Completed: rehab of Gazaek dumpsite, repair of 8 p | Goods delivered: 500 containers 1.1 cum, 44 contai | |
Date | June 22, 2006 | June 22, 2006 | ||
Comment |
Power - Dispatch of distribution material to provincial cities by April 2005. Erection of all material for Kabul City by September 2005 | Value | Material for all 7 cities has been dispatched. Ove | ||
Date | June 22, 2005 | |||
Comment |
Power - Re-commissioning of the gas turbine plant in the city of Kabul has taken place by December 31, 2002 | Value | Completed in January 2003. This provides an addit | ||
Date | January 15, 2003 | |||
Comment |
Power - Power Sector Master plan completed. | Value | The final report of the Power Sector Master Plan w | ||
Date | October 20, 2004 | |||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
This project was approved in FY02, and as such no intermediate outcome indicators were defined. | Value | na | na | |
Date | May 31, 2005 | December 30, 2005 | ||
Comment |