Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 180.00 |
Borrower/Recipient | 119.57 |
P085593
Closed
Erik A. Bloom
N/A
July 22, 2004
(as of board presentation)
December 13, 2005
October 24, 2006
US$ 299.57 million
N/A
2006
US$ 180.00 million
C
Not Applicable
December 31, 2011
BANK APPROVED
September 28, 2021
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 180.00 |
Borrower/Recipient | 119.57 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 180.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 180.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 299.57 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 13, 2005 | IBRD-73460 | Loan Commitment | 171,000,000.00 |
Dec 13, 2005 | IBRD-73490 | Loan Commitment | 9,000,000.00 |
Dec 1, 2020 | IBRD-73460 | Loan Repay | 228,683.39 |
Dec 1, 2020 | IBRD-73460 | Loan Repay | 2,351,214.20 |
Dec 1, 2020 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2020 | IBRD-73460 | Loan Repay | 2,374,299.00 |
Dec 1, 2020 | IBRD-73460 | Int Charges | 895.11 |
Dec 1, 2020 | IBRD-73460 | Int Charges | 36,443.82 |
Dec 1, 2020 | IBRD-73460 | Int Charges | 59,917.14 |
Dec 1, 2020 | IBRD-73460 | Int Charges | 37,276.44 |
Jun 1, 2020 | IBRD-73460 | Int Charges | 4,981.74 |
Jun 1, 2020 | IBRD-73460 | Int Charges | 72,887.64 |
Jun 1, 2020 | IBRD-73460 | Int Charges | 119,834.28 |
Jun 1, 2020 | IBRD-73460 | Int Charges | 74,553.00 |
Jun 1, 2020 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2020 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Jun 1, 2020 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Jun 1, 2020 | IBRD-73460 | Loan Repay | 2,374,299.00 |
Dec 1, 2019 | IBRD-73460 | Int Charges | 9,686.10 |
Dec 1, 2019 | IBRD-73460 | Int Charges | 109,331.46 |
Dec 1, 2019 | IBRD-73460 | Int Charges | 179,751.42 |
Dec 1, 2019 | IBRD-73460 | Int Charges | 111,829.44 |
Dec 1, 2019 | IBRD-73460 | Loan Repay | 227,138.30 |
Dec 1, 2019 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Dec 1, 2019 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2019 | IBRD-73460 | Loan Repay | 2,374,299.00 |
Jun 1, 2019 | IBRD-73460 | Loan Repay | 1,825,301.90 |
Jun 1, 2019 | IBRD-73460 | Loan Repay | 548,997.20 |
Jun 1, 2019 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Jun 1, 2019 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Jun 1, 2019 | IBRD-73460 | Int Charges | 149,106.00 |
Jun 1, 2019 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2019 | IBRD-73460 | Int Charges | 14,447.34 |
Jun 1, 2019 | IBRD-73460 | Int Charges | 145,775.28 |
Jun 1, 2019 | IBRD-73460 | Int Charges | 239,668.56 |
Dec 1, 2018 | IBRD-73460 | Int Charges | 299,585.70 |
Dec 1, 2018 | IBRD-73460 | Int Charges | 182,219.10 |
Dec 1, 2018 | IBRD-73460 | Int Charges | 15,724.20 |
Dec 1, 2018 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Dec 1, 2018 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2018 | IBRD-73460 | Loan Repay | 1,690,387.60 |
Dec 1, 2018 | IBRD-73460 | Loan Repay | 683,911.44 |
Dec 1, 2018 | IBRD-73460 | Int Charges | 186,382.44 |
Dec 1, 2018 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2018 | IBRD-73460 | Int Charges | 223,659.00 |
Jun 1, 2018 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2018 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Jun 1, 2018 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Jun 1, 2018 | IBRD-73460 | Loan Repay | 1,559,299.80 |
Jun 1, 2018 | IBRD-73460 | Loan Repay | 814,999.30 |
Jun 1, 2018 | IBRD-73460 | Int Charges | 13,174.56 |
Jun 1, 2018 | IBRD-73460 | Int Charges | 218,662.92 |
Jun 1, 2018 | IBRD-73460 | Int Charges | 359,502.84 |
Dec 1, 2017 | IBRD-73460 | Int Charges | 255,106.80 |
Dec 1, 2017 | IBRD-73460 | Int Charges | 419,419.97 |
Dec 1, 2017 | IBRD-73460 | Int Charges | 260,935.44 |
Dec 1, 2017 | IBRD-73460 | Loan Repay | 227,138.30 |
Dec 1, 2017 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Dec 1, 2017 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2017 | IBRD-73460 | Loan Repay | 1,425,407.10 |
Dec 1, 2017 | IBRD-73460 | Int Charges | 13,429.71 |
Dec 1, 2017 | IBRD-73460 | Loan Repay | 948,891.94 |
Jun 1, 2017 | IBRD-73460 | Int Charges | 14,159.19 |
Jun 1, 2017 | IBRD-73460 | Int Charges | 291,550.56 |
Jun 1, 2017 | IBRD-73460 | Int Charges | 479,337.12 |
Jun 1, 2017 | IBRD-73460 | Int Charges | 298,211.94 |
Jun 1, 2017 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2017 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Jun 1, 2017 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Jun 1, 2017 | IBRD-73460 | Loan Repay | 1,291,040.20 |
Jun 1, 2017 | IBRD-73460 | Loan Repay | 1,083,258.80 |
Jun 1, 2016 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2016 | IBRD-73460 | Int Charges | 10,398.65 |
Jun 1, 2016 | IBRD-73460 | Int Charges | 364,438.25 |
Jun 1, 2016 | IBRD-73460 | Int Charges | 599,171.30 |
Jun 1, 2016 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Jun 1, 2016 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Jun 1, 2016 | IBRD-73460 | Loan Repay | 1,027,525.80 |
Jun 1, 2016 | IBRD-73460 | Loan Repay | 1,346,773.20 |
Dec 1, 2016 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Dec 1, 2016 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2016 | IBRD-73460 | Loan Repay | 1,158,770.80 |
Dec 1, 2016 | IBRD-73460 | Int Charges | 539,254.20 |
Dec 1, 2016 | IBRD-73460 | Int Charges | 335,488.44 |
Dec 1, 2016 | IBRD-73460 | Loan Repay | 227,138.30 |
Dec 1, 2016 | IBRD-73460 | Loan Repay | 1,215,528.40 |
Jun 1, 2016 | IBRD-73460 | Int Charges | 372,764.94 |
Dec 1, 2016 | IBRD-73460 | Int Charges | 327,994.38 |
Dec 1, 2016 | IBRD-73460 | Int Charges | 12,791.31 |
Dec 1, 2015 | IBRD-73460 | Int Charges | 8,514.81 |
Dec 1, 2015 | IBRD-73460 | Int Charges | 400,882.10 |
Dec 1, 2015 | IBRD-73460 | Int Charges | 659,088.56 |
Dec 1, 2015 | IBRD-73460 | Int Charges | 410,041.44 |
Dec 1, 2015 | IBRD-73460 | Loan Repay | 227,138.30 |
Dec 1, 2015 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Dec 1, 2015 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2015 | IBRD-73460 | Loan Repay | 2,374,299.00 |
Jun 1, 2015 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Jun 1, 2015 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Jun 1, 2015 | IBRD-73460 | Loan Repay | 762,652.80 |
Jun 1, 2015 | IBRD-73460 | Int Charges | 7,996.74 |
Jun 1, 2015 | IBRD-73460 | Int Charges | 437,325.84 |
Jun 1, 2015 | IBRD-73460 | Int Charges | 719,005.70 |
Jun 1, 2015 | IBRD-73460 | Int Charges | 447,317.94 |
Jun 1, 2015 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2015 | IBRD-73460 | Loan Repay | 1,611,646.20 |
Jun 1, 2014 | IBRD-73460 | Int Charges | 9,650.52 |
Jun 1, 2014 | IBRD-73460 | Int Charges | 510,213.56 |
Jun 1, 2014 | IBRD-73460 | Int Charges | 838,839.94 |
Jun 1, 2014 | IBRD-73460 | Int Charges | 521,870.94 |
Jun 1, 2014 | IBRD-73460 | Loan Repay | 227,138.30 |
Jun 1, 2014 | IBRD-73460 | Int Charges | 0.01 |
Jun 1, 2014 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Jun 1, 2014 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Jun 1, 2014 | IBRD-73460 | Loan Repay | 493,724.03 |
Jun 1, 2014 | IBRD-73460 | Loan Repay | 1,880,575.00 |
Dec 1, 2013 | IBRD-73460 | Int Charges | 11,609.19 |
Dec 1, 2013 | IBRD-73460 | Int Charges | 546,657.40 |
Dec 1, 2013 | IBRD-73460 | Int Charges | 898,757.10 |
Dec 1, 2013 | IBRD-73460 | Int Charges | 559,147.44 |
Dec 1, 2013 | IBRD-73460 | Loan Repay | 358,127.94 |
Dec 1, 2013 | IBRD-73460 | Loan Repay | 2,016,171.10 |
Dec 1, 2013 | IBRD-73460 | Loan Repay | 227,138.30 |
Dec 1, 2013 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Dec 1, 2013 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2014 | IBRD-73460 | Int Charges | 8,560.20 |
Dec 1, 2014 | IBRD-73460 | Int Charges | 473,769.72 |
Dec 1, 2014 | IBRD-73460 | Int Charges | 778,922.80 |
Dec 1, 2014 | IBRD-73460 | Int Charges | 484,594.44 |
Dec 1, 2014 | IBRD-73460 | Loan Repay | 227,138.30 |
Dec 1, 2014 | IBRD-73460 | Loan Repay | 2,351,214.50 |
Dec 1, 2014 | IBRD-73460 | Loan Repay | 3,631,341.80 |
Dec 1, 2014 | IBRD-73460 | Loan Repay | 2,374,299.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Highly Satisfactory | 2011-12-28 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-12-28 |
