Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 8.90 |
P083929
Closed
Shahnaz Arshad
N/A
August 5, 2003
(as of board presentation)
June 1, 2006
June 13, 2006
US$ 58.90 million
N/A
2006
US$ 50.00 million
A
April 11, 2014
November 30, 2013
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 8.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 50.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 58.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 15, 2018 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2019 | IBRD-73800 | Int Charges | 403,217.84 |
Mar 15, 2019 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2020 | IBRD-73800 | Int Charges | 286,535.06 |
Mar 15, 2020 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2019 | IBRD-73800 | Int Charges | 397,461.03 |
Sep 15, 2019 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2021 | IBRD-73800 | Int Charges | 55,547.64 |
Mar 15, 2021 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2020 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2020 | IBRD-73800 | Int Charges | 115,084.26 |
Mar 15, 2022 | IBRD-73800 | Int Charges | 34,287.12 |
Mar 15, 2022 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2015 | IBRD-73800 | Int Charges | 138,628.19 |
Sep 15, 2015 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2016 | IBRD-73800 | Int Charges | 159,073.34 |
Mar 15, 2016 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2016 | IBRD-73800 | Int Charges | 224,887.66 |
Sep 15, 2016 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2017 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2014 | IBRD-73800 | Int Charges | 168.71 |
Mar 15, 2014 | IBRD-73800 | Int Charges | 303.42 |
Mar 15, 2014 | IBRD-73800 | Int Charges | 1,413.61 |
Mar 15, 2014 | IBRD-73800 | Int Charges | 154,763.25 |
Jul 11, 2014 | IBRD-73800 | Loan Disb | -787,716.06 |
Mar 15, 2015 | IBRD-73800 | Int Charges | 2,995.49 |
Mar 15, 2015 | IBRD-73800 | Int Charges | 127,306.88 |
Mar 15, 2015 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2014 | IBRD-73800 | Loan Repay | 1,900,786.90 |
Sep 15, 2014 | IBRD-73800 | Int Charges | 0.01 |
Sep 15, 2014 | IBRD-73800 | Int Charges | 3,089.09 |
Sep 15, 2014 | IBRD-73800 | Int Charges | 140,956.05 |
Dec 23, 2014 | IBRD-73800 | Loan Disb | -1,480.43 |
Dec 23, 2014 | IBRD-73800 | Loan Cancel | 4,473,300.00 |
Dec 23, 2014 | IBRD-73800 | Loan Disb | -54,239.89 |
Aug 12, 2013 | IBRD-73800 | Loan Disb | 724,507.94 |
Sep 15, 2013 | IBRD-73800 | Int Charges | 2,246.04 |
Sep 15, 2013 | IBRD-73800 | Int Charges | 169,576.02 |
Sep 15, 2021 | IBRD-73800 | Int Charges | 42,610.18 |
Sep 15, 2021 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Jul 1, 2014 | IBRD-73800 | Loan Disb | -2,489,606.20 |
Sep 15, 2022 | IBRD-73800 | Int Charges | 106,861.38 |
Sep 15, 2022 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2023 | IBRD-73800 | Int Charges | 307,560.60 |
Sep 15, 2023 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2023 | IBRD-73800 | Int Charges | 272,511.38 |
Mar 15, 2023 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Mar 15, 2024 | IBRD-73800 | Int Charges | 288,692.50 |
Mar 15, 2024 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Jun 1, 2006 | IBRD-73800 | Loan Commitment | 50,000,000.00 |
Mar 15, 2017 | IBRD-73800 | Int Charges | 271,744.80 |
Mar 15, 2018 | IBRD-73800 | Int Charges | 277,146.75 |
Mar 15, 2018 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2017 | IBRD-73800 | Int Charges | 293,098.16 |
Sep 15, 2017 | IBRD-73800 | Loan Repay | 1,898,362.20 |
Sep 15, 2018 | IBRD-73800 | Int Charges | 395,397.12 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2013-12-11 |
Progress towards achievement of PDO | Satisfactory | 2013-12-11 |
Financial Management | Satisfactory | 2013-12-11 |
Monitoring and Evaluation | Satisfactory | 2013-12-11 |
Procurement | Satisfactory | 2013-12-11 |
Project Management | Satisfactory | 2013-12-11 |
Overall Safeguards Rating | Satisfactory | 2013-12-11 |
Overall Implementation Progress (IP) | Satisfactory | 2013-12-11 |
