Emergency Transport Rehabilitation Project

Abstract*

The Emergency Transport and Rehabilitation Project for Afghanistan's development objective is to facilitate the country's economic and social recovery through improved physical access to goods, markets, and administrative and social services. This will be achieved by: a) removing key transport bottlenecks that hamper recovery; b) building capacity in management, implementation and maintenance of transport services and works through the provision of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To facilitate the country's economic and social recovery through improved physical access to goods, markets, and administrative and social services.This will be achieved by: (i) removing key transport bottlenecks that seriously hamper recovery, (ii) building capacity in management, implementation, and maintenance of transport services and works through the provision of equipment and technical assistance, and (iii) assisting in the establishment of an institutional and policy framework for the transport sector for sustainable service delivery.The removal of key transport bottlenecks will promote regional economic integration and facilitate trade, delivery of humanitarian aid, and reconstruction efforts in all sectors. Normal traffic operations on the key road arteries and in the air will be restored, also facilitating movements on the key import/export links and main corridors.

Key Details

Project Details

  • P078284

  • Closed

  • Mitsuyoshi Asada

  • N/A

  • Afghanistan

  • June 28, 2002

  • (as of board presentation)

    March 11, 2003

  • July 14, 2003

  • US$ 163.80 million

  • N/A

  • South Asia

  • 2003

  • US$ 113.10 million

  • B

  • March 11, 2021

  • June 30, 2009

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Bilateral Agencies (unidentified) 5.10
Borrower/Recipient 15.70
IDA Credit 108.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 108.00
IBRD + IDA Commitment 108.00
Lending Instrument
Grant Amount 5.10
Total Project Cost** 163.80

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 1, 2019 IDA-37350 Loan Repay 0.29
Feb 1, 2019 IDA-37350 Loan Repay 13,683.19
Feb 4, 2019 IDA-37350 Int Charges 262,522.00
Feb 4, 2019 IDA-37350 Int Charges 262,522.00
Feb 1, 2019 IDA-37350 Debt Relief Principal 855,070.25
Feb 1, 2019 IDA-37350 Loan Repay 855,070.25
Feb 1, 2019 IDA-37350 Int Charges 3.90
Feb 1, 2019 IDA-37350 Int Charges 3.90
Feb 1, 2019 IDA-37350 Debt Relief Charges 14,813.40
Aug 1, 2018 IDA-37350 Debt Relief Charges 27,531.39
Aug 1, 2018 IDA-37350 Int Charges 27,531.39
Aug 1, 2018 IDA-37350 Int Charges 27,531.39
Aug 1, 2018 IDA-37350 Debt Relief Principal 844,802.00
Aug 1, 2018 IDA-37350 Loan Repay 844,802.00
Aug 8, 2018 IDA-37350 Loan Repay 26,729.91
Aug 8, 2018 IDA-37350 Int Charges 11.16
Aug 8, 2018 IDA-37350 Int Charges 11.16
May 19, 2005 IDA-H1630 Loan Commitment 45,000,000.00
Mar 11, 2003 IDA-37350 Loan Commitment 108,000,000.00
Feb 8, 2024 IDA-37350 Int Charges 353.70
Feb 8, 2024 IDA-37350 Int Charges 353.70
Feb 8, 2024 IDA-37350 Loan Repay 96,705.41
Feb 8, 2024 IDA-37350 Int Charges 240,740.38
Feb 8, 2024 IDA-37350 Int Charges 240,740.38
Feb 8, 2024 IDA-37350 Loan Repay 56,201.46
Aug 1, 2024 IDA-37350 Int Charges 22.31
Aug 1, 2024 IDA-37350 Int Charges 22.31
Aug 1, 2024 IDA-37350 Int Charges 231,660.70
Aug 1, 2024 IDA-37350 Int Charges 231,660.70
Aug 1, 2024 IDA-37350 Loan Repay 150,807.66
Aug 1, 2024 IDA-37350 Debt Relief Principal 1,490,304.10
Aug 1, 2024 IDA-37350 Loan Repay 1,490,304.10
Feb 1, 2024 IDA-37350 Debt Relief Charges 4,091.34
Feb 1, 2024 IDA-37350 Int Charges 4,091.34
Feb 1, 2024 IDA-37350 Int Charges 4,091.34
Feb 1, 2024 IDA-37350 Debt Relief Principal 1,491,104.40
Feb 1, 2024 IDA-37350 Loan Repay 1,491,104.40
Feb 1, 2024 IDA-37350 Loan Repay 6,618.59
Aug 1, 2024 IDA-37350 Loan Repay 5,994.90
Nov 1, 2023 IDA-37350 Loan Repay 186,399.16
Nov 1, 2023 IDA-37350 Int Charges 239,943.80
Nov 1, 2023 IDA-37350 Int Charges 239,943.80
Feb 1, 2023 IDA-37350 Int Charges 200,402.84
Feb 1, 2023 IDA-37350 Int Charges 200,402.84
Aug 1, 2023 IDA-37350 Debt Relief Charges 26,319.09
Aug 1, 2023 IDA-37350 Int Charges 26,319.09
Aug 1, 2023 IDA-37350 Int Charges 26,319.09
Aug 1, 2023 IDA-37350 Debt Relief Principal 1,473,768.20
Aug 1, 2023 IDA-37350 Loan Repay 1,473,768.20
Feb 1, 2023 IDA-37350 Int Charges 15,220.21
Feb 1, 2023 IDA-37350 Int Charges 15,220.21
Feb 1, 2023 IDA-37350 Debt Relief Charges 12,857.66
Feb 1, 2023 IDA-37350 Int Charges 12,857.66
Feb 1, 2023 IDA-37350 Int Charges 12,857.66
Feb 1, 2023 IDA-37350 Int Charges 1,703.04
Feb 1, 2023 IDA-37350 Int Charges 1,703.04
Feb 1, 2023 IDA-37350 Debt Relief Principal 837,463.56
Feb 1, 2023 IDA-37350 Loan Repay 837,463.56
Feb 1, 2023 IDA-37350 Loan Repay 2,148.48
Dec 15, 2022 IDA-37350 Int Charges 222,609.83
Dec 15, 2022 IDA-37350 Int Charges 222,609.83
Feb 1, 2022 IDA-37350 Debt Relief Principal 855,066.40
Feb 1, 2022 IDA-37350 Loan Repay 855,066.40
Feb 1, 2022 IDA-37350 Loan Repay 13,382.98
Feb 1, 2022 IDA-37350 Int Charges 0.01
Feb 1, 2022 IDA-37350 Int Charges 0.01
Feb 1, 2022 IDA-37350 Debt Relief Charges 146.44
Feb 1, 2022 IDA-37350 Int Charges 146.44
Feb 1, 2022 IDA-37350 Int Charges 146.44
Aug 1, 2022 IDA-37350 Loan Repay 822,969.40
Aug 1, 2022 IDA-37350 Debt Relief Charges 29,797.64
Aug 1, 2022 IDA-37350 Int Charges 29,797.64
Aug 1, 2022 IDA-37350 Int Charges 29,797.64
Aug 1, 2022 IDA-37350 Debt Relief Principal 822,969.40
Jun 14, 2022 IDA-37350 Int Charges 256,872.38
Jun 14, 2022 IDA-37350 Int Charges 256,872.38
Aug 1, 2021 IDA-37350 Loan Repay 38,718.84
Aug 1, 2015 IDA-37350 Loan Repay 45,179.01
Aug 1, 2015 IDA-37350 Debt Relief Principal 821,245.10
Aug 1, 2015 IDA-37350 Loan Repay 821,245.10
Aug 18, 2015 IDA-37350 Int Charges 240,693.00
Aug 18, 2015 IDA-37350 Int Charges 240,693.00
Feb 12, 2015 IDA-37350 Int Charges 297,585.00
