Financier | Commitments |
---|---|
Local Govts. (Prov., District, City) of Borrowing Country | 262.35 |
GLOBAL ENVIRONMENT - Associated IBRD Fund | 165.00 |
Global Environment Facility (GEF) | 10.00 |
P084003
Closed
Sing Cho
N/A
January 6, 2004
(as of board presentation)
June 8, 2004
July 5, 2004
US$ 437.35 million
N/A
2004
US$ 10.00 million
A
Not Applicable
December 31, 2011
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Local Govts. (Prov., District, City) of Borrowing Country | 262.35 |
GLOBAL ENVIRONMENT - Associated IBRD Fund | 165.00 |
Global Environment Facility (GEF) | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 10.00 |
Total Project Cost** | 437.35 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Unsatisfactory | 2012-01-10 |
Summary Global Objective Rating | Moderately Satisfactory | 2012-01-10 |
Project Management | Moderately Satisfactory | 2012-01-10 |
Financial Management | Moderately Satisfactory | 2012-01-10 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-01-10 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-01-10 |
Procurement | Moderately Unsatisfactory | 2012-01-10 |
Counterpart Funding | Satisfactory | 2012-01-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2012 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |