Skip to Main Navigation

HENAN TOWNS WATER SUPPLY AND SANITATION PROJECT

Abstract*

The Henan Towns Water Supply and Sanitation Project will help create or expand water supply and wastewater management services and improve the planning, regulatory, and operational capacity of sector institutions, thereby helping improve living conditions and the economic growth of participating county towns with relatively low incomes. The project consists of the following components: Component 1: water supply - water production facilities of about...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to assist the Borrower’s Henan Province in expanding its water supply and wastewater management services and improving the institutional capacity of relevant institutions to plan, regulate and operate such services.

Key Details

Project Details

  • P081348

  • Closed

  • Shunong Hu

  • N/A

  • China

  • September 27, 2005

  • (as of board presentation)

    June 27, 2006

  • December 18, 2006

  • US$ 150.00 million

  • B

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 58.36
International Bank for Reconstruction and Development 150.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 150.00
IDA Commitment N/A
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 208.36

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 15, 2021 IBRD-48290 Loan Repay 5,112,401.50
Jul 15, 2020 IBRD-48290 Int Charges 898,191.60
Jul 15, 2020 IBRD-48290 Loan Repay 4,978,368.50
Jan 15, 2020 IBRD-48290 Int Charges 1,110,619.00
Jan 15, 2020 IBRD-48290 Loan Repay 4,853,909.50
Jul 15, 2019 IBRD-48290 Int Charges 1,440,220.50
Jul 15, 2019 IBRD-48290 Loan Repay 4,729,450.00
Jun 27, 2006 IBRD-48290 Loan Commitment 150,000,000.00
Jul 15, 2024 IBRD-48290 Int Charges 8,179.68
Jul 15, 2024 IBRD-48290 Loan Repay 6,122,436.00
Jul 15, 2024 IBRD-48290 Int Charges 1,023,545.40
Jan 15, 2024 IBRD-48290 Loan Repay 5,964,468.50
Jan 15, 2024 IBRD-48290 Int Charges 18,804.37
Jan 15, 2024 IBRD-48290 Int Charges 1,204,759.50
Jul 15, 2023 IBRD-48290 Int Charges 65,330.71
Jul 15, 2023 IBRD-48290 Int Charges 1,162,261.90
Jul 15, 2023 IBRD-48290 Loan Repay 5,811,288.00
Jan 15, 2023 IBRD-48290 Int Charges 62,659.68
Jan 15, 2023 IBRD-48290 Int Charges 973,182.25
Jan 15, 2023 IBRD-48290 Loan Repay 5,667,681.00
Jul 15, 2022 IBRD-48290 Int Charges 257,842.05
Jul 15, 2022 IBRD-48290 Loan Repay 5,519,287.50
Jan 15, 2022 IBRD-48290 Int Charges 207,495.61
Jan 15, 2022 IBRD-48290 Loan Repay 5,380,467.50
Jul 15, 2013 IBRD-48290 Int Charges 337,183.12
Jul 15, 2013 IBRD-48290 Loan Repay 3,625,000.00
Nov 13, 2013 IBRD-48290 Loan Disb 5,122,465.00
Jul 16, 2013 IBRD-48290 Loan Disb 7,230,735.00
Jan 15, 2016 IBRD-48290 Int Charges 471,945.94
Jan 15, 2016 IBRD-48290 Loan Repay 3,949,186.80
Jul 15, 2015 IBRD-48290 Int Charges 407,771.62
Jul 15, 2015 IBRD-48290 Loan Repay 3,848,662.00
Jan 15, 2015 IBRD-48290 Int Charges 389,846.70
Jan 15, 2015 IBRD-48290 Loan Repay 3,752,924.00
Jul 15, 2014 IBRD-48290 Int Charges 866.00
Jul 15, 2014 IBRD-48290 Int Charges 1,659.32
Jul 15, 2014 IBRD-48290 Int Charges 380,493.03
Jul 15, 2014 IBRD-48290 Loan Repay 3,657,186.20
Jan 15, 2014 IBRD-48290 Int Charges 2,773.51
Jan 15, 2014 IBRD-48290 Int Charges 5,662.67
Jan 15, 2014 IBRD-48290 Int Charges 13,687.82
Jan 15, 2014 IBRD-48290 Int Charges 415,511.12
Jan 15, 2014 IBRD-48290 Loan Repay 3,720,000.00
Nov 19, 2013 IBRD-48290 Loan Disb 828,700.10
Nov 19, 2013 IBRD-48290 Loan Cancel 5,639,666.50
Oct 22, 2013 IBRD-48290 Loan Disb 5,554,450.00
Jul 15, 2013 IBRD-48290 Int Charges 59,518.09
Jan 15, 2019 IBRD-48290 Int Charges 1,377,204.00
Jan 15, 2019 IBRD-48290 Loan Repay 4,609,778.00
Jul 15, 2018 IBRD-48290 Int Charges 1,108,364.20
Jul 15, 2018 IBRD-48290 Loan Repay 4,494,892.50
Jan 15, 2018 IBRD-48290 Int Charges 961,331.50
Jan 15, 2018 IBRD-48290 Loan Repay 4,380,007.00
Jul 15, 2017 IBRD-48290 Int Charges 913,719.10
Jul 15, 2017 IBRD-48290 Loan Repay 4,265,121.50
Jan 15, 2017 IBRD-48290 Int Charges 757,654.10
Jan 15, 2017 IBRD-48290 Loan Repay 4,159,810.00
Jul 15, 2016 IBRD-48290 Int Charges 687,536.90
Jul 15, 2016 IBRD-48290 Loan Repay 4,054,498.20
Jul 15, 2021 IBRD-48290 Int Charges 251,559.55
Jul 15, 2021 IBRD-48290 Loan Repay 5,241,647.50
Jan 15, 2021 IBRD-48290 Int Charges 300,971.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Moderately Unsatisfactory 2013-06-25
Procurement Moderately Satisfactory 2013-06-25
Counterpart Funding Moderately Unsatisfactory 2013-06-25
Financial Management Moderately Satisfactory 2013-06-25
Overall Safeguards Rating Moderately Unsatisfactory 2013-06-25
Progress towards achievement of PDO Unsatisfactory 2013-06-25
Overall Implementation Progress (IP) Unsatisfactory 2013-06-25
Project Management Moderately Unsatisfactory 2013-06-25
Monitoring and Evaluation Moderately Satisfactory 2013-06-25

