Health Sector Modernization Support Technical Assistance Project

Abstract*

The objectives of the Health Sector Modernization Support Technical Assistance (TA) Project are to support capacity building of the health system, to become more efficient in the financing, and delivery of health care services, and, to improve the quality of health care services, while maintaining access to care for the population, especially vulnerable groups. To this end, the components will: 1) Support TA for: a) improved financial management by...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the TAP is to assist the MOH in building the capacity of the health system to become more efficient in financing and delivering health care services and improving the quality of health care services while maintaining access to care for the population, especially the vulnerable groups, particularly through the institutional underpinning necessary to support the health sector reforms under the Program of the Government and to build the required institutional capacity in MOH, the Health Insurance Companies and related institutions.

Key Details

Project Details

  • P082879

  • Closed

  • Owen Smith

  • N/A

  • Slovak Republic

  • April 30, 2003

  • (as of board presentation)

    September 11, 2003

  • January 5, 2004

  • US$ 12.38 million

  • C

  • January 15, 2013

  • June 14, 2009

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 3.41
International Bank for Reconstruction and Development 12.38

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 12.38
IDA Commitment N/A
IBRD + IDA Commitment 12.38
Lending Instrument
Grant Amount N/A
Total Project Cost** 15.79

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 11, 2003 IBRD-71960 Loan Commitment 12,380,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2009-05-14
Monitoring and Evaluation Satisfactory 2009-05-14
Overall Implementation Progress (IP) Satisfactory 2009-05-14
Counterpart Funding Satisfactory 2009-05-14
Project Management Satisfactory 2009-05-14
Overall Safeguards Rating Satisfactory 2009-05-14
Progress towards achievement of PDO Satisfactory 2009-05-14
Procurement Satisfactory 2009-05-14

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-11-2009
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-21-2010PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

No data available.