Financier | Commitments |
---|---|
Bilateral Agencies (unidentified) | 5.90 |
Borrower/Recipient | 0.74 |
Local Sources of Borrowing Country | 8.57 |
Global Environment Facility (GEF) | 4.55 |
P084605
Closed
Ruxandra Floroiu
N/A
Western Balkans
March 12, 2004
(as of board presentation)
May 27, 2008
July 1, 2008
US$ 19.76 million
N/A
2008
US$ 10.45 million
B
Not Applicable
December 31, 2012
BANK APPROVED
June 27, 2013
Financier | Commitments |
---|---|
Bilateral Agencies (unidentified) | 5.90 |
Borrower/Recipient | 0.74 |
Local Sources of Borrowing Country | 8.57 |
Global Environment Facility (GEF) | 4.55 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 10.45 |
Total Project Cost** | 19.76 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2012-12-25 |
Procurement | Moderately Satisfactory | 2012-12-25 |
Summary Global Objective Rating | Moderately Satisfactory | 2012-12-25 |
Counterpart Funding | Moderately Satisfactory | 2012-12-25 |
Financial Management | Satisfactory | 2012-12-25 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-12-25 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-12-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2013 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 06-10-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Operational costs of maintaining and participating in SLC, lakewide database, and Working Groups are included in Governments' budgets a year before project close. | Value | Not included. | Government of Montenegro has allocated its share o | Operational costs of maintaining and participating |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | The SLC held its 5th meeting in June 7, 2012.The consultants that will assist the governments prepare a bilateral bindingagreementwith specific focus on the joint SLC and WGshave been hired and it is expected that the draft agreement is discussed andagreed uponat the National Conference on Lake Shkodra in September 2012. | The draft Legal Binding Agreement on December 2012 will discuss the SLC, WGs sustainability before project closing. |
Predictive hydrological model of lake completed and being used to analyze likely impacts of policies and proposed investments. | Value | Predictive hydrological model does not exist yet. | Memorandum of Understanding (MOU) on how to jointl | Predictive hydrological model of lake completed an |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | MoEFWA has officially nominated the Albanian representatives who will use the PHM in Albania while the MOU between bothGovernmentsis not signed yet. | Achieved. |
Lake-wide zoning and management plan approved by both governments and being incorporated in to spatial plan updates. | Value | The Lake-wide zoning and management plan does not | The Joint Lake management Strategy will be finaliz | Lake-wide zoning and management plan approved by b |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | The development of Joint Lake Management Strategy including National Fishery Management Plans for each country is on-going. SecondPublic hearing will be held in Montenegro on June 30, 2012. | The Draft Lake-wide zoning and management plans has been finalized and discussed by both Governments. |
Targeted tourism infrastructure renovations and construction completed and attracting visitors. | Value | Targeted tourism infrastructure renovations and co | Targeted tourism infrastructure renovations and co | |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | In Albania stream restoration works in Shiroka was completed by end of May 2012. In Montenegro, general design for reconstructionof the Besac has been completed according to the national legislation; the NO still pending until comments submitted by Bank teamare addressed. Based on general design it is expected that European Delegation in the MNEwill finance restoration works in theamount of 0.48 mil Euro in the first half of 2012. | Completed. |
Reduction in number of fishermen using illegal fishing methods. | Value | Estimated 350 unlicensed fishermen (43% total) and | Unlicensed fishermen not exceeding 20% of total. N | |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | In Montenegro - 17,7 % illegal fishermen registered;In Albania - the number of illegal fishermen observed during June-Decemberis120 or 27% (450 legal, 120 illegal). In Montenegro, there were 103 illegal methods registered during course of one year (2010)InAlbania - 8 cases of illegal fishing were observed during banning period in April-May 2011 and at least 30 cases of illegal fishingwere observed during June-December 2011. | Achieved. |
Socio-economic/attitude surveys indicate increased local understanding of, and engagement in, sustainable tourism and natural resources management. | Value | Survey to be carried out in the first year of the | Socio-economic/attitude surveys indicate increased | |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | The second public awareness campaign that impacts this indicator will be finalized within September 2012. The next survey isplanned for latest May 2012. | Achieved |
