Abstract*

The objectives of the Ust-Kamenogorsk Environmental Remediation Project for Kazakhstan are to: (i) prevent the groundwater contamination plume's further migration towards the residential areas, the city's sources of drinking water supply and eventually into the Irtysh River; and (ii) strengthen institutional mechanisms for groundwater quality monitoring to enable control of ongoing groundwater pollution from local municipal and industrial sources...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project has two development objectives: (i) Prevent the groundwater contamination plume's further migration towards the residential areas, the city's sources of drinking water supply and eventually into the Irtysh River; and (ii) Strengthen institutional mechanisms for groundwater quality monitoring to enable control of ongoing groundwater pollution from local municipal and industrial sources.

Key Details

Project Details

  • P078342

  • Closed

  • Katelijn Van den Berg

  • Ministry of Agriculture,Republic of Kazakhstan

  • Kazakhstan

  • July 1, 2004

  • (as of board presentation)

    February 1, 2007

  • December 15, 2008

  • US$ 40.09 million

  • Committee of Water Resources

  • Europe and Central Asia

  • 2007

  • US$ 24.29 million

  • A

  • Not Applicable

  • December 31, 2016

  • BANK APPROVED

  • July 31, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 24.29
Borrower/Recipient 15.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 24.29
IDA Commitment N/A
IBRD + IDA Commitment 24.29
Lending Instrument
Grant Amount N/A
Total Project Cost** 40.09

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2014 IBRD-48480 Loan Cancel 7,000,000.00
Feb 1, 2007 IBRD-48480 Loan Commitment 24,290,000.00
Aug 15, 2013 IBRD-48480 Int Charges 30,069.53
Feb 15, 2014 IBRD-48480 Int Charges 6,714.97
Feb 15, 2014 IBRD-48480 Loan Repay 2,970,162.00
Feb 15, 2014 IBRD-48480 Int Charges 43.40
Feb 15, 2014 IBRD-48480 Int Charges 81.59
Feb 15, 2014 IBRD-48480 Int Charges 28,103.33
Sep 27, 2013 IBRD-48480 Loan Disb 466,000.03
Nov 12, 2013 IBRD-48480 Loan Disb 1,800,000.00
Aug 15, 2014 IBRD-48480 Int Charges 25,401.78
Aug 15, 2014 IBRD-48480 Int Charges 2,462.08
Aug 15, 2014 IBRD-48480 Loan Repay 2,030,125.20
Feb 15, 2015 IBRD-48480 Int Charges 21,337.74
Jun 2, 2014 IBRD-48480 Loan Disb 2,030,125.20
Aug 15, 2015 IBRD-48480 Int Charges 2,972.60
Aug 15, 2015 IBRD-48480 Int Charges 12,263.28
Aug 1, 2016 IBRD-48480 Loan Disb 97,858.27
Feb 15, 2016 IBRD-48480 Int Charges 15,363.57
Dec 30, 2015 IBRD-48480 Loan Disb 356,553.90
Feb 15, 2017 IBRD-48480 Int Charges 9.36
Aug 15, 2016 IBRD-48480 Int Charges 114.48
Aug 15, 2016 IBRD-48480 Int Charges 285.86
Aug 15, 2016 IBRD-48480 Int Charges 14,825.58
Aug 15, 2016 IBRD-48480 Int Charges 2,199.16
Aug 15, 2016 IBRD-48480 Loan Repay 356,553.90
Aug 15, 2017 IBRD-48480 Int Charges 14,672.54
Aug 16, 2017 IBRD-48480 Loan Cancel 11,835,300.00
Feb 15, 2017 IBRD-48480 Int Charges 14,884.93
Feb 15, 2017 IBRD-48480 Int Charges 800.24
Feb 15, 2017 IBRD-48480 Loan Repay 97,858.27
Feb 15, 2017 IBRD-48480 Int Charges 37.06
Aug 15, 2018 IBRD-48480 Int Charges 81.06
Aug 6, 2013 IBRD-48480 Loan Disb 704,162.06

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2016-12-29
Project Management Moderately Satisfactory 2016-12-29
Overall Implementation Progress (IP) Moderately Unsatisfactory 2016-12-29
Progress towards achievement of PDO Moderately Unsatisfactory 2016-12-29
Counterpart Funding Moderately Unsatisfactory 2016-12-29
Financial Management Moderately Satisfactory 2016-12-29
Monitoring and Evaluation Satisfactory 2016-12-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2017
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-21-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduce level of heavy metals & other hazardous pollutants in groundwater, thereby reducing risk of contamination of city's soil & groundwater system, drinking water wells, & surface water of Irtysh.ValueBased on the detailed one year monitoring campaignNo exceedings of maximum allowable concentrations Level of heavy metals pollution in groundwater red
    DateNovember 30, 2007December 30, 2016December 31, 2016
    Comment
  • Contaminated land managed or dump sites closed under the projectValue0.0031.5045.50
    DateDecember 15, 2008December 30, 2016December 31, 2016
    Comment
  • Preventing further pollution of the local underground and aquifer through containment of identified high-risk waste dumps and slurry ponds located in the city areaValueNo high risk waste dumps and slurry ponds identifi5 identified high risk waste dumps and slurry pond7 identified high risk waste dumps and slurry pond
    DateNovember 30, 2007December 30, 2016December 31, 2016
    Comment
  • Groundwater quality monitoring system is established and functioning and local institutions are capable of sampling and sample analysisValueNo groundwater quality monitoring system establishThree (3) phases of long term groundwater monitoriGroundwater quality monitoring system is establish
    DateDecember 15, 2008December 30, 2016December 31, 2016
    Comment
  • Direct project beneficiariesValue0.00207000.00300000.00
    DateDecember 15, 2008December 30, 2016December 31, 2016
    Comment
  • Female beneficiariesValue0.0050.0050.00
    DateDecember 15, 2008December 30, 2016December 31, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Eliminating pollution inflitration into the groundwater from these sitesValueNo target identifiedVerification of effectiveness of the containment tVerification of effectiveness of the containment t
    DateNovember 30, 2007December 30, 2016December 31, 2016
    Comment
  • Capacity of local institutions to implement and manage monitoring program has been increased.ValueCurrent monitoring capabilities are inadequate.Regular monitoring program now underway and implemImplementation of monitoring program is according
    DateNovember 30, 2007December 30, 2016December 31, 2016
    Comment