Hydrometerological System Modernization Project

Abstract*

The National Hydromet Modernization Project for the Russian Federation aims at increasing the accuracy of forecasts provided to the Russian people and economy by modernizing key elements of the technical base and strengthening RosHydromet's institutional arrangements. The project has the following four components: Component 1) will upgrade computing capacity and capacity for transmission, archiving and retrieval of data through three subcomponents:...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The main development objective of the project is to increase the accuracy of forecasts provided to the Russian people and economy by modernizing key elements of RosHydromet's technical base and strengthening its institutional arrangements. This would enable enterprise and household adjustments to protect lives and support economic growth.

Key Details

Project Details

  • P082239

  • Closed

  • Adriana Damianova

  • N/A

  • Russian Federation

  • October 8, 2003

  • (as of board presentation)

    March 17, 2005

  • December 12, 2005

  • US$ 80.00 million

  • C

  • Not Applicable

  • May 31, 2013

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 53.33
International Bank for Reconstruction and Development 80.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 80.00
IDA Commitment N/A
IBRD + IDA Commitment 80.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 133.33

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 17, 2005 IBRD-47690 Loan Commitment 80,000,000.00
Oct 15, 2014 IBRD-47690 Loan Repay 3,162,450.00
Oct 15, 2014 IBRD-47690 Loan Repay 156,446.03
Apr 15, 2014 IBRD-47690 Loan Repay 176,679.14
Apr 15, 2014 IBRD-47690 Int Charges -63.58
Apr 15, 2014 IBRD-47690 Int Charges 42.39
Apr 15, 2014 IBRD-47690 Int Charges 21.19
Apr 15, 2014 IBRD-47690 Loan Repay 3,142,217.00
Apr 15, 2014 IBRD-47690 Int Charges 13.39
Apr 15, 2014 IBRD-47690 Int Charges 24.13
Apr 15, 2014 IBRD-47690 Int Charges 176,679.14
Oct 15, 2013 IBRD-47690 Loan Repay 209,742.72
Oct 15, 2013 IBRD-47690 Int Charges 213.98
Oct 15, 2013 IBRD-47690 Int Charges 209,528.73
Oct 15, 2013 IBRD-47690 Loan Repay 3,121,296.50
Sep 30, 2013 IBRD-47690 Loan Cancel 206,288.80
Oct 15, 2016 IBRD-47690 Int Charges 254,835.36
Oct 15, 2016 IBRD-47690 Loan Repay 3,318,896.00
Apr 15, 2016 IBRD-47690 Int Charges 188,444.38
Apr 15, 2016 IBRD-47690 Loan Repay 3,130,451.80
Apr 15, 2016 IBRD-47690 Loan Repay 188,444.38
Oct 15, 2015 IBRD-47690 Int Charges 172,274.47
Oct 15, 2015 IBRD-47690 Loan Repay 3,318,896.00
Apr 15, 2015 IBRD-47690 Int Charges 153,403.80
Apr 15, 2015 IBRD-47690 Loan Repay 3,318,896.00
Apr 15, 2018 IBRD-47690 Loan Repay 298,600.88
Apr 15, 2018 IBRD-47690 Int Charges 298,600.88
Apr 15, 2018 IBRD-47690 Loan Repay 3,020,295.20
Oct 15, 2017 IBRD-47690 Loan Repay 3,007,156.00
Oct 15, 2017 IBRD-47690 Int Charges 311,740.20
Oct 15, 2017 IBRD-47690 Loan Repay 311,740.20
Apr 15, 2017 IBRD-47690 Loan Repay 3,318,896.00
Apr 15, 2017 IBRD-47690 Int Charges 306,048.00
Apr 15, 2020 IBRD-47690 Int Charges 207,016.20
Apr 15, 2020 IBRD-47690 Loan Repay 207,016.20
Apr 15, 2020 IBRD-47690 Loan Repay 3,111,879.80
Oct 15, 2019 IBRD-47690 Int Charges 0.01
Oct 15, 2019 IBRD-47690 Loan Repay 315,194.80
Oct 15, 2019 IBRD-47690 Int Charges -0.01
Oct 15, 2019 IBRD-47690 Int Charges 315,194.80
Oct 15, 2019 IBRD-47690 Loan Repay 3,003,701.20
Apr 15, 2019 IBRD-47690 Int Charges 365,822.50
Apr 15, 2019 IBRD-47690 Loan Repay 2,953,073.50
Apr 15, 2019 IBRD-47690 Loan Repay 365,822.50
Oct 15, 2018 IBRD-47690 Int Charges 396,212.30
Oct 15, 2018 IBRD-47690 Loan Repay 2,922,683.80
Oct 15, 2018 IBRD-47690 Loan Repay 396,212.30
Apr 15, 2022 IBRD-47690 Loan Repay 3,279,089.00
Apr 15, 2022 IBRD-47690 Int Charges 11,272.77
Oct 15, 2021 IBRD-47690 Int Charges 0.01
Oct 15, 2021 IBRD-47690 Int Charges 24,819.41
Oct 15, 2021 IBRD-47690 Loan Repay 3,318,896.00
Apr 15, 2021 IBRD-47690 Loan Repay 3,318,896.00
Apr 15, 2021 IBRD-47690 Int Charges 37,100.17
Apr 15, 2021 IBRD-47690 Loan Repay 0.01
Oct 15, 2020 IBRD-47690 Int Charges 115,052.00
Oct 15, 2020 IBRD-47690 Loan Repay 3,203,844.00
Oct 15, 2020 IBRD-47690 Loan Repay 115,052.00
Aug 21, 2013 IBRD-47690 Loan Disb -35,581.52
Oct 15, 2014 IBRD-47690 Int Charges 156,446.03

