Hanoi Urban Transport Development Project GEF component

Development Objective

GEF strategic objectives are to promote a shift to more environmentally-sustainable transport modes and urban development plans, and to promote the replication of these approaches in the country and region. Its global environment objective is to lower Hanoi's transport-related greenhouse gas emissions, relative to a business-as-usual scenario.

Key Details

Project Details

  • P085393

  • Closed

  • Van Anh Thi Tran , Jung Oh

  • N/A

  • Viet Nam

  • August 29, 2007

  • (as of board presentation)

    September 11, 2007

  • November 22, 2007

  • US$ 9.80 million

  • A

  • July 15, 2021

  • December 31, 2016

  • BANK APPROVED

  • P083581

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 9.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 9.80
Total Project Cost** 9.80

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2016-12-28
Procurement Moderately Unsatisfactory 2016-12-28
Counterpart Funding Satisfactory 2016-12-28
Summary Global Objective Rating Moderately Satisfactory 2016-12-28
Monitoring and Evaluation Moderately Satisfactory 2016-12-28
Overall Implementation Progress (IP) Moderately Satisfactory 2016-12-28
Financial Management Moderately Satisfactory 2016-12-28

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-30-2018
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency