Financier | Commitments |
---|---|
European Bank for Reconstruction and Development | 7.00 |
GLOBAL ENVIRONMENT - Associated IDA Fund | 3.00 |
Borrower/Recipient | 0.45 |
IDA Credit | 5.00 |
Sub-borrower(s) | 6.60 |
Borrowing Country's Fin. Intermediary/ies | 3.00 |
P083352
Closed
Gevorg Sargsyan
N/A
January 3, 2005
(as of board presentation)
March 29, 2006
August 4, 2006
US$ 25.05 million
N/A
2006
US$ 12.00 million
F
Not Applicable
June 30, 2011
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
European Bank for Reconstruction and Development | 7.00 |
GLOBAL ENVIRONMENT - Associated IDA Fund | 3.00 |
Borrower/Recipient | 0.45 |
IDA Credit | 5.00 |
Sub-borrower(s) | 6.60 |
Borrowing Country's Fin. Intermediary/ies | 3.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 5.00 |
IBRD + IDA Commitment | 5.00 |
Lending Instrument | |
---|---|
Grant Amount | 7.00 |
Total Project Cost** | 25.05 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2024 | IDA-41590 | Loan Repay | 242.56 |
Nov 15, 2023 | IDA-41590 | Loan Repay | 43,514.71 |
Nov 15, 2023 | IDA-41590 | Int Charges | 767.88 |
Nov 15, 2023 | IDA-41590 | Int Charges | 30,923.96 |
Nov 15, 2023 | IDA-41590 | Int Charges | 13,870.33 |
Nov 15, 2023 | IDA-41590 | Int Charges | 13,870.33 |
May 15, 2023 | IDA-41590 | Int Charges | 14,206.04 |
May 15, 2023 | IDA-41590 | Int Charges | 14,206.04 |
May 15, 2023 | IDA-41590 | Int Charges | 31,423.08 |
May 15, 2020 | IDA-41590 | Int Charges | 93.01 |
May 15, 2020 | IDA-41590 | Loan Repay | 44,598.68 |
May 15, 2020 | IDA-41590 | Int Charges | 15,386.53 |
May 15, 2020 | IDA-41590 | Int Charges | 15,386.53 |
May 15, 2020 | IDA-41590 | Int Charges | 34,876.18 |
Nov 15, 2021 | IDA-41590 | Int Charges | 15,383.48 |
Nov 15, 2021 | IDA-41590 | Int Charges | 15,383.48 |
Nov 15, 2021 | IDA-41590 | Int Charges | 439.48 |
Nov 15, 2021 | IDA-41590 | Int Charges | 439.48 |
Nov 15, 2021 | IDA-41590 | Loan Repay | 46,092.75 |
May 15, 2021 | IDA-41590 | Int Charges | 15,480.20 |
May 15, 2023 | IDA-41590 | Int Charges | 934.93 |
May 15, 2023 | IDA-41590 | Int Charges | 934.93 |
May 15, 2023 | IDA-41590 | Loan Repay | 44,049.80 |
Nov 15, 2022 | IDA-41590 | Loan Repay | 2,118.88 |
Nov 15, 2022 | IDA-41590 | Loan Repay | 41,055.28 |
Nov 15, 2022 | IDA-41590 | Int Charges | 13,169.24 |
Nov 15, 2022 | IDA-41590 | Int Charges | 13,169.24 |
Nov 15, 2017 | IDA-41590 | Int Charges | 1,545.32 |
Nov 15, 2017 | IDA-41590 | Loan Repay | 46,355.54 |
Nov 15, 2017 | IDA-41590 | Int Charges | 16,861.86 |
Nov 15, 2017 | IDA-41590 | Int Charges | 16,861.86 |
Nov 15, 2017 | IDA-41590 | Int Charges | 38,220.14 |
Nov 15, 2019 | IDA-41590 | Loan Repay | 708.00 |
Nov 15, 2019 | IDA-41590 | Loan Repay | 44,386.74 |
Nov 15, 2019 | IDA-41590 | Int Charges | 15,726.79 |
Nov 15, 2019 | IDA-41590 | Int Charges | 15,726.79 |
Nov 15, 2019 | IDA-41590 | Int Charges | 35,553.36 |
May 15, 2019 | IDA-41590 | Loan Repay | 1,492.87 |
May 15, 2019 | IDA-41590 | Loan Repay | 43,858.41 |
May 15, 2019 | IDA-41590 | Int Charges | 36,235.68 |
May 15, 2019 | IDA-41590 | Int Charges | 15,986.31 |
May 15, 2019 | IDA-41590 | Int Charges | 15,986.31 |
Nov 15, 2018 | IDA-41590 | Int Charges | 16,148.71 |
Nov 15, 2018 | IDA-41590 | Int Charges | 16,148.71 |
Nov 15, 2018 | IDA-41590 | Int Charges | 36,603.70 |
May 15, 2021 | IDA-41590 | Int Charges | 15,480.20 |
May 15, 2021 | IDA-41590 | Int Charges | 223.56 |
May 15, 2021 | IDA-41590 | Loan Repay | 47,200.67 |
Nov 15, 2020 | IDA-41590 | Loan Repay | 45,270.15 |
Nov 15, 2020 | IDA-41590 | Int Charges | 15,895.88 |
Nov 15, 2020 | IDA-41590 | Int Charges | 15,895.88 |
Nov 15, 2020 | IDA-41590 | Loan Repay | 1,311.10 |
Nov 15, 2020 | IDA-41590 | Int Charges | 35,809.98 |
Nov 15, 2015 | IDA-41590 | Int Charges | 38,597.40 |
May 15, 2017 | IDA-41590 | Int Charges | 16,522.27 |
May 15, 2017 | IDA-41590 | Int Charges | 16,522.27 |
May 15, 2017 | IDA-41590 | Int Charges | 35,951.71 |
May 15, 2017 | IDA-41590 | Loan Repay | 42,257.20 |
May 15, 2017 | IDA-41590 | Loan Repay | 2,701.38 |
Nov 15, 2016 | IDA-41590 | Int Charges | 16,607.96 |
Nov 15, 2016 | IDA-41590 | Int Charges | 16,607.96 |
Nov 15, 2016 | IDA-41590 | Int Charges | 37,644.62 |
Nov 15, 2016 | IDA-41590 | Int Charges | 1,215.48 |
Nov 15, 2016 | IDA-41590 | Loan Repay | 44,735.16 |
May 15, 2016 | IDA-41590 | Loan Repay | 1,095.60 |
May 15, 2016 | IDA-41590 | Loan Repay | 45,195.30 |
May 15, 2016 | IDA-41590 | Int Charges | 17,359.11 |
May 15, 2016 | IDA-41590 | Int Charges | 17,359.11 |
May 15, 2016 | IDA-41590 | Int Charges | 38,089.52 |
Nov 15, 2018 | IDA-41590 | Loan Repay | 43,539.89 |
Nov 15, 2018 | IDA-41590 | Loan Repay | 1,789.75 |
May 15, 2018 | IDA-41590 | Loan Repay | 792.26 |
May 15, 2018 | IDA-41590 | Loan Repay | 46,064.58 |
May 15, 2018 | IDA-41590 | Int Charges | 16,868.45 |
May 15, 2018 | IDA-41590 | Int Charges | 16,868.45 |
May 15, 2018 | IDA-41590 | Int Charges | 38,235.19 |
Nov 15, 2014 | IDA-41590 | Int Charges | 17,907.58 |
Nov 15, 2014 | IDA-41590 | Int Charges | 17,907.58 |
Nov 15, 2014 | IDA-41590 | Int Charges | 105.18 |
Nov 15, 2014 | IDA-41590 | Int Charges | 105.18 |
May 15, 2015 | IDA-41590 | Int Charges | 16,982.26 |
May 15, 2015 | IDA-41590 | Int Charges | 16,982.26 |
May 15, 2015 | IDA-41590 | Int Charges | 37,675.63 |
May 15, 2015 | IDA-41590 | Int Charges | 438.49 |
May 15, 2015 | IDA-41590 | Int Charges | 438.49 |
May 15, 2014 | IDA-41590 | Int Charges | 110.28 |
May 15, 2014 | IDA-41590 | Int Charges | 110.28 |
May 15, 2014 | IDA-41590 | Int Charges | 18,975.49 |
May 15, 2014 | IDA-41590 | Int Charges | 18,975.49 |
Nov 15, 2013 | IDA-41590 | Int Charges | 201.65 |
Nov 15, 2013 | IDA-41590 | Int Charges | 201.65 |
Nov 15, 2013 | IDA-41590 | Int Charges | 18,486.55 |
Nov 15, 2013 | IDA-41590 | Int Charges | 18,486.55 |
Nov 15, 2015 | IDA-41590 | Int Charges | 17,028.28 |
Nov 15, 2015 | IDA-41590 | Int Charges | 17,028.28 |
Nov 15, 2015 | IDA-41590 | Int Charges | 1,770.54 |
May 15, 2022 | IDA-41590 | Loan Repay | 42,731.17 |
May 15, 2022 | IDA-41590 | Loan Repay | 928.54 |
May 15, 2022 | IDA-41590 | Int Charges | 14,407.69 |
May 15, 2022 | IDA-41590 | Int Charges | 14,407.69 |
Mar 29, 2006 | IDA-41590 | Loan Commitment | 5,000,000.00 |
