Abstract*

The development objectives of the Support to Basic Education Project, are to improve efficiency in the allocation and management of resources, improve the quality of the education services, and reduce inequities in the provision of these services. The Project will pursue a three-fold agenda of action: 1) build the capacity of the Ministry of Primary and Secondary Education to prepare the system for decentralization, in particular, providing support...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The revised project development objective is to improve efficiency, quality and equity in the provision of basic education in theterritory of the Recipient with a view to achieving universal quality primary education by 2015.

Key Details

Project Details

  • P084317

  • Closed

  • Cristina Panasco Santos

  • N/A

  • Congo, Republic of

  • January 23, 2004

  • (as of board presentation)

    September 23, 2004

  • March 25, 2005

  • US$ 35.00 million

  • B

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • March 19, 2014

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA GRANT FOR POST-CONFLICT 20.00
IDA Credit 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 35.00
IBRD + IDA Commitment 35.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 35.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 23, 2004 IDA-H1270 Loan Commitment 20,000,000.00
Jun 9, 2009 IDA-H4870 Loan Commitment 15,000,000.00
Dec 27, 2013 IDA-H4870 Loan Cancel 429,058.80
Jul 2, 2013 IDA-H4870 Loan Disb 1,077,954.60
Dec 27, 2013 IDA-H4870 Loan Disb -149,490.72
Nov 13, 2013 IDA-H4870 Loan Disb -94,350.91
Nov 13, 2013 IDA-H4870 Loan Disb -181,808.53

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2013-06-24
Procurement Satisfactory 2013-06-24
Project Management Moderately Satisfactory 2013-06-24
Monitoring and Evaluation Moderately Satisfactory 2013-06-24
Overall Implementation Progress (IP) Moderately Satisfactory 2013-06-24
Overall Safeguards Rating Moderately Satisfactory 2013-06-24
Counterpart Funding Highly Satisfactory 2013-06-24
Financial Management Satisfactory 2013-06-24

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-31-2014
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-19-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Ratio Administrative Staff/Teaching Staff (Efficiency)Value40.0057.0017.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentThis indicator will not be met.Preliminary data from school year 2011/12.
  • Student Teacher Ratio (Quality)Value92.0057.0056.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentPreliminary data from school year 2011/12.
  • Primary Education Completion Rate (Quality)Value50.0080.0690.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentPreliminary data from school year 2011/12.
  • Gross Enrolement Rate (Equity)Value107.00120.69114.00
    DateMarch 1, 2008May 15, 2013June 30, 2013
    CommentTarget has been exceeded.Preliminary data from school year 2011/12.
  • Girl Boy Ratio of Primary School Enrollment (Equity)Value0.911.060.95
    DateMarch 1, 2007May 15, 2013June 30, 2013
    CommentTarget has already been exceeded.Preliminary data from school year 2011/12.
  • Primary Repetition Rate (Efficiency)Value30.0022.8720.00
    DateDecember 1, 2004May 15, 2013June 30, 2013
    CommentPreliminary data from school year 2011/12.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions.Value0.00908.00960.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentTarget met at 95%
  • Textbooks in Math and Civic Education at primary level bought and distributedValue0.002600000.002600000.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentTarget met.
  • EMIS OperationalValueNoNoYes
    DateJune 30, 2009May 15, 2013June 30, 2013
    CommentAlthough progress has been made through procurement of software and training of staff, education statistics are produced with ayear of delay and there are still issues with their quality.
  • School management committees (CGDC) createdValue0.001694.001700.00
    DateJune 30, 2009May 15, 2013June 30, 2013
    CommentThe target has been almost fully met.
  • CGDCs having a school development planValue0.00100.00100.00
    DateJune 30, 2009May 15, 2013June 30, 2013
    CommentThe target was already met.
  • School improvement plans carried outValue0.00270.00150.00
    DateJune 30, 2009May 15, 2013June 30, 2013
    CommentTarget exceed
  • Primary teachers having received in-service trainingValue0.009141.006000.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentTarget has already been exceeded.
  • School directors having received trainingValue0.002548.002000.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentTarget has already been exceeded.
  • Inspectors and pedagogical advisors for primary having received trainingValue0.00945.001000.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    Comment
  • Implementation of the new curricula strategy has started by the end of the projectValueNoYesYes
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentThe strategy is already under implementation.
  • Textbooks in French and Mathematics at junior secondary level, bought and distributedValue0.00340600.00260000.00
    DateMay 15, 2013June 30, 2013
    CommentTarget has already been exceeded.
  • Strategy for social inclusion and schooling for the indigenous children implementedValueNoYesYes
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentThe strategy is already under implementation and a study on its impact is under way.
  • Indigenous children having received pedagogical materials and uniformsValue0.004030.004000.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentTarget has already been exceeded.
  • Suitable system for follow up trained out of school youth is operational and producing timely informationValueNoYesYes
    DateMarch 1, 2004October 19, 2012June 30, 2013
    CommentThe system is on-going.
  • RehabilitatedValue0.00781.00780.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentTarget met.
  • ConstructedValue0.00135.00180.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    CommentCivil works are still on-going and the indicator should approach the target by June 30.
  • Lower secondary teachers having received in-service trainingValue0.001760.002000.00
    DateMarch 1, 2004May 15, 2013June 30, 2013
    Comment
  • The share of education budget allocated to primary level increases from 19% in 2008 to 25% in 2011Value19.0049.6125.00
    DateDecember 31, 2008May 15, 2013June 30, 2013
    CommentPreliminary data from school year 2011/12.
  • The share of education expenditures as total government expenditures increases from 13% in 2008 to 16% in 2011Value13.009.6516.00
    DateDecember 31, 2008October 19, 2012June 30, 2013
    CommentThe previous value was wrongly calculated.
  • The first round of standardized tests is carried out at the end of school year 2010/2011 and continues in following yearsValueNoYesYes
    DateJune 30, 2009May 15, 2013June 30, 2013
    Commentnot applicableThe exercise was completed.
  • The number of autochtone children enrolled in the formal education increases from 2,100 in 2009 to 4,000 at end of projectValue2100.004030.004000.00
    DateJune 30, 2009May 15, 2013June 30, 2013
    CommentTarget has already been exceeded.
  • The number of out-of-school youth aged 14-19 who completed vocational training is 1,600 by end of projectValue0.001423.001600.00
    DateJune 30, 2009October 19, 2012June 30, 2013
    CommentAt present 1,423 youth have started their one-year training program after contracts have been signed with the enterprises
  • The percentage of out of school youth who are working in a new activity 6 months after finishing the programs is at least 50%Value0.0062.1050.00
    DateJune 30, 2009May 15, 2013June 30, 2013
    CommentThis is the result of the program undertaken under the original project. 318 youth out of 512 are being employed by theenterprisesthat have trained them.
  • Regularity of annual statistics production with key sector indicatorsValueNoYesYes
    DateJuly 22, 2011May 15, 2013June 30, 2013
    Commentthis is a new indicator being introducedAnnual statistics have been produced but often delayed in terms of their production and publication
  • A sectoral strategy for EFA-FTI approvedValuenoYesYes
    DateJuly 22, 2011May 15, 2013June 30, 2013
    CommentNew indicator being introducedTarget already met.
  • Number of additional qualified primary teachers resulting from project interventions.Value0.001697.001697.00
    DateJune 30, 2008May 15, 2013June 30, 2013
    CommentThe baseline and results presented in this ISR refer only to the period after restructuring (May 2012 onwards), and according tothe revise results framework in the restructuring paper.Target already met.