Feb 12, 2015 IDA-37350 Int Charges 297,585.00
Aug 1, 2021 IDA-37350 Int Charges 29.58
Aug 1, 2021 IDA-37350 Int Charges 29.58
Feb 1, 2015 IDA-37350 Int Charges 21,246.28
Feb 1, 2015 IDA-37350 Debt Relief Charges 21,246.28
Feb 1, 2015 IDA-37350 Int Charges 21,246.28
Feb 1, 2015 IDA-37350 Loan Repay 7,600.54
Feb 1, 2015 IDA-37350 Debt Relief Principal 868,204.10
Feb 1, 2015 IDA-37350 Loan Repay 868,204.10
Feb 1, 2015 IDA-37350 Int Charges 3.52
Feb 1, 2015 IDA-37350 Int Charges 3.52
Aug 1, 2014 IDA-37350 Debt Relief Charges 1,852.89
Aug 1, 2014 IDA-37350 Int Charges 1,852.89
Aug 1, 2014 IDA-37350 Int Charges 1,852.89
Aug 1, 2014 IDA-37350 Debt Relief Principal 889,973.94
Aug 1, 2014 IDA-37350 Loan Repay 889,973.94
Aug 4, 2014 IDA-37350 Loan Repay 61,206.15
Aug 4, 2014 IDA-37350 Int Charges 28.12
Aug 4, 2014 IDA-37350 Int Charges 28.12
Aug 1, 2014 IDA-37350 Debt Relief Charges 72.89
Aug 1, 2014 IDA-37350 Int Charges 72.89
Aug 1, 2014 IDA-37350 Int Charges 72.89
Aug 4, 2014 IDA-37350 Int Charges 349,802.20
Aug 4, 2014 IDA-37350 Int Charges 349,802.20
Feb 1, 2014 IDA-37350 Debt Relief Principal 894,345.50
Feb 1, 2014 IDA-37350 Loan Repay 894,345.50
Feb 24, 2014 IDA-37350 Int Charges 23.31
Feb 24, 2014 IDA-37350 Int Charges 23.31
Feb 24, 2014 IDA-37350 Int Charges 13,000.73
Feb 24, 2014 IDA-37350 Int Charges 13,000.73
Feb 24, 2014 IDA-37350 Loan Repay 59,110.68
Aug 26, 2013 IDA-37350 Loan Repay 44,082.19
Aug 26, 2013 IDA-37350 Int Charges 341,435.80
Aug 26, 2013 IDA-37350 Int Charges 341,435.80
Aug 1, 2013 IDA-37350 Debt Relief Principal 894,588.20
Aug 1, 2013 IDA-37350 Loan Repay 894,588.20
Feb 24, 2014 IDA-37350 Int Charges 354,199.28
Feb 24, 2014 IDA-37350 Int Charges 354,199.28
Aug 1, 2013 IDA-37350 Int Charges 650.37
Aug 1, 2013 IDA-37350 Int Charges 650.37
Aug 1, 2013 IDA-37350 Debt Relief Charges 2,203.15
Aug 1, 2013 IDA-37350 Int Charges 2,203.15
Aug 1, 2013 IDA-37350 Int Charges 2,203.15
Aug 8, 2018 IDA-37350 Int Charges 292,967.44
Aug 8, 2018 IDA-37350 Int Charges 292,967.44
Aug 1, 2018 IDA-37350 Int Charges 526.20
Aug 1, 2018 IDA-37350 Int Charges 526.20
Aug 1, 2018 IDA-37350 Int Charges 1,373.94
Aug 1, 2018 IDA-37350 Int Charges 1,373.94
Feb 20, 2018 IDA-37350 Int Charges 23,136.20
Feb 20, 2018 IDA-37350 Int Charges 23,136.20
Feb 1, 2018 IDA-37350 Debt Relief Principal 874,779.20
Feb 1, 2018 IDA-37350 Loan Repay 874,779.20
Feb 20, 2018 IDA-37350 Loan Repay 29,339.01
Feb 20, 2018 IDA-37350 Int Charges 0.13
Feb 20, 2018 IDA-37350 Int Charges 0.13
Feb 20, 2018 IDA-37350 Int Charges 277,903.66
Feb 20, 2018 IDA-37350 Int Charges 277,903.66
Aug 2, 2017 IDA-37350 Loan Repay 5,860.24
Aug 2, 2017 IDA-37350 Int Charges 279,712.78
Aug 2, 2017 IDA-37350 Int Charges 279,712.78
Aug 1, 2017 IDA-37350 Debt Relief Charges 5,960.75
Aug 1, 2017 IDA-37350 Int Charges 5,960.75
Aug 1, 2017 IDA-37350 Int Charges 5,960.75
Aug 1, 2017 IDA-37350 Debt Relief Principal 871,264.20
Aug 1, 2017 IDA-37350 Loan Repay 871,264.20
Feb 21, 2017 IDA-37350 Int Charges 250,403.00
Feb 21, 2017 IDA-37350 Int Charges 250,403.00
Aug 1, 2016 IDA-37350 Debt Relief Charges 3,957.17
Aug 1, 2016 IDA-37350 Int Charges 3,957.17
Aug 1, 2016 IDA-37350 Int Charges 3,957.17
Aug 1, 2016 IDA-37350 Debt Relief Principal 867,809.50
Aug 1, 2016 IDA-37350 Loan Repay 867,809.50
Aug 1, 2016 IDA-37350 Debt Relief Charges 10,349.90
Aug 1, 2016 IDA-37350 Int Charges 10,349.90
Aug 1, 2016 IDA-37350 Int Charges 10,349.90
Feb 1, 2017 IDA-37350 Debt Relief Principal 842,972.00
Feb 1, 2017 IDA-37350 Loan Repay 842,972.00
Feb 1, 2017 IDA-37350 Debt Relief Charges 36,698.78
Feb 1, 2017 IDA-37350 Int Charges 36,698.78
Feb 1, 2017 IDA-37350 Int Charges 36,698.78
Feb 1, 2017 IDA-37350 Loan Repay 3,753.09
Aug 16, 2016 IDA-37350 Int Charges 296,648.90
Aug 16, 2016 IDA-37350 Int Charges 296,648.90
Feb 1, 2016 IDA-37350 Debt Relief Charges 22,396.28
Feb 1, 2016 IDA-37350 Int Charges 22,396.28
Feb 1, 2016 IDA-37350 Int Charges 22,396.28
Feb 1, 2016 IDA-37350 Debt Relief Charges 6,228.20
Feb 1, 2016 IDA-37350 Int Charges 6,228.20
Feb 1, 2016 IDA-37350 Int Charges 6,228.20
Feb 1, 2016 IDA-37350 Debt Relief Principal 855,937.90
Feb 1, 2016 IDA-37350 Loan Repay 855,937.90
Feb 1, 2016 IDA-37350 Debt Relief Principal -855,937.90
Feb 1, 2016 IDA-37350 Loan Repay -855,937.90
Feb 1, 2016 IDA-37350 Debt Relief Charges -28,624.49
Feb 1, 2016 IDA-37350 Int Charges -28,624.49
Feb 1, 2016 IDA-37350 Int Charges -28,624.49
Feb 1, 2016 IDA-37350 Debt Relief Principal 855,937.90
Feb 1, 2016 IDA-37350 Loan Repay 855,937.90
Mar 2, 2016 IDA-37350 Int Charges 279,128.00
Mar 2, 2016 IDA-37350 Int Charges 279,128.00
Feb 1, 2016 IDA-37350 Debt Relief Charges 28,624.49
Feb 1, 2016 IDA-37350 Int Charges 28,624.49
Feb 1, 2016 IDA-37350 Int Charges 28,624.49
Aug 1, 2015 IDA-37350 Debt Relief Charges 65,762.99
Aug 1, 2015 IDA-37350 Int Charges 65,762.99
Aug 1, 2015 IDA-37350 Int Charges 65,762.99
Aug 1, 2021 IDA-37350 Int Charges 279,590.60
Aug 1, 2021 IDA-37350 Int Charges 279,590.60
Aug 1, 2021 IDA-37350 Debt Relief Charges 8,788.11
Aug 1, 2021 IDA-37350 Int Charges 8,788.11
Aug 1, 2021 IDA-37350 Int Charges 8,788.11
Aug 1, 2021 IDA-37350 Debt Relief Principal 848,870.50
Aug 1, 2021 IDA-37350 Loan Repay 848,870.50
Feb 1, 2021 IDA-37350 Debt Relief Charges 34,654.13
Feb 1, 2021 IDA-37350 Int Charges 34,654.13
Feb 1, 2021 IDA-37350 Int Charges 34,654.13
Feb 22, 2021 IDA-37350 Loan Repay 68,257.14
Feb 22, 2021 IDA-37350 Int Charges 4.41
Feb 22, 2021 IDA-37350 Int Charges 4.41
Feb 22, 2021 IDA-37350 Int Charges 276,761.44
Feb 22, 2021 IDA-37350 Int Charges 276,761.44
Feb 1, 2021 IDA-37350 Debt Relief Principal 825,450.25
Feb 1, 2021 IDA-37350 Loan Repay 825,450.25
Aug 1, 2020 IDA-37350 Int Charges 0.35
Aug 1, 2020 IDA-37350 Int Charges 0.35
Aug 1, 2020 IDA-37350 Debt Relief Charges 2,001.51
Aug 1, 2020 IDA-37350 Int Charges 2,001.51
Aug 1, 2020 IDA-37350 Int Charges 2,001.51
Aug 1, 2020 IDA-37350 Debt Relief Principal 860,548.70
Aug 1, 2020 IDA-37350 Loan Repay 860,548.70
Aug 13, 2020 IDA-37350 Int Charges 248,708.70
Aug 13, 2020 IDA-37350 Int Charges 248,708.70
Aug 13, 2020 IDA-37350 Loan Repay 17,263.30
Feb 1, 2020 IDA-37350 Loan Repay 5,711.31
Feb 1, 2020 IDA-37350 Debt Relief Principal 849,686.06
Feb 1, 2020 IDA-37350 Loan Repay 849,686.06
Feb 1, 2020 IDA-37350 Debt Relief Charges 15,309.91
Feb 1, 2020 IDA-37350 Int Charges 15,309.91
Feb 1, 2020 IDA-37350 Int Charges 15,309.91
Feb 27, 2020 IDA-37350 Int Charges 260,426.66
Feb 27, 2020 IDA-37350 Int Charges 260,426.66
Aug 1, 2019 IDA-37350 Debt Relief Principal 850,850.00
Aug 1, 2019 IDA-37350 Loan Repay 850,850.00
Aug 1, 2019 IDA-37350 Debt Relief Charges 4,671.41
Aug 1, 2019 IDA-37350 Int Charges 4,671.41
Aug 1, 2019 IDA-37350 Int Charges 4,671.41
Aug 1, 2019 IDA-37350 Debt Relief Charges 11,920.36
Aug 1, 2019 IDA-37350 Int Charges 11,920.36
Aug 1, 2019 IDA-37350 Int Charges 11,920.36
Aug 15, 2019 IDA-37350 Int Charges 277,068.70
Aug 15, 2019 IDA-37350 Int Charges 277,068.70
Feb 1, 2019 IDA-37350 Int Charges 14,813.40
Feb 1, 2019 IDA-37350 Int Charges 14,813.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2008-06-23
Progress towards achievement of PDO Satisfactory 2008-06-23
Project Management Moderately Satisfactory 2008-06-23
Financial Management Moderately Satisfactory 2008-06-23
Monitoring and Evaluation Moderately Satisfactory 2008-06-23
Overall Implementation Progress (IP) Satisfactory 2008-06-23
Overall Safeguards Rating Unsatisfactory 2008-06-23
Counterpart Funding Satisfactory 2008-06-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-30-2008
OutcomesModerately Satisfactory
Risk to Development OutcomeHigh
Bank PerformanceSubstantial
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-19-2009PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average travel time along northern corridor is reduced by 50% by 11/30/04.ValueTravel time between Kabul - Kunduz was more than 4Travel time between Kabul - Kunduz is about 6.0 hoTravel time between Kabul - Kunduz is about 6.0 ho
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • Daytime humanitarian flows along northern corridor are technically feasible by end of project; day and night flows by end of projectValueDaytime humanitarian flows along northern corridorDaytime humanitarian flows along northern corridorDaytime humanitarian flows along northern corridor
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • International airlines have begun operating to Kabul by December 31, 2003.ValueNo international commercial airlines were operatinIn addition to UNHAS flights, Ariana, Kam Air, PIAMultiple international airlines begin operations t
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • At least ten rural communities have improved access to markets, social services and administrative centers by end of project.ValueAverage access time for ten rural communities to mAverage access time for ten rural communities to mRural communities in northern corridor have good a
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Tunnel & snow gallery work is begun by 10/15/02 and completed by 9/30/03. Two-way daytime traffic operating 7 days a week from Kabul to Doshi by 10/31/03.ValueTunnel & snow gallery work was uregently necessaryTunnel & snow gallery work began before Oct. 2002,Two-way daytime traffic keeps operating 24/7/365 b
    DateApril 1, 2004May 22, 2008June 30, 2008
    Comment
  • All bridges, road sections and pavement repaired by 11/30/04. Equipped, trained and functional winter maintenance unit in place by11/30/03.ValueAll bridges, road sections and pavement needed urgAll bridges, road sections and pavement repaired bAll bridges, road sections and pavement repaired b
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • Two-way traffic between Pol-e-Khomri and Shirkhan operating on rehabilitated pavement by 12/31/04.ValueTwo-way traffic between Pol-e-Khomri and Shirkhan Pol-e-Khomri and Shirkhan pavement fully rehabilitPol-e-Khomri and Shirkhan pavement fully rehabilit
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • Kabul Airport achieves basic conditions allowing safe commercial air traffic in conformance with ICAO requirements by 12/31/03.ValueKabul Airport needed achievement of basic conditioKabul Airport achieved full runway rehabilitation Kabul Airport achieves basic conditions allowing s
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • At least 250km of rural roads improved by end of project. Maintenance plan for improved roads agreed and adopted by end of project.ValueAt least 250km of rural roads improvement was urge130km of secondary roads (Kunduz-Taloqan-Kishem) i130km of secondary roads improved by end of projec
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • Transport sector policy reforms developed and adopted by 12/31/03. Feasibility determined of studied projects by 12/31/03. Transport sector investment program developed by 12/31/03.ValueTransport sector policy reforms development was neTransport sector investment program developed in TTransport sector investment program and feasibilit
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment
  • Plan for improving sector capabilities for management and maintenance are established by 12/31/03.ValuePlan for improving sector capabilities for managemPlan for improving sector capabilities for managemPlan for improving sector capabilities for managem
    DateApril 1, 2003May 22, 2008June 30, 2008
    Comment