Transparency and Accountability Capacity Building Project

Abstract*

The project development objective (PDO) of the Transparency and Accountability Capacity Development Project for Cameroon is to contribute: (i) to enhance transparency and efficiency in the public finance management (PFM) of Cameroon; and (ii) to strengthen accountability in the use of public resource in Cameroon. The project will play a key role in Cameroon's acceleration of the pace toward a more transparent and orderly PFM and, in addition, more...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective (PDO) is to contribute (i) to enhance transparency and efficiency in public financial management, and (ii) to strengthen accountability in the use of public resource. The project will play a key role in Cameroon in accelerating the pace toward a more orderly and open PFM and thus more efficient service delivery.

Key Details

Project Details

  • P084160

  • Closed

  • Alexandre Arrobbio

  • N/A

  • Cameroon

  • June 13, 2007

  • (as of board presentation)

    June 24, 2008

  • June 5, 2009

  • US$ 5.60 million

  • C

  • Not Applicable

  • December 31, 2012

  • BANK APPROVED

  • March 26, 2015

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 5.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 5.60
IBRD + IDA Commitment 5.60
Lending Instrument
Grant Amount N/A
Total Project Cost** 5.60

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 15, 2016 IDA-44790 Int Charges 99.98
Aug 15, 2016 IDA-44790 Int Charges 99.98
Feb 15, 2016 IDA-44790 Int Charges 12,552.76
Feb 15, 2016 IDA-44790 Int Charges 12,552.76
Feb 15, 2016 IDA-44790 Int Charges 45.84
Feb 15, 2016 IDA-44790 Int Charges 45.84
Sep 11, 2020 IDA-44790 Int Charges 12,105.84
Aug 15, 2020 IDA-44790 Loan Repay 173.29
Mar 12, 2020 IDA-44790 Int Charges 12,006.73
Mar 12, 2020 IDA-44790 Int Charges 12,006.73
Mar 12, 2020 IDA-44790 Int Charges 453.82
Mar 12, 2020 IDA-44790 Int Charges 453.82
Mar 12, 2020 IDA-44790 Loan Repay 33,008.11
Mar 12, 2020 IDA-44790 Int Charges 17.19
Mar 12, 2020 IDA-44790 Int Charges 17.19
Sep 10, 2019 IDA-44790 Int Charges 232.44
Sep 10, 2019 IDA-44790 Int Charges 232.44
Sep 10, 2019 IDA-44790 Loan Repay 32,606.65
Sep 10, 2019 IDA-44790 Int Charges 13.41
Sep 10, 2019 IDA-44790 Int Charges 13.41
Sep 10, 2019 IDA-44790 Int Charges 11,534.66
Sep 10, 2019 IDA-44790 Int Charges 11,534.66
Mar 5, 2019 IDA-44790 Int Charges 15.06
Mar 5, 2019 IDA-44790 Int Charges 15.06
Mar 5, 2019 IDA-44790 Loan Repay 32,677.44
Mar 5, 2019 IDA-44790 Int Charges 12,069.93
Mar 5, 2019 IDA-44790 Int Charges 12,069.93
Feb 15, 2019 IDA-44790 Loan Repay 468.80
Aug 15, 2018 IDA-44790 Loan Repay 293.24
Sep 7, 2018 IDA-44790 Int Charges 12,500.62
Aug 29, 2022 IDA-44790 Int Charges 9,614.33
Aug 29, 2022 IDA-44790 Int Charges 508.93
Aug 29, 2022 IDA-44790 Int Charges 508.93
Aug 29, 2022 IDA-44790 Loan Repay 31,000.60
Aug 29, 2022 IDA-44790 Int Charges 19.37
Aug 29, 2022 IDA-44790 Int Charges 19.37
Mar 15, 2022 IDA-44790 Loan Repay 32,843.34
Mar 15, 2022 IDA-44790 Int Charges 438.90
Mar 15, 2022 IDA-44790 Int Charges 438.90
Mar 15, 2022 IDA-44790 Int Charges 14.37
Mar 15, 2022 IDA-44790 Int Charges 14.37
Mar 15, 2022 IDA-44790 Int Charges 10,914.94
Mar 15, 2022 IDA-44790 Int Charges 10,914.94
Sep 6, 2021 IDA-44790 Int Charges 200.63
Sep 6, 2021 IDA-44790 Int Charges 200.63