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-26-2013
OutcomesUnsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-17-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue1550.001934.302360.00
    DateJune 30, 2006May 31, 2013June 30, 2013
    CommentThe number is in thousand.The above figure reflects the value as of December 31, 2012. The number is in thousand.This is a revised target. The number is in thousand.
  • Number of water utilities that the project is supportingValue35.0020.0020.00
    DateJune 30, 2006May 31, 2013June 30, 2013
    CommentThere were 35 water supply companies to be supported by the Project at the project appraisal.The above figure reflects the value of December 31, 2012.This is a revised target.
  • Direct project beneficiariesValue1550.001934.302360.00
    DateJune 30, 2006May 31, 2013June 30, 2013
    CommentThe number is in thousand.The above figure reflects the value of December 31, 2012. The number is in thousand.This is a revised target.
  • Female beneficiariesValue50.0050.0050.00
    DateJune 30, 2006May 31, 2013June 30, 2013
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people with access to improved water supply in project towns (in thousands)Value1,5501934.34,202
    DateJune 30, 2006May 31, 2013June 30, 2013
    CommentNo change to the previous one updated in June 2012.The revised YR6 (2012) target was 2,360. The figure of 1934.3 is based on the data collected from 20 counties remaining in theproject at the end of 2012.The revised target in the restructuring is 2,360.
  • Number of people with access to wastewater management services in project towns (in thousands)Value364837811
    DateJune 30, 2006May 31, 2013June 30, 2013
    CommentNo change to the previous one updated in June 2012.Revised YR6 (2012) target was 563. The figure of 837 is based on the data collected from 20 counties remaining in the project atthe end of 2012. The ICR mission will review this data to make sure correct data are collected.The revised target in the Restructuring is 563.
  • Aggregate net profit after taxes of participating WSCs (in million RMB)Value-2.3-558.07110.4
    DateJune 30, 2006May 31, 2013June 30, 2013
    CommentNo change to the previous one updated in June 2012.Revised YR6 (2012) target = RMB 69.34 M. The figure of RMB -558.07 million is based on the data collected from 20 countiesremaining in the project at the end of 2012. The current data may not reflect the true financial status of the project utilities assome of them still remain under government control.The revised target in the restructuring is 69.34.