Third Tamil Nadu Urban Development Project (TNUDP III)

Abstract*

The Third Tamil Nadu Urban Development Project for India aims at improving the delivery of urban services through enhancing the quality of urban infrastructure and strengthening the institutional and financial framework. The Project will consist of two complementary components: Component 1) will provide support for management improvements and institutional changes, including provision of goods, technical assistance, workshops, and staff training to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the project is to improve the delivery of urban services through enhancing the quality of urban infrastructure and strengthening the institutional and financial framework. The proposed repeater project would build on and consolidate the achievements of TNUDP II, continuing to improve urban infrastructure services in Tamil Nadu in a sustainable manner. The two main objectives are: to strengthen and deepen the empowerment of ULBs by continuing the decentralization process through delegation of powers from state level bodies to ULBs; and through continuing and expanding the capacity building programs started under TNUDP II; and to mobilize resources on a sustainable basis for urban infrastructure investments through: - mobilizing private financing for ULB infrastructure investments by linking ULBs to the financial markets through the intermediation of the Tamil Nadu Urban Development Fund (TNUDF); - providing incentives for investments in low income neighborhoods through the use of supporting capital grants.

Key Details

Project Details

  • P083780

  • Closed

  • Raghu Kesavan

  • N/A

  • India

  • June 24, 2004

  • (as of board presentation)