May 15, 2024 | IDA-41590 | Int Charges | 13,675.80 |
May 15, 2024 | IDA-41590 | Int Charges | 13,675.80 |
May 15, 2024 | IDA-41590 | Int Charges | 30,998.51 |
May 15, 2024 | IDA-41590 | Int Charges | 514.22 |
May 15, 2024 | IDA-41590 | Loan Repay | 43,172.73 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2011-03-11 |
Overall Safeguards Rating | Satisfactory | 2011-03-11 |
Procurement | Satisfactory | 2011-03-11 |
Project Management | Satisfactory | 2011-03-11 |
Overall Safeguards Rating | Satisfactory | 2011-03-11 |
Progress towards achievement of PDO | Satisfactory | 2011-03-11 |
Financial Management | Satisfactory | 2011-03-11 |
Monitoring and Evaluation | Satisfactory | 2011-03-11 |
Overall Implementation Progress (IP) | Satisfactory | 2011-03-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2012 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 09-17-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Highly Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Installed capacity MW of renewables connected to the power grid (MW) | Value | 47 | 130 | 127 |
Date | March 31, 2006 | December 31, 2010 | June 30, 2011 | |
Comment | The end target was exceeded by December 31, 2010. |
Renewable generation added to the generation mix (GWh) | Value | 137 | 417 | 336 |
Date | March 31, 2006 | December 31, 2010 | June 30, 2011 | |
Comment | The end-target was reached in mid 2010. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Laws and regulations to improve the environment for the development of renewables are prepared and enacted | Value | A number of legal and regulatory impediments for d | Several key improvements in legal and regulatory f | The relevant package is enacted |
Date | March 31, 2006 | December 31, 2010 | December 31, 2009 | |
Comment | The work of the government inter-sectoral commission established to pursue enactment of legislative amendments to remove barriersto development of renewables continues. |
The renewable energy Geographic Information System, Integrated Database and web portal provide comprehensive national data (# of Regions/Marzes) on renewable resources | Value | GIS and database for one marz are piloted | GIS and database for the entire country prepared | GIS database and web portal for the entire country |
Date | March 31, 2006 | December 31, 2010 | December 31, 2009 | |
Comment | The end-target was reached in August 2009. |
Aggregate dollar amount of investments financed or leveraged by the participating financial institution or the R2E2 Fund (million US$) | Value | Zero | 27 | 21 |
Date | March 31, 2006 | December 31, 2011 | June 30, 2011 | |
Comment | The end-target was exceeded in 2009 due to large co-financing by project developers. |
Loan repayment rate by the Project beneficiaries | Value | Zero | 95% | 95% |
Date | March 31, 2006 | December 31, 2011 | June 30, 2011 | |
Comment |
Iincreased displacement of CO2 emission (tCO2) | Value | 89,050 | 270,770 | 218,400 |
Date | March 31, 2006 | December 31, 2010 | June 30, 2011 | |
Comment | The end-target was reached in mid 2010 |