Sep 6, 2021 IDA-44790 Int Charges 6.09
Sep 6, 2021 IDA-44790 Int Charges 6.09
Sep 6, 2021 IDA-44790 Int Charges 11,492.95
Sep 6, 2021 IDA-44790 Int Charges 11,492.95
Sep 6, 2021 IDA-44790 Loan Repay 33,888.88
Feb 15, 2021 IDA-44790 Loan Repay 1,398.68
Feb 24, 2021 IDA-44790 Loan Repay 32,997.58
Feb 24, 2021 IDA-44790 Int Charges 18.55
Feb 24, 2021 IDA-44790 Int Charges 18.55
Feb 24, 2021 IDA-44790 Int Charges 12,051.38
Feb 24, 2021 IDA-44790 Int Charges 12,051.38
Sep 11, 2020 IDA-44790 Loan Repay 33,453.83
Sep 11, 2020 IDA-44790 Int Charges 18.92
Sep 11, 2020 IDA-44790 Int Charges 18.92
Sep 11, 2020 IDA-44790 Int Charges 12,105.84
Jun 24, 2008 IDA-44790 Loan Commitment 15,000,000.00
Feb 15, 2024 IDA-44790 Int Charges 10,178.60
Feb 15, 2024 IDA-44790 Int Charges 10,178.60
Feb 15, 2024 IDA-44790 Loan Repay 425.68
Feb 15, 2024 IDA-44790 Loan Repay 31,072.09
Aug 20, 2024 IDA-44790 Int Charges 10,555.27
Aug 20, 2024 IDA-44790 Int Charges 10,555.27
Aug 20, 2024 IDA-44790 Int Charges 338.97
Aug 20, 2024 IDA-44790 Int Charges 338.97
Aug 20, 2024 IDA-44790 Loan Repay 31,985.66
Aug 15, 2023 IDA-44790 Int Charges 0.45
Aug 15, 2023 IDA-44790 Int Charges 0.45
Aug 15, 2023 IDA-44790 Int Charges 10,707.06
Aug 15, 2023 IDA-44790 Int Charges 10,707.06
Aug 15, 2023 IDA-44790 Loan Repay 31,724.69
Aug 15, 2023 IDA-44790 Int Charges 23.13
Aug 15, 2023 IDA-44790 Int Charges 23.13
Mar 20, 2023 IDA-44790 Int Charges 1,112.31
Mar 20, 2023 IDA-44790 Int Charges 1,112.31
Mar 20, 2023 IDA-44790 Loan Repay 31,901.61
Mar 20, 2023 IDA-44790 Int Charges 9.30
Mar 20, 2023 IDA-44790 Int Charges 9.30
Mar 20, 2023 IDA-44790 Int Charges 10,885.95
Mar 20, 2023 IDA-44790 Int Charges 10,885.95
Aug 29, 2022 IDA-44790 Int Charges 9,614.33
Feb 27, 2014 IDA-44790 Int Charges 13,332.59
Feb 27, 2014 IDA-44790 Int Charges 13,332.59
Aug 15, 2013 IDA-44790 Int Charges 14,845.65
Aug 15, 2013 IDA-44790 Int Charges 14,845.65
Aug 15, 2013 IDA-44790 Int Charges 374.50
Aug 15, 2013 IDA-44790 Int Charges 374.50
Aug 15, 2015 IDA-44790 Int Charges 649.42
Aug 15, 2015 IDA-44790 Int Charges 649.42
Aug 15, 2015 IDA-44790 Int Charges 12,487.53
Aug 15, 2015 IDA-44790 Int Charges 12,487.53
Aug 15, 2014 IDA-44790 Int Charges 88.33
Aug 15, 2014 IDA-44790 Int Charges 88.33
Aug 15, 2014 IDA-44790 Int Charges 13,567.67
Aug 15, 2014 IDA-44790 Int Charges 13,567.67
Feb 15, 2015 IDA-44790 Int Charges 79.08
Feb 15, 2015 IDA-44790 Int Charges 79.08
Feb 15, 2015 IDA-44790 Int Charges 11,984.29
Feb 15, 2015 IDA-44790 Int Charges 11,984.29
Feb 15, 2014 IDA-44790 Int Charges 22.25
Feb 15, 2014 IDA-44790 Int Charges 22.25
Jul 11, 2013 IDA-44790 Loan Disb -439,060.94
Sep 27, 2013 IDA-44790 Loan Cancel 1,231,804.60
Sep 7, 2018 IDA-44790 Int Charges 12,500.62
Sep 7, 2018 IDA-44790 Loan Repay 33,038.28
Feb 15, 2018 IDA-44790 Int Charges 446.72
Feb 15, 2018 IDA-44790 Int Charges 446.72
Feb 15, 2018 IDA-44790 Int Charges 12,577.23
Feb 15, 2018 IDA-44790 Int Charges 12,577.23
Aug 15, 2017 IDA-44790 Int Charges 86.07
Aug 15, 2017 IDA-44790 Int Charges 86.07
Aug 15, 2017 IDA-44790 Int Charges 12,480.44
Aug 15, 2017 IDA-44790 Int Charges 12,480.44
Feb 15, 2017 IDA-44790 Int Charges 32.71
Feb 15, 2017 IDA-44790 Int Charges 32.71
Feb 15, 2017 IDA-44790 Int Charges 12,020.83
Feb 15, 2017 IDA-44790 Int Charges 12,020.83
Aug 15, 2016 IDA-44790 Int Charges 12,361.26
Aug 15, 2016 IDA-44790 Int Charges 12,361.26