    July 5, 2005

  • October 19, 2005

  • US$ 435.00 million

  • N/A

  • South Asia

  • 2006

  • US$ 300.00 million

  • F

  • Not Applicable

  • March 31, 2014

  • BANK APPROVED

  • April 16, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 300.00
Borrower/Recipient 95.00
Local Sources of Borrowing Country 40.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 435.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 15, 2015 IBRD-47980 Int Charges 2,632.35
Mar 15, 2015 IBRD-47980 Int Charges 659.23
Mar 15, 2015 IBRD-47980 Int Charges 918.13
Mar 15, 2015 IBRD-47980 Int Charges 698,751.50
Sep 15, 2014 IBRD-47980 Int Charges 679,052.70
Mar 15, 2016 IBRD-47980 Int Charges 923,824.10
Mar 15, 2016 IBRD-47980 Loan Repay 8,820,342.00
Sep 15, 2015 IBRD-47980 Int Charges -129.07
Sep 15, 2015 IBRD-47980 Int Charges 86.05
Sep 15, 2015 IBRD-47980 Int Charges 43.02
Sep 15, 2015 IBRD-47980 Int Charges 65.14
Sep 15, 2015 IBRD-47980 Int Charges 795,982.50
Sep 15, 2015 IBRD-47980 Loan Repay 8,676,219.00
Sep 15, 2016 IBRD-47980 Int Charges 1,290,643.40
Sep 15, 2016 IBRD-47980 Loan Repay 8,969,270.00
Mar 15, 2017 IBRD-47980 Loan Repay 9,123,001.00
Sep 15, 2017 IBRD-47980 Int Charges 1,718,236.40
Sep 15, 2017 IBRD-47980 Loan Repay 9,276,733.00
Mar 15, 2017 IBRD-47980 Int Charges 1,575,073.10
Sep 15, 2018 IBRD-47980 Int Charges 2,277,463.20
Sep 15, 2018 IBRD-47980 Loan Repay 9,589,000.00
Mar 15, 2018 IBRD-47980 Loan Repay 9,430,464.00
Mar 15, 2018 IBRD-47980 Int Charges 1,637,952.00
Mar 15, 2019 IBRD-47980 Int Charges 2,330,021.20
Mar 15, 2019 IBRD-47980 Loan Repay 9,747,535.00
Sep 15, 2019 IBRD-47980 Int Charges 2,311,999.20
Sep 15, 2019 IBRD-47980 Loan Repay 9,915,679.00
Mar 15, 2020 IBRD-47980 Int Charges 1,698,339.50
Mar 15, 2020 IBRD-47980 Loan Repay 10,079,019.00
Mar 15, 2021 IBRD-47980 Loan Repay 10,420,110.00
Mar 15, 2021 IBRD-47980 Int Charges 435,355.34
Sep 15, 2020 IBRD-47980 Int Charges 758,842.00
Sep 15, 2020 IBRD-47980 Loan Repay 10,247,163.00
Sep 15, 2021 IBRD-47980 Loan Repay 10,597,863.00
Sep 15, 2021 IBRD-47980 Int Charges 365,056.60
Mar 15, 2022 IBRD-47980 Int Charges 308,014.30
Mar 15, 2022 IBRD-47980 Loan Repay 10,775,615.00
Sep 15, 2022 IBRD-47980 Int Charges 670,433.56
Sep 15, 2022 IBRD-47980 Loan Repay 10,953,367.00
Sep 15, 2023 IBRD-47980 Loan Repay 11,328,087.00
Mar 15, 2023 IBRD-47980 Loan Repay 11,140,727.00
Mar 15, 2023 IBRD-47980 Int Charges 92,001.59
Mar 15, 2023 IBRD-47980 Int Charges 1,685,114.00
Sep 15, 2023 IBRD-47980 Int Charges 26,623.96
Sep 15, 2023 IBRD-47980 Int Charges 1,646,480.60
Jul 5, 2005 IBRD-47980 Loan Commitment 300,000,000.00
Mar 15, 2024 IBRD-47980 Int Charges 30,049.20
Mar 15, 2024 IBRD-47980 Int Charges 1,480,923.60
Mar 15, 2024 IBRD-47980 Loan Repay 11,515,447.00
Aug 20, 2013 IBRD-47980 Loan Disb 1,672,882.00
Jul 19, 2013 IBRD-47980 Loan Disb 346,621.62
Jul 31, 2014 IBRD-47980 Loan Cancel 8,491,412.00
Dec 12, 2013 IBRD-47980 Loan Disb 510,842.16
Dec 12, 2013 IBRD-47980 Loan Disb 2,998,889.00
Oct 1, 2013 IBRD-47980 Loan Disb 294,111.06
Nov 22, 2013 IBRD-47980 Loan Disb 2,315,494.00
Feb 11, 2014 IBRD-47980 Loan Disb 1,000,000.00
Sep 15, 2013 IBRD-47980 Int Charges 747,129.00
Sep 15, 2013 IBRD-47980 Loan Repay 8,431,909.00
Sep 15, 2013 IBRD-47980 Int Charges 59,298.17
Sep 15, 2013 IBRD-47980 Int Charges 132.80
Sep 15, 2013 IBRD-47980 Int Charges 373.47
Jun 13, 2014 IBRD-47980 Loan Disb 2,057,178.80
Jun 26, 2014 IBRD-47980 Loan Disb 3,338,636.00
Mar 27, 2014 IBRD-47980 Loan Disb 6,761,355.00
Apr 21, 2014 IBRD-47980 Loan Disb 449,491.53
Apr 3, 2014 IBRD-47980 Loan Disb 8,470,172.00
Mar 15, 2014 IBRD-47980 Int Charges 435.61
Mar 15, 2014 IBRD-47980 Int Charges 783.37
Mar 15, 2014 IBRD-47980 Int Charges 47,782.65
Mar 15, 2014 IBRD-47980 Int Charges 682,481.56
Mar 15, 2014 IBRD-47980 Loan Repay 8,571,609.00
Sep 26, 2013 IBRD-47980 Loan Disb 699,876.44
Sep 25, 2013 IBRD-47980 Loan Disb 760,239.56
Sep 15, 2014 IBRD-47980 Loan Repay 8,716,299.00
Sep 15, 2014 IBRD-47980 Int Charges 219.18
Sep 15, 2014 IBRD-47980 Int Charges 349.71
Sep 15, 2014 IBRD-47980 Int Charges 20,843.54
Feb 6, 2015 IBRD-47980 Loan Disb -169,761.80
Jul 18, 2014 IBRD-47980 Loan Disb 60,487.76
Jul 14, 2014 IBRD-47980 Loan Disb 3,432,277.50
Jul 30, 2014 IBRD-47980 Loan Disb 1,971,856.50
Feb 6, 2015 IBRD-47980 Loan Cancel 169,761.80
Mar 15, 2015 IBRD-47980 Loan Repay 8,538,791.00
Mar 15, 2015 IBRD-47980 Int Charges -7,897.06
Mar 15, 2015 IBRD-47980 Int Charges 5,264.71