Government of Montenegro/KAP owners (Rusal) agreement on preferred solution and joint action plan for hazardous waste dump at KAP site. | Value | Inadequate outdated information on nature and quan | Government of Montenegro/KAP owners (Rusal) agreem | |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | Government of Montenegro will receive a loan from the Bank proposed to reduce the environmental and public risks of selectedindustrial waste disposal sites through investments in environmental control measures and infrastructure for management anddisposal of industrial waste including KAP hazardous waste dump site. Proposed project is in preparation phase and will build onthe findings fromthe Feasibility study and EIA done under LSIEMP. | Achieved |
Sewage collection and wastewater treatment system established at Vranjina village. | Value | Only sanitation in place is largely non-functional | Vranjina: Construction of sewerage System and used | |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | Works are pending on the final approval of the design by the MSTD in line with national legislation | Not achieved. Investment was canceled and funds returned to GEF. |
Area of water buffer vegetation restored in pilot areas to reduce sedimentation and runoff into lake. | Value | 2 degraded sites for restoration identified; no da | Restoration works in 2 streams in Shiroka will be | Area of water buffer vegetation restored in pilot |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | Shiroka stream works will finalized in July 2012; the fire damage coverage is under evaluation; a new proposal to replace the sagecultivation assignment was made to invest in the rehabilitation of a second stream in Shiroka, based on the detailed designpreparedby Shkodra Municipality. | Achieved |
Status of key transboundary indicators of Lake water and ecological quality maintained or improved. | Value | Initial Monitoring Data baseline to be agreed (e.g | The results of physical and chemical analises, con | At baseline or better |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | Basic water quality indicators (BOD, Ammonia, Nitrite, Nitrate, CN, Zn, Pb,Cr,Hg, PAH, PCB) at multiple sampling sites allbelowdetection or within Class 1A water quality parameters. Status of selected transboundary indicators (algal concentrations,PAH/PCBand heavy metals in fish tissues, etc.) not known. | 72 water samples were tested for physic-chemical parameters. The temperature ranged from 14.1-28.2 °C and pH values ranged from8.1to 8.5. The DO values ranged from 6.7 - 9.7 mg\l or 82.3 % - 111 %. The results of conductivity changed from 215-232 μS\m. Theaverage values of NH4-N ranged from 0.025-0.05 mg/L and the levels of NO3-N ranged from 0.18-0.27 mg/L. The average of fecal coliforms was from 101-102 cfu/100 ml in Buna, Zogaj, and Livadhet during June, July, September and October 2011. According to thedegree of total coli forms the water can be classified as good to moderate. The results show that the quality of the Shkodra lakewater is goodaccording to the European Community Standards.According to the physical-chemical analysis water quality of LakeShkodra can be classified as good. According to the microbiological parameters analyzed and EU-Directive for surface waters(Quality of Bathing Water76/160/EEC), Lake Shkodra results with slight pollution, fecal coli forms (100-2000 cfu/100ml) and totalcoli forms (100-500 cfu/100ml). In most cases G-values of the EU-directive on bathing waters for total coli forms and fecal coliforms were met. The cleanest point resulted was Middle lake and the most problematic point regarding both chemical andmicrobiological parameters was Buna, because of the discharging of sewages of the municipality. | The monitoring indicators developed as part of the joint Lake Monitoring Program will continue to provide annually values for lakewater quality as agreed by stakeholders. |
Immediate and longer term threats to lake ecology and water quality are reduced on both sides of the border, through direct investments, information exchange, bilateral planning, and agreements. | Value | Immediate threats: Improperly stored hazardous was | The project has l finalized activities related to | Immediate and longer term threats to lake ecology |
Date | September 29, 2008 | June 8, 2012 | September 30, 2012 | |
Comment | The project has launched and finalized activities related to this indicator. 19 cases of illegal fishing methods were observedduring a survey in April 15-May 31 in Albanian side of the lake which is 97.7 % less than 2006 and 95.7% less than 2010Thenumber of unlicensed fishermen observed is 39 persons, 88.9% less than 2006 and 85%less than 2010. On the Albanian side decreasewith more than 70% in illegal fishing activities and unlicensed fishermen is an indicator of increased awareness in naturalresource management.Through the activities of the Joint Public Awareness Campaigns more than 70% of the community has beeninformed about the cultural,natural and tourist potentials of the lake. | The project has finalized activities related to this indicator in June 2012. . 19 cases of illegal fishing methods were observedduring a survey in April 15-May 31 in Albanian side of the lake which is 97.7 % less than 2006 and 95.7% less than 2010Thenumber of unlicensed fishermen observed is 39 persons, 88.9% less than 2006 and 85%less than 2010. On the Albanian side decreasewith more than 70% in illegal fishing activities and unlicensed fishermen is an indicator of increased awareness in naturalresource management.Through the activities of the Joint Public Awareness Campaigns more than 70% of the community has beeninformed about the cultural,natural and tourist potentials of the lake. |