Financier | Commitments |
---|---|
Borrower/Recipient | 3.50 |
IDA GRANT FOR HIV/AIDS | 35.00 |
P082604
Closed
Mai Thi Nguyen
N/A
January 27, 2004
(as of board presentation)
March 29, 2005
October 17, 2005
US$ 38.50 million
Minisry of Health
2005
US$ 35.00 million
B
Not Applicable
December 31, 2013
BANK APPROVED
June 17, 2013
Financier | Commitments |
---|---|
Borrower/Recipient | 3.50 |
IDA GRANT FOR HIV/AIDS | 35.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 35.00 |
IBRD + IDA Commitment | 35.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 38.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 29, 2005 | IDA-H1520 | Loan Commitment | 35,000,000.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2013-12-31 |
Overall Implementation Progress (IP) | Satisfactory | 2013-12-31 |
Progress towards achievement of PDO | Moderately Satisfactory | 2013-12-31 |
Monitoring and Evaluation | Moderately Satisfactory | 2013-12-31 |
Procurement | Moderately Satisfactory | 2013-12-31 |
Project Management | Satisfactory | 2013-12-31 |
Financial Management | Satisfactory | 2013-12-31 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2014 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Substantial |
Borrower Performance | Moderately Satisfactory |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 10-01-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percent of vulnerable groups in participating provinces reporting safer injection practices (from 20-70%) | Value | 20% | 82.7% | 70% |
Date | April 29, 2005 | December 3, 2013 | December 31, 2013 | |
Comment | IBBS results will be announced by the first quarter of 2014 and it will be reflected in ICR report. Therefore, the indicatorremains the same last year. |
Percent of vulnerable groups in participating provinces reporting condom use in sexual intercourse (from 40-80%) | Value | 40% | 85.2% | 80% |
Date | April 29, 2005 | December 3, 2013 | December 31, 2013 | |
Comment | IBBS results will be announced by the first quarter of 2014 and it will be reflected in ICR report. Therefore, the indicatorremains the same last year. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
An increased percentage of vulnerable groups (from an estimate 10% at baseline to 80% by project end) are reached by provincial services | Value | 10% | 85% | 80% |
Date | April 29, 2005 | December 3, 2013 | December 31, 2013 | |
Comment | HIV services at provinces included condoms ( free and social marketing), needles and syringes ( free and can be purchased at drugstore) at pharmacies), lubricant and condoms for MSM ( free), VCT, STI. Those activities are available to serve targeted groups. |
An increased percentage (for an estimated 10% at baseline to 90% at project end) of provinces prepare high quality provincial plans | Value | 10% | 91% | 90% |
Date | April 29, 2005 | December 3, 2013 | December 31, 2013 | |
Comment | This year is final year so, there is no Provincial Action Plan for 2014 to be evaluated. Therefore, percentage remains unchanged. |
An increased percentage of provinces (from 0 to 90% at project end) establish adequate M&E systems | Value | 0 | 100% | 90% |
Date | April 29, 2005 | December 3, 2013 | December 31, 2012 | |
Comment | all 32 project provinces set up and implemented the M&E Unit. Data base on epidemic has set up with additional MSM group. |
An increased percentage of provinces (from an estimated 10% at baseline to 80% at project end) meet targets specified in provincialplans | Value | 10% | 85% | 80% |
Date | April 29, 2005 | December 3, 2013 | December 31, 2013 | |
Comment | 5/32 provinces transferred harm reduction activities to other projects/national program. therefore, original targets were not met. |
Increased number of provinces offering Methadone sevices (from an estimated 0 at baseline to 6 by project end) | Value | 0 | 7 | 6 |
Date | April 29, 2005 | December 3, 2013 | December 31, 2013 | |
Comment | The number of provinces implementing the Methadone program was 7; this surpassed the project target (6 provinces). |
Increased number of injecting drug users enrolled in Methadone services (from an estimated 0 at baseline to 2000 by project end) | Value | 0 | 2167 | 2000 |
Date | April 29, 2005 | December 3, 2013 | December 31, 2013 | |
Comment | The number of patients who have received the Methadone program was over the target. It has reached 2167 patients. |