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2013-10-30
Counterpart Funding Satisfactory 2013-10-30
Project Management Moderately Satisfactory 2013-10-30
Monitoring and Evaluation Satisfactory 2013-10-30
Overall Implementation Progress (IP) Satisfactory 2013-10-30
Overall Safeguards Rating Moderately Satisfactory 2013-10-30
Progress towards achievement of PDO Satisfactory 2013-10-30
Financial Management Satisfactory 2013-10-30
Overall Moderately Low 2013-10-30
Overall Safeguards Rating Moderately Satisfactory 2013-10-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-30-2014
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-12-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1. Strengthen empowerment and institutional capacity of ULBs by continuing delegation of powers, capacity building programs and specific IT related initiatives.Value0, This project will carry forward the IT related 4940 (80%) newly created ULBs are fully IT enabled.
    DateJuly 12, 2005August 31, 2013March 31, 2014
    Comment
  • 2. Improved urban service delivery, in terms of coverage and quality.Value057%80% participating ULBs (receiving over Rs.1Crore)
    DateJuly 1, 2005August 31, 2013March 31, 2014
    CommentExpected to attain 87% based on other sub-projects currently under implementation.
  • 3. Expand resource mobilization for urban infrastructure investments.Value0US$ 40 millionUS$40 million
    DateJuly 1, 2005August 31, 2013March 31, 2014
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of participating ULBs completing GIS mapping and implementation of new IT systems for core municipal functions.Value-5 & 497(mapping) & 52 (IT enabled processes) in newly fo
    DateJuly 1, 2005August 31, 2013March 31, 2014
    CommentSurvey and GIS base mapping now available for 5 pilot ULBs - web based applications and integration of these maps underway.
  • Improved financial soundness of participating ULBs through cost recovery, increased own revenues, better debt managementValue065% of participating ULBs where water-supply sub-p70% of water/sewerage sub-projects (that account f
    DateJuly 1, 2005August 31, 2013March 31, 2014
    CommentIn addition, all ULBs where sewerage sub-projects are being undertaken have already resolved introduce new sewerage tariffs thatwill cover O&M costs.
  • Expand resource mobilization for Urban Infrastructure through non-traditional sourcesValue0US$ 40 millionUS$40 million
    DateJuly 1, 2005August 31, 2013March 31, 2014
    Comment
  • Total quantum of urban subprojects approved and fully implemented at ULBs / Chennai Metro areaValue0US$ 458 million of sub-projects approved and takenUS$434 million
    DateJuly 1, 2005August 31, 2013March 31, 2014
    Comment
  • Road length (in km) in good condition out of roads upgraded as part of the project in Chennai Metropolitan area.Value0 km1536.05km (revised figure)
    DateJuly 1, 2005August 31, 2013March 31, 2014
    CommentExpected to reach 32 km by closing.
  • Financial Sustainability of TNUDF as measured by annual repayment rate performance of its loan portfolioValue> 95%100%Maintain > 95%
    DateJuly 1, 2005August 31, 2013March 29, 2014
    CommentAs per audited financial statements for FY 13
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue0.00500000.001300000.00
    DateJuly 1, 2005August 31, 2013March 31, 2014
    CommentThe previous figure stands corrected.
  • New household sewer connections constructed under the projectValue0.00120000.00150000.00
    DateJuly 1, 2005August 31, 2013March 31, 2014
    Comment