Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IBRD Fund | 10.00 |
Global Environment Facility (GEF) | 6.00 |
Borrower/Recipient | 1.20 |
Local Communities | 0.90 |
P083045
Closed
Norman Bentley Piccioni
N/A
January 3, 2006
(as of board presentation)
June 15, 2006
January 18, 2007
US$ 18.10 million
National Environmental Authority
2006
US$ 6.00 million
B
Not Applicable
July 31, 2014
BANK APPROVED
July 23, 2015
Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IBRD Fund | 10.00 |
Global Environment Facility (GEF) | 6.00 |
Borrower/Recipient | 1.20 |
Local Communities | 0.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 6.00 |
Total Project Cost** | 18.10 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2014-11-29 |
Financial Management | Moderately Satisfactory | 2014-11-29 |
Summary Global Objective Rating | Satisfactory | 2014-11-29 |
Monitoring and Evaluation | Satisfactory | 2014-11-29 |
Counterpart Funding | Highly Satisfactory | 2014-11-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2014-11-29 |
Procurement | Moderately Satisfactory | 2014-11-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 07-24-2015 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 06-22-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Community associations and rural producer associations implement at least 450 natural resources, sustainable agriculture and conservation subprojects in the project area. | Value | None | 350 | 350 |
Date | June 15, 2006 | July 31, 2014 | July 31, 2014 | |
Comment | Target was revised during the MTR in June 2011. |
Protected area co-management agreements under implementation increases by at least 100%. | Value | 14 co-management agreements | 11 | 14 additional groups with comanagement agreements, |
Date | June 15, 2006 | July 31, 2014 | January 27, 2015 | |
Comment |
28 district-level CCAs and at least two UAMs established, trained and operating with financial plans. | Value | 18 CCAs and 0 UMAs. | 25 CCAs, 4 UMAs | 25 CCAs and 2 UMAs. |
Date | June 15, 2006 | July 31, 2014 | July 31, 2014 | |
Comment |
PES program piloted in two project sites and replication strategy developed. | Value | None | 0 | Two PES projects |
Date | June 15, 2006 | July 31, 2014 | July 31, 2014 | |
Comment | No pilot PES implemented |
By end of year three, monitoring systems developed by the project are incorporated into national (SINIA) and other international systems. | Value | None. | A national monitoring system for biodiversity impl | |
Date | June 15, 2006 | July 31, 2014 | January 27, 2015 | |
Comment |
Local and national institutional capacity is improved, as measured by the WWF/Bank Management Effectiveness (GEF BD SP 1) Tracking Tool to manage 14 protected areas (675,775 ha) | Value | 45% average rate for protected areas in 2005. | 70.1% average METT score | 14 protected areas with scores increases to the hi |
Date | June 15, 2006 | July 31, 2014 | January 27, 2015 | |
Comment |
At least 50,000 ha of forests and other natural ecosystems of global biodiversity significance in buffer zones and corridors under effective conservation (protection and sustainable management) | Value | 1,472 ha. | 43,109.36 | 50,000 ha by EOP |
Date | June 15, 2006 | July 31, 2014 | January 27, 2015 | |
Comment |
Biodiversity of global significance is under effective conservation, as measured by vegetation cover and indicator species of conservation interest. | Value | To be determined during FY 09 | Map completed | An updated map of vegetation cover estimated to be |
Date | June 15, 2006 | July 31, 2014 | January 27, 2015 | |
Comment | No baseline was determined in FY09. At MTR in June 2011, a decision was made to have ANAM update map of vegetation cover of 2000. | Waiting for official report. |
60% of districts in the project area have incorporated biodiversity aspects into sector policies and plans and adopted appropriate regulations and implementation plans accordingly. | Value | None. | 60% | 60% of districts. |
Date | June 15, 2006 | October 15, 2013 | July 31, 2014 | |
Comment |
Areas brought under enhanced biodiversity protection (ha) | Value | 32557.00 | 247645.00 | 248000.00 |
Date | June 15, 2006 | February 28, 2014 | July 31, 2014 | |
Comment |