Abstract*

The Central America Integration System for a Regional HIV/AIDS Project development objective is to provide knowledge, and tools to decision makers in all countries in the region, to manage and control HIV/AIDS, and other opportunistic infections. Component 1 - Regional Laboratory and contingencies, will support the establishment of a regional laboratory to implement highly-specialized functions, as a single regional institution. These functions include:...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to provide knowledge and tools to decision makers in all countries in the region to manage and control HIV/AIDS and other opportunistic infections . This objective would be achieved by providing countries with: (a) better access to high quality diagnosis of HIV/AIDS infections; (b) a regional second-generation surveillance system for the epidemic; (c) cross/fertilization of better practices in epidemic prevention and control; and (d) mechanisms to reduce the mobile populations vulnerability to HIV/AIDS.

Key Details

Project Details

  • P082243

  • Closed

  • Fernando Montenegro Torres

  • N/A

  • Central America

  • July 12, 2004

  • (as of board presentation)

    March 29, 2005

  • July 14, 2005

  • US$ 8.10 million

  • B

  • Not Applicable

  • November 30, 2010

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
The Global Fund to Fight AIDS, Tuberculosis & Malaria 0.10
IDA Credit 8.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 8.00
IBRD + IDA Commitment 8.00
Lending Instrument
Grant Amount 0.10
Total Project Cost** 8.10

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 29, 2005 IDA-H1540 Loan Commitment 8,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2010-12-17
Project Management Highly Satisfactory 2010-12-17
Overall Implementation Progress (IP) Satisfactory 2010-12-17
Procurement Moderately Satisfactory 2010-12-17
Financial Management Moderately Satisfactory 2010-12-17
Progress towards achievement of PDO Satisfactory 2010-12-17
Monitoring and Evaluation Satisfactory 2010-12-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-27-2011
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceModerately Satisfactory
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-01-2011PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Regional Action Plan adopted by the regional ministers of health at the Central American Commission of Ministers of Health (COMISCA).ValueNoYesYes
    DateJuly 14, 2005September 25, 2009November 30, 2010
    CommentThe Regional Strategy was approved by the Regional Coordination Mechanism and COMISCA. The Monitoring and evaluation plan forthisstrategy was presented to COMISCARegional Action Plan adopted by the regional ministers of health at the Central American Commission of Ministers of Health (COMISCA)

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Health personnel receiving trainingValue0.00784.00100.00
    DateApril 1, 2005November 4, 2010November 30, 2010
    Comment
  • No. of analytical and specialized techniques implemented by the Regional LaboratoryValue0.008.005.00
    DateJuly 14, 2005November 4, 2010November 30, 2010
    Comment
  • No. of analytical techniques transferred to at least four national laboratoriesValue0.005.004.00
    DateJuly 14, 2005November 4, 2010November 30, 2010
    Comment
  • Number of new techniques in national laboratories subjected to quality assurance auditsValue0.0012.0016.00
    DateJuly 14, 2005March 3, 2010November 30, 2010
    Comment
  • No. of analytical reports issued by the information systemValue0.000.007.00
    DateJuly 14, 2005November 4, 2010November 30, 2010
    CommentThe project was not able to implement the envisioned information system.
  • No. of countries that assess the HIV epidemic based on the second-generation second-generation surveillance system regional frameworkValue0.006.006.00
    DateJuly 14, 2005March 3, 2010November 30, 2010
    Comment
  • No. of policy documents on HIV prevention and comprehensive care presented to high-level regional meetings: COMISCA, SICA, and to the President#s Summit MeetingValue0.0013.009.00
    DateJuly 14, 2005November 4, 2010November 30, 2010
    Comment
  • No. of best practice reports disseminated annually throughout the regionValue0.003.002.00
    DateJuly 14, 2005March 3, 2010November 30, 2010
    Comment
  • No. of key persons engaged in best practice exchangesValue0.00820.00120.00
    DateJuly 14, 2007March 3, 2010November 30, 2010
    Comment
  • No. of ongoing prevention projects, carried out by NGOs, supported.Value0.0023.0018.00
    DateJuly 14, 2007March 3, 2010November 30, 2010
    Comment