Skip to Main Navigation

Emergency Education Rehabilitation & Development Project

Development Objective

The project development objective is to selectively support the Transitional Islamic State of Afghanistan in its efforts to reconstruct and develop the education sector. Specifically, the project aims to: (a) increase access to education opportunities in the formal and non-formal systems for under-served groups, especially women and girls; (b) support the development of a policy framework and the reform of education management at all levels, in partnership with civil society, NGOs and the private sector; and c) introduce modern information technologies for communications in the Ministries and distance learning for capacity building of the civil servants.

Key Details

Project Details

  • P077896

  • Closed

  • Habibullah Wajdi

  • N/A

  • Afghanistan

  • April 15, 2002

  • (as of board presentation)

    June 6, 2002

  • June 11, 2002

  • US$ 15.00 million

  • N/A

  • South Asia

  • 2002

  • US$ 15.00 million

  • C

  • Not Applicable

  • June 30, 2006

  • BANK APPROVED

  • September 6, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA GRANT FOR POST-CONFLICT 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.00
IBRD + IDA Commitment 15.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 15.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 6, 2002 IDA-H0080 Loan Commitment 15,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2006-08-07
Progress towards achievement of PDO Moderately Satisfactory 2006-08-07
Procurement Moderately Satisfactory 2006-08-07
Project Management Moderately Satisfactory 2006-08-07
Financial Management Moderately Satisfactory 2006-08-07
Monitoring and Evaluation Moderately Unsatisfactory 2006-08-07
Overall Implementation Progress (IP) Moderately Satisfactory 2006-08-07

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-23-2007
OutcomesModerately Satisfactory
Risk to Development OutcomeHigh
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-22-2007PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

No data available.