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2013-05-23
Progress towards achievement of PDO Satisfactory 2013-05-23
Financial Management Satisfactory 2013-05-23
Monitoring and Evaluation Satisfactory 2013-05-23
Overall Low 2013-05-23
Procurement Satisfactory 2013-05-23
Counterpart Funding Satisfactory 2013-05-23
Overall Implementation Progress (IP) Satisfactory 2013-05-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 11-30-2013
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-07-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Lead time increases for national and regional weather forecasts.ValueRegional forecasts at Novosibirsk and Khabarovsk aRegional forecasts at 36 hours lead time in lower Regional forecasts at Novosibirsk and Khabarovsk a
    DateFebruary 16, 2005April 9, 2013April 9, 2013
    CommentBeneficiaries survey shows high level of user's satisfaction.End target is achieved.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Computing centers obtain operational forecasts at higher resolution and using ensemble methods.ValueT170L31 or better resolution is not used for operaRHM uses a new version of the global weather forecT170L31 or better resolution is used for operation
    DateFebruary 16, 2005April 9, 2013April 9, 2013
    CommentEnd target was achieved by the original closing date September 30, 2010.End target is achieved.
  • Data collected and transmitted (including processed information) within Russia or globally does not encounter infrastrucuture bottlenecks in RosHydromet telecoms.Value87% of WMO reporting stations now report data to G92% of WMO-reporting stations now report data to G92% of WMO reporting stations now report data to G
    DateFebruary 16, 2005April 9, 2013April 9, 2013
    CommentTarget was revised and values increased during the MTR.End target achieved.End target is achieved by the original closing date and prior to restructuring.
  • Response time drops for requests for archived data.ValueTypical response time is now 14 days for an averagResponse time is up to several hours (less than 24Average response time for requesters to the Obnins
    DateFebruary 16, 2005April 9, 2013April 9, 2013
    CommentEnd target achieved.End target is achieved
  • Percentage of upper air stations in compliance with WMO requirementsValue5% (total of stations) - this value was re-evaluat62% of the total number of upper air stations are 62% (total of stations) - this value was re-evalua
    DateFebruary 16, 2005April 9, 2013April 9, 2013
    CommentThe baseline target was reevaluated during MTR and augmented.End target is achieved.End target is achieved.
  • Area covered by strong wind alarms and precipitationValuestrong wind alarms is 0 km2; 300,000 km2 for precThe GORF continues to implement own plan for incre100,000 km2 strong wind storm alarms 500,000 km2 f
    DateFebruary 16, 2005April 9, 2013April 9, 2013
    CommentThis target is delinked from project investments after the changes agreed during MTR. The MTR agreed to cancel procurement ofmeteorological radars and to re-allocate “released” funds to other high priority activities.Doppler radar program is being implemented using funds from RF.The GORF is currently implementing an investment program for Doppler radars with own funds.