Overall Safeguards Rating | Satisfactory | 2013-12-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-21-2014 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 06-02-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Evidence, via reports from independent technical and social audit teams, of improved effectiveness and financial and technical viability of urban services provided by participating TMAs | Value | TMAs in need of improved and well structured manag | Findings of the two ID assessments undertaken at M | Improved TMA capacity for provision of effective a |
Date | November 27, 2006 | November 21, 2013 | November 30, 2013 | |
Comment |
Evidence of rising levels of satisfaction among key stakeholder groups with respect to services targeted under the project and improvement in selected service delivery indicators. | Value | Refer intermediate outcome indicators. | Results from the independent third-party survey of | Improvements in TMAs’ key service delivery indicat |
Date | November 27, 2006 | November 21, 2013 | November 30, 2013 | |
Comment |
Evidence of GoPunjab's improved capacity to monitor TMA performance. | Value | GoPunjab currently has no ability to systematicall | Integrated web-based Performance Management System | Data Networking and Performance Monitoring System |
Date | November 27, 2006 | November 21, 2013 | November 30, 2013 | |
Comment |
Evidence of GoPunjab's improved capacity to manage cultural heritage assets | Value | Overlapping institutional mandates and lack of coo | The Walled City of Lahore Authority (WCLA) has bee | GoPunjab will have a clear and effective instituti |
Date | November 27, 2006 | November 21, 2013 | November 30, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of households connected with water supply system | Value | 40% (average of 11 TMAs with PMSIP water supply su | 53% (average of 11 TMAs with PMSIP water supply | 59% |
Date | November 27, 2006 | October 31, 2013 | November 30, 2013 | |
Comment | Baseline and target values updated to 11 TMAs. |
% of solid waste disposed per day at landfill site | Value | 0 (average of 6 TMAs with landfill sites developed | 74% (average of 6 TMAs with landfill sites develop | 70% |
Date | November 27, 2006 | October 31, 2013 | November 30, 2013 | |
Comment | No landfill site developed under the project was operating in partner TMAs. |
% of street lights working | Value | 70% (average of 105 TMAs) | 73% (Average of 105 TMAs) | 75% |
Date | November 27, 2006 | October 31, 2013 | November 30, 2013 | |
Comment |
Number of TMAs Having 90% complaint resolution efficiency | Value | 20.00 | 81.00 | 75.00 |
Date | August 2, 2010 | October 31, 2013 | November 30, 2013 | |
Comment | This indicator has been added following project restructuring | This indicator has been added following project restructuring |
Number of TMAs generating monthly Performance Management System (PMS) reports (atleast 9 reports in a year) | Value | 12.00 | 81.00 | 40.00 |
Date | August 2, 2010 | October 31, 2013 | November 30, 2013 | |
Comment | This indicator has been added following project restructuring | This indicator has been added following project restructuring |
Number of TMAs staff trained in IT, planning, O&M etc. | Value | 1000.00 | 3137.00 | 2300.00 |
Date | August 2, 2010 | October 31, 2013 | November 30, 2013 | |
Comment | This indicator has been added following project restructuring | This indicator has been added following project restructuring |
Number of TMAs having updated GIS based service maps | Value | 30.00 | 104.00 | 100.00 |
Date | August 2, 2010 | October 31, 2013 | November 30, 2013 | |
Comment | This indicator has been added following project restructuring | This indicator has been added following project restructuring |
Number of TMAs having updated plans | Value | 20.00 | 104.00 | 75.00 |
Date | August 2, 2010 | October 31, 2013 | November 30, 2013 | |
Comment | This indicator has been added following project restructuring | This indicator has been added following project restructuring |
Number of TMAs using FMS generated reports for the annual local fund audit. | Value | 0.00 | 102.00 | 10.00 |
Date | August 2, 2010 | October 31, 2013 | November 30, 2013 | |
Comment | This indicator has been added following project restructuring | This indicator has been added following project restructuring.CFMS reports are being generated by 102 TMAs. Office of DG Audit ispreparing for system audit, once Account Rules, Budget Rules, and Rules of Business under PLGA 2013 are operationalized. |