Progress towards achievement of PDO | Moderately Satisfactory | 2011-12-28 |
Procurement | Moderately Satisfactory | 2011-12-28 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2011-12-28 |
Financial Management | Moderately Satisfactory | 2011-12-28 |
Project Management | Moderately Satisfactory | 2011-12-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2012 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 03-20-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of graduates from tertiary education in Mexico | Value | 296650.00 | 455000.00 | 478000.00 |
Date | October 1, 2003 | December 13, 2011 | December 31, 2011 | |
Comment | For the 2002-2003 academic year. Taken from the PAD and based on current information. | For the 2009-2010 academic year. Based on official government statistics. | This is an adjusted target for the end of Phase I. |
Share of 18-24 year-old students in tertiary education from households classified at the two lowest quintiles of the income distribution | Value | 10.00 | 20.60 | 20.00 |
Date | October 1, 2003 | December 13, 2011 | December 31, 2011 | |
Comment | This is a revised baseline value based on currently available data. | Updated estimate, based on latest ENIGH survey. Subject to further revision for the ICR using data and methodology. | This is an adjusted target for the end of the project. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of students with income less than 1 minimum salary | Value | 17.00 | 18.80 | 20.00 |
Date | October 1, 2003 | December 13, 2011 | December 31, 2011 | |
Comment | This is based on the methodology and data used in the past. It is subject to update in the ICR. |
Percentage of students with income less than 2 minimum salaries | Value | 42.50 | 40.20 | 40.00 |
Date | October 1, 2003 | December 13, 2011 | December 31, 2011 | |
Comment | This is based on the methodology and data used in the past. It is subject to update in the ICR. |
Percentage of students with income less than 3 minimum salaries | Value | 33.50 | 31.00 | 33.00 |
Date | October 1, 2003 | December 13, 2011 | December 31, 2011 | |
Comment | This is based on the methodology and data used in the past. It is subject to update in the ICR. |
Percentage of students with income less than 4 minimum salaries | Value | 7.00 | 10.00 | 7.00 |
Date | October 1, 2003 | December 13, 2011 | December 31, 2011 | |
Comment | This is based on the methodology and data used in the past. It is subject to update in the ICR. |
Percentage of beneficiaries that were in the OPORTUNIDADES program during upper secondary education | Value | 5.20 | 17.87 | 20.00 |
Date | October 1, 2003 | December 13, 2011 | December 31, 2011 | |
Comment | This is the revised target. |
Percentage of female beneficiaries | Value | 54.00 | 56.71 | 56.00 |
Date | September 1, 2004 | December 13, 2011 | December 31, 2011 | |
Comment |
Percentage of indigenous beneficiaries | Value | 6.00 | 12.55 | 10.00 |
Date | September 1, 2004 | December 13, 2011 | December 30, 2011 | |
Comment | This is a revised baseline value based on revised data. |
Number of studies per year | Value | 0.00 | 3.00 | 3.00 |
Date | September 1, 2006 | December 13, 2011 | December 31, 2011 | |
Comment | This is an adjusted target. Cumulative value. |
Number of beneficiaries (Pathways-ANUIES) | Value | 0.00 | 12601.00 | 10000.00 |
Date | September 1, 2008 | December 13, 2011 | December 31, 2011 | |
Comment | No baseline in the original PAD. However since the program restarted with Bank support, the baseline was set at 0. | Preliminary numbers by ANUIES | This is an adjusted final value target. |
Change in Retention Rate | Value | 0.00 | 20.00 | 20.00 |
Date | November 15, 2006 | December 13, 2011 | December 31, 2011 | |
Comment | This is value without the project | Preliminary numbers by ANUIES. | This is an adjusted final value target. |
Average change in GPA of Beneficiaries (scale from 1 to 10) | Value | 0.00 | 0.04 | 0.30 |
Date | November 15, 2005 | December 13, 2011 | December 31, 2011 | |
Comment | This is value without the project | Preliminary numbers by ANUIES. | This is an adjusted final value target. |