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2013-04-14
Overall Moderately Ineffective 2013-04-14
Procurement Moderately Satisfactory 2013-04-14
Project Management Unsatisfactory 2013-04-14
Overall Implementation Progress (IP) Unsatisfactory 2013-04-14
Progress towards achievement of PDO Unsatisfactory 2013-04-14
Counterpart Funding Satisfactory 2013-04-14
Monitoring and Evaluation Unsatisfactory 2013-04-14

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2013
OutcomesUnsatisfactory
Risk to Development OutcomeNegligible
Bank PerformanceUnsatisfactory
Borrower PerformanceUnsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-31-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Availability of information on resources received by service delivery units (PEFA PI-23)ValueD (Source: PEFA Report, 2007)C (source: PETS2 report, 2011)B (source PEFA report)
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentNo new PEFA report. However, PETS2 report on 2009 budget was published in Dec. 2010 (NSI website in 2011)Not met. No new PETS exercise was produced in 2010, 2011 or 2012.
  • Public access to key fiscal information (PEFA PI-10)ValueB (Source: PEFA Report, 2007)B (source: Bank assessment)A (Source: PEFA Report)
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentNo new PEFA report. No major change since 2007 in PFM with regards to this indicator.Not met.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Legal and regulatory texts to enforce the new Budget Law are signed and effective.ValueApplication texts have not been drafted yet (firstDecree on new budget nomenclature not drafted.Decree on new budget nomenclature including progr
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentPresidential circulars on Budget execution monitoring and 2013 Budget preparation were published in 2012.Not met
  • Completeness of the financial statements (in French, Loi de R#glement) (PI-25 i)ValueD (Source: PEFA Report, 2007)D+ (Source: own assessment)B (Source: PEFA Report)
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentNo new PEFA report. (Assessment based on information provided by experts in the field with regards to LR 2011)Not met
  • Percentage of investment projects which are domestically financed in annual budget compliant with the new project legal and procedures framework.ValueNumber of Projects: 0 percentN/ANumber of Project: >= 20 percent
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentThe new Public Investment Management system are not yet operational and Manual of administrative procedures are not yetcompleted.Therefore there is no data to confirm the compliance of project in 2013 budget.N/A
  • Percentage of contracts above threshold procured through open competition, in selected ministries (Health, Education, Agriculture, Public Works, and Finance). (PI-19 i, modified).Value(To be determined by project effectiveness) In FraN/A100 percent
    DateDecember 31, 2007December 31, 2012December 31, 2012
    CommentNo change. Baseline data at project effectiveness were never produced.No data available.
  • Timeliness of the issue of semi-annual budget reports (PI-24 ii)ValueD (Source: PEFA Report, 2007)D (source: own assessment)B (Source: PEFA Report)
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentNo PEFA report. Semi-annual budget reports are produced, but delay is superior to 8 weeks.Not met.
  • Degree of integration and reconciliation between personnel records and payroll data. (PI-18 i)ValueD (source: PEFA Report, 2007)D+ (source: own assessment)B (source: PEFA Report)
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentNo structural change in using the HR and Payroll databases are effective and systematic yet. D+ indicate the gradual efforts since2005 in cleaning progressively the 2 databases (SIGIPES-ANTILOPES). Merging of the 2 databases is in preparation.Not met
  • Scope of the legislature scrutiny of the annual budget law. (PI-27-i)ValueC (Source: PEFA Report, 2007)C (source: own assessment)B (Source: PEFA Report, 2007)
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentNo indication that value has changed from baseline at Nov. 2012 Parliament session.Not met.
  • Timeliness of the release of semi-annual budget reports on available media (government websites, national newspapers)ValueNo publication of semi-annual budget reports in PMSemi-annual budget reports published in Cameroon TTimeliness: 2 months
    DateJune 30, 2008December 31, 2012December 31, 2012
    CommentSemi-annual 2012 budget report was published in Cameroon Tribune in Sept. 2012. Not available on PM, DGT, MINEPAT or Presidencywebsites.Partially met.
  • Control steps in expeditor chainValue22.0022.008.00
    DateDecember 9, 2006December 31, 2012December 31, 2012
    CommentSource is the PEMFAR report 2006No indication of change.Not met.