Financier | Commitments |
---|---|
Borrower/Recipient | 219.87 |
International Bank for Reconstruction and Development | 180.00 |
P083322
Closed
Paul Procee
N/A
November 1, 2004
(as of board presentation)
September 7, 2006
January 5, 2007
US$ 399.87 million
N/A
2007
US$ 180.00 million
A
Not Applicable
December 31, 2013
BANK APPROVED
August 15, 2014
Financier | Commitments |
---|---|
Borrower/Recipient | 219.87 |
International Bank for Reconstruction and Development | 180.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 180.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 180.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 399.87 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2013 | IBRD-48380 | Int Charges | 475.64 |
May 15, 2024 | IBRD-48380 | Loan Repay | 7,535,000.00 |
Nov 15, 2013 | IBRD-48380 | Loan Repay | 4,290,000.00 |
Nov 15, 2014 | IBRD-48380 | Int Charges | 471,657.97 |
Nov 15, 2014 | IBRD-48380 | Loan Repay | 4,525,000.00 |
May 15, 2014 | IBRD-48380 | Int Charges | 509,696.97 |
May 15, 2014 | IBRD-48380 | Loan Repay | 4,405,000.00 |
Nov 15, 2015 | IBRD-48380 | Loan Repay | 4,775,000.00 |
Nov 15, 2015 | IBRD-48380 | Int Charges | 559,405.44 |
May 15, 2015 | IBRD-48380 | Int Charges | 481,860.20 |
May 15, 2015 | IBRD-48380 | Loan Repay | 4,650,000.00 |
May 15, 2017 | IBRD-48380 | Int Charges | 1,128,477.60 |
May 15, 2017 | IBRD-48380 | Loan Repay | 5,175,000.00 |
Nov 15, 2016 | IBRD-48380 | Int Charges | 910,378.30 |
Nov 15, 2016 | IBRD-48380 | Loan Repay | 5,040,000.00 |
May 15, 2016 | IBRD-48380 | Int Charges | 689,808.80 |
May 15, 2016 | IBRD-48380 | Loan Repay | 4,905,000.00 |
Nov 15, 2017 | IBRD-48380 | Int Charges | 1,249,491.90 |
Nov 15, 2017 | IBRD-48380 | Loan Repay | 5,315,000.00 |
May 15, 2018 | IBRD-48380 | Loan Repay | 5,460,000.00 |
May 15, 2018 | IBRD-48380 | Int Charges | 1,298,023.40 |
Nov 15, 2018 | IBRD-48380 | Int Charges | 1,816,462.40 |
Nov 15, 2018 | IBRD-48380 | Loan Repay | 5,610,000.00 |
May 15, 2019 | IBRD-48380 | Int Charges | 1,908,499.20 |
May 15, 2019 | IBRD-48380 | Loan Repay | 5,765,000.00 |
Nov 15, 2019 | IBRD-48380 | Loan Repay | 5,920,000.00 |
Nov 15, 2019 | IBRD-48380 | Int Charges | 1,698,349.60 |
May 15, 2020 | IBRD-48380 | Int Charges | 1,237,175.40 |
May 15, 2020 | IBRD-48380 | Loan Repay | 6,080,000.00 |
May 15, 2021 | IBRD-48380 | Int Charges | 333,510.60 |
May 15, 2021 | IBRD-48380 | Loan Repay | 6,415,000.00 |
Nov 15, 2020 | IBRD-48380 | Int Charges | 568,491.50 |
Nov 15, 2020 | IBRD-48380 | Loan Repay | 6,245,000.00 |
Nov 15, 2021 | IBRD-48380 | Int Charges | 302,014.28 |
Nov 15, 2021 | IBRD-48380 | Loan Repay | 6,590,000.00 |
May 15, 2022 | IBRD-48380 | Int Charges | 288,977.84 |
May 15, 2022 | IBRD-48380 | Loan Repay | 6,770,000.00 |
Nov 15, 2022 | IBRD-48380 | Int Charges | 1,037,885.80 |
Nov 15, 2022 | IBRD-48380 | Loan Repay | 6,955,000.00 |
Nov 15, 2023 | IBRD-48380 | Loan Repay | 7,340,000.00 |
May 15, 2023 | IBRD-48380 | Int Charges | 97,987.85 |
May 15, 2023 | IBRD-48380 | Int Charges | 1,559,961.80 |
May 15, 2023 | IBRD-48380 | Loan Repay | 7,145,000.00 |
Nov 15, 2023 | IBRD-48380 | Int Charges | 37,688.72 |
Nov 15, 2023 | IBRD-48380 | Int Charges | 1,672,683.60 |
Sep 7, 2006 | IBRD-48380 | Loan Commitment | 180,000,000.00 |
May 15, 2024 | IBRD-48380 | Int Charges | 10,995.71 |
May 15, 2024 | IBRD-48380 | Int Charges | 1,537,735.80 |
Nov 15, 2013 | IBRD-48380 | Int Charges | 581,886.50 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2013-06-22 |
Financial Management | Satisfactory | 2013-06-22 |
Overall Implementation Progress (IP) | Satisfactory | 2013-06-22 |
Project Management | Satisfactory | 2013-06-22 |
Progress towards achievement of PDO | Satisfactory | 2013-06-22 |
Procurement | Satisfactory | 2013-06-22 |
Monitoring and Evaluation | Satisfactory | 2013-06-22 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-19-2014 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 02-23-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Evidence that identified bottlenecks have been removed, as expected by the strategic investments of the project, including a high level of satisfaction among users of investments and PAP | Value | Not applicable | Time savings on the roads are apparent adn overal | Evidence identified via reports from technical and |
Date | September 7, 2006 | April 30, 2013 | June 28, 2013 | |
Comment | Critical bottlenecks have been addressed and roads are operational. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Mianyang: Area of land sold (ha) | Value | 0 | Pioneer Park: 208haSEDZ: 192.4ha | Pioneer Park: 238; SEDZ: 312 |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | The previous number in the report for SEDZ was wrong and has been corrected. | Difficult to quantify in how far this (infrastructure) project contributes to land sales and values. |
Mianyang: Number of new residents on site | Value | 0 | Pioneer Park: 65,020SEDZ: 3,850 | 30,440 (Pioneer Park), 18,202 (SEDZ) |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | The numbers reflect changes in policies after the Earthquake, with more residents moving to PP. |
Mianyang: Satisfaction of PAPs with resettlement process and outcome in both Pioneer Park and SEDZ. | Value | Not applicable | 75% of PAPs satisfied with resettlement process an | |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | Final survey is being prepared as the reported number of 100% is not believable and need to be substantiated. |
Suining: Area of land sold (ha) | Value | 0 | 70.6ha | 141 ha |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | Difficult to quantify in how far this (infrastructure) project contributes to this indicator (land area sold). |
Suining: Number of new residents on site | Value | 0 | 17,500 | 19,820 |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment |
Suining: Satisfaction of PAPs with resettlement process and outcome | Value | Not applicable | 75% of PAPs satisfied with resettlement process an | |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | Site visits find the majority of PAP satisfied, but more detailed information needs to be collected after completion of activities. |
Yibin: Reduced travel time from Mianjiang Bridge to Chang Jiang Bridge: Travel time in minutes at peak | Value | 10 min | 6 min | 7.5 min |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment |
Yibin: Satisfaction level of landscape improvements | Value | Not applicable | 75% of sampled people satisfied with landscape imp | |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | A proper survey needs to be conducted. |
Yibin: Satisfaction of PAPs with resettlement process and outcome | Value | Not applicable | 75% of PAPs satisfied with resettlement process an | |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | A proper survey needs to be conducted. |
Panzhihua: Wastewater service coverage (average wastewater volume collected and treated, 1000 m3/d) | Value | 40 | 88 | 85 |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | Revised since the previous number was wrong (referred to length of sewer constructed). |
Panzhihua: Reduced travel time at peak in minutes -- East Duren Road at KM 49 to railway station | Value | 56.4 min. | 20 | 49.9 min. |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | Greatly reduced as a result of a tunnel built. |
Panzhihua: Satisfaction level of scenic improvements | Value | Not applicable | 75% of sampled people satisfied with landscape imp | |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | Results will be provided as part of the final survey. |
Panzhihua: Satisfaction of PAPs with resettlement process and outcome | Value | Not applicable | 75% of PAPs satisfied with resettlement process an | |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | A survey will be conducted at the end of project when resettlement activities have been fully completed. |
Suining: Travel time in minutes at peak from Railway station to Xining District | Value | 25 min | 16 min | |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | No data has been reported recently. |
Roads constructed, non-rural | Value | 0.00 | 80.70 | 87.10 |
Date | December 1, 2005 | April 30, 2013 | June 28, 2013 | |
Comment | This include all roads and sewage and drainage pipelines (including service roads as described in the restructuring paper). | Core indicators being measured first time at an aggregate level for all cities. | Cumulative for all 4 cities. |
People provided with access to ‘improved sanitation facilities” under the proj. | Value | 0.00 | 21300.00 | 24375.00 |
Date | April 30, 2013 | June 30, 2013 | ||
Comment | Based on number of households connected (7,100) x 3 people/household. |
People provided with access to “improved sanitation facilities” - urban | Value | 0.00 | 21300.00 | 24375.00 |
Date | April 30, 2013 | June 30, 2013 | ||
Comment | Based on number of households connected (7,100) x 3 people/household. | Based on number of households connected (8,125) x 3 people/household. |